A list of the upcoming events and deadlines for all applications that are in the examination stage is below. If you are interested in a particular application the exam timetable view on the relevant project page will show a full history.
There is an alternative calendar based view (not fully accessible) of the same information.
January 2025
February 2025
March 2025
April 2025
May 2025
June 2025
Event Date | Project | Description |
---|---|---|
January 2025 | ||
06 January 2025 | Dogger Bank South Offshore Wind Farms | Pre-Exam Procedural Deadline C Deadline for receipt by the ExA of: - Responses to the updated Rule 6 letter including written submissions on the updated draft Examination Timetable - Requests to be heard orally at the resumed Preliminary Meeting including which agenda items you wish to speak on, points you wish to make and why these need to be made orally rather than in writing - Requests to participate in Compulsory Acquisition Hearing 1 on Tuesday 14 January 2025 - Requests to participate in Issue Specific Hearing 1 (ISH1) on Wednesday 15 January 2025 - Requests to participate in ISH2 on Wednesday 15 January 2025 and Thursday 16 January 2025 - Applicants’ suggested draft itinerary for an ASI - Local Impact Reports (LIRs) from Local Authorities |
07 January 2025 | Stonestreet Green Solar | Deadline 2 For receipt by the ExA of: - Comments on Written Representations - Comments on the Local Impact Reports - The Applicant’s revised dDCO - Status of Negotiations / Compulsory Acquisition Schedule - Draft Statements of Common Ground – see Annex D - Statement of Commonality on Statements of Common Ground - Comments on any further information/additional submissions received by Deadline 1 - Any further information requested by the ExA |
08 January 2025 | Byers Gill Solar | Deadline 7a - Requests to be heard orally at the Open Floor Hearing from additional affected persons or additional interested parties - Requests to be heard orally at a Compulsory Acquisition Hearing) from additional affected persons or additional interested parties - Written Representations (WRs) (in accordance with Regulation 13 of the CA Regulations) - Comments on the CA Regulations RRs received by Deadline 6a |
08 January 2025 | H2Teesside | Deadline 5A Deadline for receipt by ExA of: - Comments on Relevant Representations (RRs) received that concern the Applicant’s proposed provision for the CA of additional land - Written Representations (WRs) (including summaries of all WRs exceeding 1500 words) about the proposed provisions from the applicant, additional Affected Person(s) (AP); additional Interested Party (IP); or IPs - Notification of a wish to speak at an Open Floor Hearing (OFH) - Notification from any Additional AP(s) of a wish to speak at CAH 2 (CAH2) - Notification by any Statutory Parties, who is/ are affected as a result of the Applicant’s proposed provision for the CA of additional land, who have not submitted a RR of their wish to be considered as an IP |
10 January 2025 | Five Estuaries Offshore Wind Farm | Deadline 5 Receipt by the ExA of: - Further PADs update from Natural England (clean and tracked) - Completed and signed Statements of Common Ground (SoCG) - Applicant’s updated version of the dDCO (clean and tracked) (if required) - Applicant’s update to the Land Rights Tracker (clean and tracked) - Applicant’s updated Guide to the Application documents (clean and tracked) - Comments on any submissions received at Deadline 4 - Any other submission from the Applicant - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
10 January 2025 | M60/M62/M66 Simister Island | Deadline 5 (D5) For receipt by the ExA of: - Responses to ExQ2 (if required) - The Applicant’s updates – refer to Annex E of the Rule 6 letter - Any further information requested by the ExA under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 - Comments on any further information/ submissions received by Deadline 4 |
10 January 2025 | Oaklands Farm Solar Park | Close of Examination The ExA is under a duty to complete the Examination no later than the end of the period of six months beginning with the day after the close of the Preliminary Meeting. The ExA will provide reasonable notification if it decides to close the Examination before Friday 10 January 2025. |
10 January 2025 | Stonestreet Green Solar | Publication by the ExA of Publication by the ExA of:- The ExA’s First Written Questions (ExQ1) |
10 January 2025 | Byers Gill Solar | Deadline 7 For receipt by the ExA of: - Response to Third Written Questions (if issued) - Comments on the ExA’s commentary on, or schedule of changes to, the draft DCO - Comments on any additional information/submissions received by Deadline 6 - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
13 January 2025 | Outer Dowsing Offshore Wind (Generating Station) | Examining Authority's Further Written Questions (ExQ2) Publication of the Examining Authority's Further Written Questions (ExQ2) (if required) |
