The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.
There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.
Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.
Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.
The Sizewell C Project View all advice for this project
Enquiry
Good afternoon.
I feel it is appropriate to bring to your attention the attached letter
that has been sent to our County and District Council leaders and senior
officers, as well as relevant departments in central Government.
Not only has EDFE failed dismally to provide cogent information for us
to meaningfully respond to their consultations at Stage 1 and 2, but the
Councils' Task Group have clearly been discussing some of the most
important issues that will affect the local population in camera. They
are unwilling to share any of the topics discussed or possible outcomes.
Allied to what is now recognised will be a head-on clash between the
building of Sizewell C and the onshore infrastructure for the Scottish
Power Renewables (SPR) windfarms East Anglia ONE north and TWO, we are
very concerned.
SPR are being equally secretive concerning the release of any useful
information, to permit potentially affected residents to effectively
respond to their latest Consultation Stage 3.5. See the Parish Council
notice that Middleton has circulated, also attached.
East Suffolk is already on the verge of being overburdened with the
support of existing major infrastructure that currently overloads our
local roads (particularly the B1122) on a regular basis to the detriment
of everyday life and livelihood. Yet the two power companies are
attempting to simply ride roughshod over us in their quest to build even
more using existing roads - in order to save them expense? In the long
run, they will each get in each others' way and cause both projects to
lose time - and that would be more expensive!
Kind regards,
Cllr Roy Dowding
Middleton Parish Council
On behalf of the B1122 Action Group
Advice given
Dear Sir,
Thank you for your email and apologies for the delayed reply.
As the project has not yet been submitted to the Planning Inspectorate
(the Inspectorate), the Inspectorate has no formal powers to intervene
on consultees’ behalf and therefore I would encourage you to contact the
developer directly to make your concerns heard as they have a statutory
duty to take your views into account.
Your comments sent to local authorities (LA) should be considered when
the LA’s provide Adequacy of Consultation responses to the Inspectorate
on whether the Applicant has fulfilled its consultation duties.
The Inspectorate can also consider your comments in addition to the
statutorily required Acceptance tests when making the decision about
whether or not to accept the application under section 55 of the
Planning Act 2008. It will be for the decision maker (the Inspectorate
on behalf of the Secretary of State) to decide the weight to give to the
views expressed in your comments based on the individual facts of the
case.
If the application is accepted for examination you will have the
opportunity to make representations about the merits of the application
to an appointed Examining Authority at the appropriate time.
For information, please see link below to Advice Note 8 which sets out
an overview of the nationally significant infrastructure planning
process for members of the public and others.
attachment 1
A copy of your email and attachments and this response will be published
to the project webpages.
Yours faithfully