13 January 2025 | Tillbridge Solar Project | Time reserved for Hearings and an ASI (if required) Time reserved for Hearings and an ASI:- Issue Specific Hearings (ISH) (if required) - Compulsory Acquisition Hearing 1 (CAH1) (if required) - Open Floor Hearing 2 (OFH2) (if required) - Accompanied Site Inspection (ASI) (for locations, if any, where accompanied access is required on to private land)(if required) |
13 January 2025 | H2Teesside | Deadline 6 Deadline for receipt by ExA of: - Comments on responses to ExQ2 (if required) - Comments on the Applicant’s second update to the Land Rights Tracker (CA/ TP Schedule) - Updated tracking documents, if required - Comments/ Responses to the Applicant Examination Progress Tracker submitted at DL5 |
13 January 2025 | Five Estuaries Offshore Wind Farm | Deadline 5A Receipt by the ExA of: - Written Representations relating to the Proposed Provisions (changes) submitted by the Applicant on 10 October 2024 - Requests to be heard at Open Floor Hearing 1 from parties entitled to make such requests (Alde and Ore Association and Mrs Roscoe) |
13 January 2025 | Five Estuaries Offshore Wind Farm | Registration for the events week commencing 20 January 2025 Registration for the events week commencing 20 January 2025- [To register to take part in any of the events week commencing 20 January 2025 click on this link and complete the form](https://forms.office.com/e/8m1VBURUAS) |
13 January 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - Comments on any additional information/submissions received by Deadline 1 - Comments on the Applicant’s draft suggestions for site inspections - Local Impact Reports (LIR) from relevant local planning authorities - Written Representations (WR) and Summaries of WRs exceeding 1500 words - SoCGs requested by the ExA (see Annex F, section 3) and updated SoCGs submitted at Procedural Deadline A where any substantive updates have been made - Statement of Commonality for all SoCGs - PADs requested by the ExA (see Annex F section 4) which were not submitted at Procedural Deadline A or any updated PADs - The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001)) - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
13 January 2025 | H2Teesside | Compulsory Acquisition Hearing 2 (CAH2) Compulsory Acquisition Hearing 2 (CAH2) |
14 January 2025 | M60/M62/M66 Simister Island | Publication by the ExA 3 Publication by the ExA of:- Report on the Implications for European Sites (RIES) and any associated questions (if required) |
14 January 2025 | Dogger Bank South Offshore Wind Farms | Preliminary Meeting (PM) - Part 2 Preliminary Meeting (PM) - Part 2The resumed Preliminary Meeting (part 2) for the Dogger Bank South Offshore Wind Farms Development Consent Order Application is to be held by virtual means using Microsoft Teams. This meeting will commence at 10:00 on Tuesday 14 January 2025. A livestream of this event will be available. [Please click on this link to view the livestream for this event.](https://www.liveeventstream.online/planning-inspectorate-hearings/dogger-bank-south) |
14 January 2025 | Dogger Bank South Offshore Wind Farms | Compulsory Acquisition Hearing 1 (CAH1) Compulsory Acquisition Hearing 1 (CAH1)Compulsory Acquisition Hearing 1 for the Dogger Bank South Offshore Wind Farms Development Consent Order Application is to be held by virtual means using Microsoft Teams. This hearing will commence at 14:00 on Tuesday 14 January 2025. A livestream of this event will be available. [Please click on this link to view the livestream for this event.](https://www.liveeventstream.online/planning-inspectorate-hearings/dogger-bank-south) |
14 January 2025 | Mona Offshore Wind Farm | Deadline 7 For receipt by the ExA of: - IP’s Closing Statement(s) (if desired, see Appendix F of the Rule 6 letter) - Applicant’s Close of Examination Progress Tracker (see Part 5 of Appendix F of the Rule 6 letter) - Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report (clean and tracked versions) - Final Explanatory Memorandum in clean, tracked and Word versions - Final Schedule of Changes to the dDCO (if required) - Final Statement of Commonality and Final SoCGs - Final BoR and Schedule of changes to BoR - Applicant’s final Land Rights Tracker - Applicant’s final Application Guide in clean and tracked versions - Applicant’s final Schedule of Negotiations and Powers Sought in clean and tracked versions - Applicant’s final planning obligations and commercial side agreements tracking lists (see Part 11 of Appendix F of the Rule 6 letter) - Any final signed and dated section 106 agreements together with CIL compliance schedule - Applicant’s final versions of any application documents updated during the Examination - Comments on any other submissions received at Deadline 6 - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
14 January 2025 | A46 Newark Bypass | The ExA’s Written Questions (ExQ2) Publication by the ExA of:- ExA’s Second Written Questions (ExQ2), if required - Report on the Implications for European Sites (RIES) and any associated questions, if required |
14 January 2025 | Byers Gill Solar | Issue Specific Hearing 8 (ISH8) Issue Specific Hearing 8 (ISH8) |
14 January 2025 | H2Teesside | Issue Specific Hearing 3 (ISH3) Issue Specific Hearing 3 (ISH3) |
15 January 2025 | H2Teesside | Issue Specific Hearing 4 (ISH4) Issue Specific Hearing 4 (ISH4) |
15 January 2025 | Dogger Bank South Offshore Wind Farms | Issue Specific Hearing 1 (ISH1) on the draft Development Consent Order (DCO) Issue Specific Hearing 1 (ISH1) on the draft Development Consent Order (DCO)Issue Specific Hearing 1 (ISH1) on the draft Development Consent Order (DCO) for the Dogger Bank South Offshore Wind Farms Development Consent Order Application is to be held by virtual means using Microsoft Teams. This hearing will commence at 10:00 on Wednesday 15 January 2025. A livestream of this event will be available. [Please click on this link to view the livestream for this event.](https://www.liveeventstream.online/planning-inspectorate-hearings/dogger-bank-south) |
15 January 2025 | Dogger Bank South Offshore Wind Farms | Issue Specific Hearing 2 (ISH2) on the scope of the Proposed Development including construction activities Issue Specific Hearing 2 (ISH2) on the scope of the Proposed Development including construction activitiesIssue Specific Hearing 2 (ISH2) on the scope of the Proposed Development including construction activities for the Dogger Bank South Offshore Wind Farms Development Consent Order Application is to be held by virtual means using Microsoft Teams. This hearing will commence at 14:00 on Wednesday 15 January 2025. A livestream of this event will be available. [Please click on this link to view the livestream for this event.](https://www.liveeventstream.online/planning-inspectorate-hearings/dogger-bank-south) |
15 January 2025 | Byers Gill Solar | Compulsory Acquisition Hearing 2 (CAH2), Issue Specific Hearing 9 (ISH9) and Open Floor Hearing 5 (OFH5) * Compulsory Acquisition Hearing 2 (CAH2) held under Reg 15 - Issue Specific Hearing 9 (ISH9) held under Reg. 14 - Open Floor Hearing 5 (OFH5) held under Reg. 16 All the above hearings will be held for additional APs or IPs as a consequence of the additional land or rights sought arising from Change 1 (if required) |
15 January 2025 | H2Teesside | Open Floor Hearing (OFH) Open Floor Hearing (OFH) |
16 January 2025 | Morgan Offshore Wind Project Generation Assets | Deadline 5 For receipt by the Examining Authority of: - Responses to ExQ2 (if required) - Comments on any other submissions received at Deadline 4 - Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
16 January 2025 | Dogger Bank South Offshore Wind Farms | Continuation of Issue Specific Hearing 2 (ISH2) on the scope of the Proposed Development including construction activities (if required) Continuation of Issue Specific Hearing 2 (ISH2) on the scope of the Proposed Development including construction activities (if required)The continuation of Issue Specific Hearing 2 (ISH2) on the scope of the Proposed Development including construction activities for the Dogger Bank South Offshore Wind Farms Development Consent Order Application is to be held by virtual means using Microsoft Teams. This hearing (if required) will commence at 10:00 on Thursday 16 January 2025. A livestream of this event will be available. [Please click on this link to view the livestream for this event.](https://www.liveeventstream.online/planning-inspectorate-hearings/dogger-bank-south) |
16 January 2025 | Mona Offshore Wind Farm | Close of Examination The ExA is under a duty to complete the Examination of the application by the end of the period of six months |
16 January 2025 | Byers Gill Solar | Time reserved for continuation of ISH8, CAH2, ISH9 and OFH5 (if required) Time reserved for continuation of ISH8, CAH2, ISH9 and OFH5 (if required) |
16 January 2025 | H2Teesside | Publication by the ExA Publication by the ExA of:- The ExA’s schedule of changes to the dDCO (if required) - Report on Implications for European Sites (RIES) (if required) |
16 January 2025 | H2Teesside | Reserve Hearing Date. Reserve Hearing Date. |
17 January 2025 | Cory Decarbonisation Project | Deadline 3 (D3) For receipt by the ExA of: - Responses to ExQ1 - Comments on any further information or submissions received at Deadline 2 - Updated Land Rights Tracker - Updated Examination Tracker - Updated Policy Tracker (if required) - Updated SoCG and Statement of Commonality (as required) - Notification of wish to attend ASI - Updated BoR and Schedule of Changes to the BoR, in clean and tracked versions (if required) - Updated dDCO in clean, tracked and Word versions, schedule of changes to the dDCO and updated Explanatory Memorandum (if required) - Updated Application Guide (Application Document Tracker) (if required) in clean and tracked versions - Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
17 January 2025 | Byers Gill Solar | Deadline 8 For receipt by the ExA of: - Comments on the REIS (if issued) - Comments on responses to Third Written Questions (if required) - Final dDCO to be submitted by the Applicant in the SI template with the SI template validation report - Final Schedule of Changes to the dDCO - Final Explanatory Memorandum (EM) and schedule of changes to Explanatory Memorandum - Final updated BoR and schedule of changes to BoR - Final CA Schedule - Final Status of Negotiations with Statutory Undertakers - Final SoCG - Final SoC - List of matters not agreed where SoCG could not be finalised - Final Guide to the Application - Comments on any further information/submissions received by Deadline 7 - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
17 January 2025 | Byers Gill Solar | Deadline 8a For receipt by the ExA of: - Comments on WRs received at Deadline 7a |
20 January 2025 | Five Estuaries Offshore Wind Farm | Week reserved for third round of hearings and Site Inspection Week reserved for third round of hearings and Site Inspection:- ISH (if required) - CAH3 (if required) - OFH1 (if required) - ASI1 (if required) |
20 January 2025 | North Falls Offshore Wind Farm | Deadline for receipt by the ExA of: - Written submissions on the Examination Procedure, including any submissions about the use of virtual methods - Requests to be heard at an Open-Floor Hearing (OFH1 - Suggested locations for site inspections (accompanied or unaccompanied), including justification, for consideration by the ExA) - Register to attend the Preliminary Meeting and OFH1 in w/c 27 January 2025 - [Please click on this link and complete the form to register](https://forms.office.com/Pages/ResponsePage.aspx?id=mN94WIhvq0iTIpmM5VcIjZ-v4ExxjdxJp25d4wYUsTJUOEpVUFA0RDlITTJMWVZMWURVNFBTTTMzQiQlQCN0PWcu) |
22 January 2025 | Morecambe Offshore Windfarm Generation Assets | Deadline 3 (D3) For receipt by the ExA of: - Responses to ExQ1 - Comments on the Applicant’s further update to the draft DCO and EM - Comments on the progress tracker / Statement of Commonality - Any other updated documents, including the Guide to the Application, and statements from the Applicant deemed necessary following responses at Deadline 2 (if required) - Comments on any other submissions received at Deadline 2 - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
22 January 2025 | H2Teesside | Deadline 6A Deadline for receipt by ExA of: - Written summaries of oral submissions made at any Hearings held during the week commencing 13 January 2025 - Responses to Action Points arising from Hearings held during the week commencing 13 January 2025 - Any other post-hearing submissions requested by the ExA |
23 January 2025 | Byers Gill Solar | Deadline 9 For receipt by the ExA of: - Any further information requested by the ExA |
23 January 2025 | Byers Gill Solar | Close of Examination The ExA is under a duty to complete the Examination of the application by the end of the period of six months |
23 January 2025 | Byers Gill Solar | Deadline 9a For receipt by the ExA of: - Post-hearing submissions including written submissions of oral cases as heard at the hearings held on the 15 – 16 Jan 2025 |
27 January 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001)) - Updated PADs where any substantive changes have been made - Comments on any information. requested/submissions received by Deadline 2 - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
28 January 2025 | North Falls Offshore Wind Farm | Preliminary Meeting Preliminary Meeting (PM)- [Click this link for further information on events](https://www.gov.uk/guidance/nationally-significant-infrastructure-projects-registering-to-speak-at-or-attend-a-nationally-significant-infrastructure-project-event) |
28 January 2025 | Tillbridge Solar Project | Deadline 4 (D4) For receipt by the Examining Authority (ExA) of: - Comments on submissions for Deadline 3 - Post-Hearing Submissions, including written summaries of oral submissions and any documents requested by the ExA - Updated Statement of Common Ground (SoCGs) - Updated Statement of Commonality for all SoCGs - The Applicant's updated documents - Any further information requested by the ExA |
29 January 2025 | North Falls Offshore Wind Farm | Open Floor Hearing Open Floor Hearing (OFH)(if requested at PDA) |
31 January 2025 | M60/M62/M66 Simister Island | Hearing Dates reserved for hearings w/c 27 January 2025:- Further Issue Specific Hearings (ISH)(if required) - Further Compulsory Acquisition Hearing (CAH) (if required) - Further Open Floor Hearings (OFH) (if required) |
31 January 2025 | Stonestreet Green Solar | Deadline 3 For receipt by the ExA of: - Responses to ExQ1 - Interested Parties are required to notify the Examining Authority (ExA) in writing of their wish to take part in an Open Floor Hearing (OFH) or Compulsory Acquisition Hearing (CAH) |
February 2025 | ||
03 February 2025 | Morecambe Offshore Windfarm Generation Assets | Hearings Week commencing Monday 03 February 2025 reserved (if required) for:- Further Issue Specific Hearings (if required) - Open Floor Hearings (of required) |
03 February 2025 | Five Estuaries Offshore Wind Farm | Publication by the ExA of Publication by the ExA of:- The Report on the Implications for European Sites (RIES) - The ExA’s proposed schedule of changes to the dDCO (if required) - The ExA’s Written Questions (ExQ3) (if required) |
03 February 2025 | Outer Dowsing Offshore Wind (Generating Station) | Deadline 4 Deadline for receipt by the ExA of: - Responses to ExQ2 (if published) - Comments on the Applicant’s update to the draft DCO - Comments on the Applicant’s update to the Land Rights Tracker - Applicant’s update to the draft DCO - Applicant’s update to the Land Rights Tracker - Applicant’s update to the Guide to the Application - Applicant’s update to the Statements of Commonality of Statements of Common Ground - Comments on any other submissions received at Deadline 3 - Updated report on the inter-relationship with other infrastructure projects (as described in Annex B) - Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules |
04 February 2025 | A46 Newark Bypass | Deadline 5 For receipt by the ExA of: - Responses to ExQ2, if required - Responses on the (RIES) and any associated questions, if required - Comments on any submissions received at the previous deadline - Responses to any further information requested by the ExA for this deadline From the Applicant - Updated NPS accordance table - Updated application documents tracker - Updated BoR - Updated Schedule of Changes to the BoR - Updated Land Rights Tracker - Updated dDCO - Updated Schedule of Changes to the dDCO - Updated EM - Updated SoCG and SoC - Updated legal agreements, if identified |
04 February 2025 | Tillbridge Solar Project | Publication by the ExA 2 Publication by the Examining Authority (ExA) of:- The ExA's Second Written Questions (ExQ2) |
06 February 2025 | Morgan Offshore Wind Project Generation Assets | REIS and dDCO commentary or schedule of changes publication Publication by the Examining Authority of:- Report on the Implications for European Sites (RIES) and any associated questions (if required) - Examining Authority’s commentary on, or schedule of changes to, the draft Development Consent Order (if required) |
06 February 2025 | Helios Renewable Energy Project | Publication of ExQ1 Publication by the ExA of:- The ExA's First Written Questions (ExQ1) |
06 February 2025 | H2Teesside | Deadline 7 Deadline for receipt by ExA of: - Written summaries of oral submissions at hearings (if required) - Comments on any submissions received at DL5,DL5A,DL6 and DL6A, including any additional AP(s); additional IP(s); or IP(s), as well as any RRs or WRs made pursuant to the Change Request proposed provision - Response to Applicant’s comments on RRs received at DL5A - Comments on the RIES (if required) - Comments on the ExA’s proposed schedule of changes to the dDCO (if required) - Finalised SoCGs - Final Statement of Commonality for SoCG - Final BoR in clean and tracked versions - Final Statement of Reasons in clean and tracked versions - Schedule of Changes to the BoR in clean and tracked versions - Applicant’s final update to the Land Rights Tracker (CA/ TP Schedule) - Final Application Guide (Application Document Tracker), in clean and tracked versions - Final Examination Progress Tracker - Final update to tracking documents, if required - Applicant’s Final Preferred Development Consent Order (DCO) in the SI template validation report and a validated copy of the DCO - Applicant’s preferred DCO in word format - Final Schedule of Changes to the dDCO - Any further information requested by the ExA (if required) |
10 February 2025 | Morgan Offshore Wind Project Generation Assets | Hearings during week commencing 10 February 2024 Reserve dates for:- Further Hearings (if required) |
10 February 2025 | Cory Decarbonisation Project | Hearings Week commencing Monday 10 February 2025 (if required) for:- Issue Specific Hearing 2 (ISH2) draft Development Consent Order (dDCO) - Any further Issue Specific Hearings (If required) - Compulsory Acquisition Hearing 2 (CAH2) (If required) - Open Floor Hearing (OFH2) (if required) - Accompanied Site Inspection (ASI) |
11 February 2025 | Outer Dowsing Offshore Wind (Generating Station) | Hearing Dates Tuesday 11 - Friday 14 February 2025Dates reserved (if required) for: - Any Compulsory Acquisition Hearing - A further Open Floor Hearing (if requested) - Any Issue Specific Hearing - Accompanied Site Inspection |
11 February 2025 | Five Estuaries Offshore Wind Farm | Deadline 6 Receipt by the ExA of: - Post-Hearing submissions including written submissions of oral case as requested by Examining Authority - Further PADs update from Natural England (clean and tracked) - Applicant’s updated version of the dDCO (clean and tracked) (if required) - Applicant’s updated Guide to the Application documents (clean and tracked) - Any SoCG updates, either agreed updating notes or unilateral notes (if required) - Comments on any submissions received at Deadline 5 and Deadline 5A - Any other submission from the Applicant - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
11 February 2025 | M60/M62/M66 Simister Island | Deadline 6(D6) For receipt by the ExA of: - Post-hearing submissions including written submissions of oral cases (if held) - Comments on the RIES (if issued) and responses to any associated questions - Any further information requested by the ExA under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 - Comments on any further information/ submissions received by Deadline 5 |
14 February 2025 | M60/M62/M66 Simister Island | Publication by the ExA 4 Publication by the ExA of:- ExA’s commentary on, or schedule of changes to, the dDCO (if required) |
17 February 2025 | Outer Dowsing Offshore Wind (Generating Station) | Publication of RIES and Examining Authority's preferred draft DCO Issue by the ExA of:- The Report into the Implications for European Sites (RIES) (if required) - The ExA’s preferred draft DCO, proposed schedule of changes, or commentary on the draft DCO (if required) |
17 February 2025 | A46 Newark Bypass | Week reserved for Hearings (if required) Week reserved for Hearings, if required for:- Further Issue Specific Hearing(s) - Further Compulsory Acquisition Hearing(s) - Further Open Floor Hearing(s) |
18 February 2025 | Morecambe Offshore Windfarm Generation Assets | Deadline 4 (D4) For receipt by the ExA of: - Post-hearing submissions including written submissions of oral cases (if required) - Applicant’s mid-Examination Progress Tracker / update to the Statement of Commonality - Mid-Examination Report on interrelationship with other infrastructure projects - Applicant’s update to the draft DCO and EM - Any other updated documents, including the Guide to the Application, and statements from the Applicant deemed necessary following responses at Deadline 3 (if required) - Comments on any other submissions received at Deadline 3 - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
20 February 2025 | H2Teesside | Deadline 8 Deadline for receipt by ExA of: - Comments on any submissions received at DL7 - Updated LIRs (if required) - Closing submissions - Any further information requested by the ExA (if required) |
21 February 2025 | Stonestreet Green Solar | Publication by the ExA of 2 Publication by the ExA of: - The ExA’s final itinerary for the ASI (if required) |
24 February 2025 | Stonestreet Green Solar | Dates reserved for ASIs and hearings ASI and HearingsDates reserved for ASIs and hearings wc 24 February 2024: - Further ISHs (if required) - CAH (if required) - Further OFHs (if required) - ASIs (if required) |
25 February 2025 | Cory Decarbonisation Project | Deadline 4 (D4) For receipt by the ExA of: - Post hearing submissions, including written summaries of oral submissions and any information requested by the ExA at the Hearings w/c 10 February 2025 - Comments on any other information or submissions submitted at Deadline 3 - Updated Land Rights Tracker - Updated Examination Tracker - Updated Policy Tracker (if required) - Updated SoCG and Statement of Commonality (if required) - Updated BoR and Schedule of Changes to the BoR, in clean and tracked versions (if required) - Updated dDCO in clean, tracked and Word versions, schedule of changes to the dDCO and updated Explanatory Memorandum (if required) - Updated Schedule of Changes to the dDCO (if required) - Updated Application Guide (Application Document Tracker) (if required) in clean and tracked versions - Any further information requested by ExA under Rule 17 of the Examination Rules |
25 February 2025 | A46 Newark Bypass | Deadline 6 For receipt by the ExA of: - Written summaries of oral submissions made at the Hearings - Comments on any submissions received at the previous deadline - Responses to any further information requested by ExA From the Applicant - Updated application documents tracker - Updated Land Rights Tracker - Updated dDCO - Updated Schedule of Changes to the dDCO - Updated EM - Updated SoCG and SOC - Updated legal agreements, if identified |
25 February 2025 | Tillbridge Solar Project | Deadline 5 (D5) For Receipt by the Examining Authority (ExA): - Comments on any submissions received by Deadline 4 - Responses to the Examining Authority's Second Written Questions (ExQ2) - Requests to be heard at ISHs in w/c 03 March 2025 (if required) - Requests by Affected Persons (defined in section 59(4( of the Planning Act 2008) to be heard at Compulsory Acquisition Hearing 2 (CAH2) in w/c 03 March 2025 (if required) - Updated Statement of Common Ground (SoCGs) - Updated Statement of Commonality for all SoCGs - Any further information requested by the ExA |
26 February 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - Responses to the ExA’s First Written Questions (ExQ1) - Comments on any information requested/submissions received by Deadline 3 - The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001)) - Updated PADs where any substantive changes have been made - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules |
27 February 2025 | Morgan Offshore Wind Project Generation Assets | Deadline 6 For receipt by the Examining Authority of: - Post-hearing submissions including written submissions of oral cases (if applicable) - Comments on responses to ExQ2 (if provided) - Comments on the RIES (if provided) - Comments on the Examining Authority’s commentary on, or schedule of changes to, the draft Development Consent Order (if provided) - Finalised Statements of Common Ground - Final Statement of Commonality and Close of Examination Progress Tracker - Applicant’s Closing Statement with summary of areas of disagreement - Closing Statements from Interested Parties regarding matters that they have previously raised during the Examination and have not been resolved to their satisfaction (if desired) - Final Report on interrelationship with other infrastructure projects - Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report - Final Guide to the Application - Comments on any further information/ submissions received by Deadline 5 - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
27 February 2025 | M60/M62/M66 Simister Island | Deadline 7 (D7) For receipt by the ExA of: - Summary statements from parties regarding matters that they have previously raised during the Examination and that have not been resolved to their satisfaction - Comments on the ExA’s dDCO/Schedule of changes (if required) - The Applicant’s closing summary statement. - The Applicant’s final updates – refer to Annex E of the Rule 6 letter - Comments on the Deadline 6 submissions and any other information requested by the ExA for Deadline 7 - Any further information requested by the ExA under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 |
27 February 2025 | Morecambe Offshore Windfarm Generation Assets | Pulication by the ExA 3 Publication by the ExA of:- Further Written Questions (ExQ2) (if required) |
28 February 2025 | H2Teesside | Close of Examination The ExA is under a duty to complete the Examination of the application by the end of the period of six months. |
March 2025 | ||
03 March 2025 | Tillbridge Solar Project | Time reserved for Hearings (if required) 2 Time reserved for Hearings (if required)- Issue Specific Hearings (ISHs)(if required) - Compulsory Acquisition Hearing 2 (CAH2) (if required) |
03 March 2025 | Five Estuaries Offshore Wind Farm | Deadline 7 Receipt by the ExA of: - Comments on the Report on the Implication for European Site (RIES) - Comments on the ExA’s proposed schedule of changes to the dDCO (if required) - Responses to the ExA’s ExQ3 (if required) - Applicant's final dDCO (clean and tracked) - Applicant's final dDCO in Word in the SI template - The SI template validation report. - The Applicant’s final version of the Explanatory Memorandum (clean and tracked) - Final Land Rights Tracker (clean and tracked) - Final Book of Reference (BoR) and a schedule of any changes to BoR - Final Statement of Reasons (clean and tracked) - Certified copies of any executed (signed and dated) legal agreements - Applicant’s final Guide to the Application Documents (clean and tracked) - Final PADs update from Natural England (clean and tracked) - Any SoCG updates, either agreed updating notes or unilateral notes (if required) - Comments on any submissions received at Deadline 6 - Any other submission from the Applicant - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
07 March 2025 | M60/M62/M66 Simister Island | Deadline 8 (D8) For receipt by the ExA of: - Any further information requested by the ExA under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules |
10 March 2025 | Morgan Offshore Wind Project Generation Assets | Deadline 7 For receipt by the Examining Authority of: - Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 (if required) |
10 March 2025 | Morgan Offshore Wind Project Generation Assets | Close of Examination The Examining Authority is under a duty to complete the Examination of the application by the end of the period of six months.Please note that the Examining Authority may close the Examination before the end of the six-month period if it is satisfied that all relevant matters have been addressed and discussed. |
10 March 2025 | Five Estuaries Offshore Wind Farm | Deadline 8 Receipt by the ExA of: - Comments on any submissions received at Deadline 7 - Any other submission from the Applicant - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 (if required |
10 March 2025 | Helios Renewable Energy Project | Hearings Time reserved for hearings and Site Inspections w/c 10 March 2025- Issue Specific Hearings (ISH) (if required) - Compulsory Acquisition Hearing 2 (CAH2) (if required) - Open Floor Hearing 2 (OFH2) (if required) - Site Inspections (SI1) (if required) |
11 March 2025 | M60/M62/M66 Simister Island | Close of Examination Close of ExaminationThe ExA must complete the Examination of the application within six months. |
11 March 2025 | Stonestreet Green Solar | Deadline 4 For receipt by the ExA of: - Post-Hearing Submissions, including written summaries of oral submissions and any documents requested by the ExA - Comments on the Applicant’s revised dDCO at Deadline 3 - Comments on any additional submissions received by Deadline 3 - Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
11 March 2025 | Morecambe Offshore Windfarm Generation Assets | Deadline 5 (D5) For receipt by the ExA of: - Responses to ExQ2 (if required) - Any other updated documents, including the Guide to the Application, and statements from the Applicant deemed necessary following responses at Deadline 4 (if required) - Comments on any other submissions received at Deadline 4 - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning(Examination Procedure) Rules 2010 |
11 March 2025 | Cory Decarbonisation Project | Publication by the ExA 2 Publication by the ExA of:- Second Written Questions (ExQ2) (if required) |
11 March 2025 | Tillbridge Solar Project | Publication by the ExA 3 Publication by the Examining Authority of:- The ExA's Third Written Questions (ExQ3) (if required) - The ExA's commentary on, or schedule of changes to, the dDCO - Report on the Implications for European Sites (RIES)(if required) |
12 March 2025 | A46 Newark Bypass | The ExA’s Written Questions (ExQ3) Publication by the ExA of:- ExQ3, if required - ExA’s commentary on, or schedule of changes to, the dDCO |
13 March 2025 | Outer Dowsing Offshore Wind (Generating Station) | Deadline 5 Deadline for receipt by the ExA of: - Post-hearing submissions including written summaries of oral case put at hearings during w/c 10 February 2025 (if held) - Comments on the Applicant’s third update to the draft DCO - Comments on the Applicant’s third update to the Land Rights Tracker - Comments on the Report into the Implications for European Sites (RIES) (if required) - Comments on ExA’s commentary on, or schedule of changes to, the draft DCO (if required) - Completed, signed and dated Statements of Common Ground - Final Statement of Commonality of Statements of Common Ground - Comments on any other submissions received at Deadline 4 - Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules |
17 March 2025 | Five Estuaries Offshore Wind Farm | Close of Examination by the Examining Authority Close of Examination by the Examining AuthorityThe ExA is under a duty to complete the Examination of the application by the end of the period of six months. Please note that the ExA may close the Examination before the end of the six-month period if it is satisfied that all relevant matters have been addressed and discussed. |
20 March 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - Post-Hearing Submissions, comprising written summaries of oral submissions made at the Hearings held on the week commencing 10 March 2025 - Comments on any information requested/submissions received by Deadline 4 - The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001)) - Updated PADs where any substantive changes have been made. - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules |
21 March 2025 | Outer Dowsing Offshore Wind (Generating Station) | Dates reserved for hearings Tuesday 18 - Friday 21 March 2025Dates reserved (if required) for: - Any Compulsory Acquisition Hearing - Any Issue Specific Hearing - Accompanied Site Inspection |
25 March 2025 | Stonestreet Green Solar | Publication by the ExA of 3 Publication by the ExA of:- Report on the Implications for European Sites (RIES) and any associated questions (if required) - The ExA’s Second Written Questions (ExQ2) (if required) |
25 March 2025 | Morecambe Offshore Windfarm Generation Assets | Publication by the ExA 4 Publication by the ExA of:- Report on the Implications for European Sites (RIES) and any associated questions (if required) - ExA’s commentary on, or schedule of changes to, the draft DCO (if required) |
25 March 2025 | Cory Decarbonisation Project | Deadline 5 (D5) For receipt by the ExA of: - Response to ExQ2 (if required) - Comments on any other information or submission submitted at D4 - Updated Land Rights Tracker - Updated Examination Tracker - Updated Policy Tracker (if required) - Updated SoCG and Statement of Commonality (if required) - Updated BoR and Schedule of Changes to the BoR, in clean and tracked versions (if required) - Updated dDCO in clean, tracked and Word versions, schedule of changes to the dDCO and updated Explanatory Memorandum (if required) - Updated Schedule of Changes to the dDCO (if required) - Updated Application Guide (Application Document Tracker) (if required) in clean and tracked versions - Final draft of Planning Obligation - Any further information requested by ExA under Rule 17 of the Examination Rules |
25 March 2025 | A46 Newark Bypass | Deadline 7 For receipt by the ExA of: - Responses to ExQ3, if required - Comments on the ExA’s schedule of changes to the dDCO, if issued - Comments on any submissions received at the previous deadline - Responses to any further information requested by the ExA |
27 March 2025 | Helios Renewable Energy Project | Publication of ExQ2 Publication by the ExA of:- The ExA's Second Written Questions (ExQ2) |
31 March 2025 | Morecambe Offshore Windfarm Generation Assets | Hearings 2 Week commencing Monday 31 March 2025 reserved (if required) for:- Further Hearings (if required) |
April 2025 | ||
01 April 2025 | Tillbridge Solar Project | Deadline 6 (D6) For receipt by the Examining Authority of: - Comments on submissions by Deadline 5 - Post Hearing submissions including written summaries of oral submissions and any documents requested by the ExA (if required) - Responses to the Examining Authority's Third Written Questions (ExQ3) - Comments on the ExA's commentary on, or schedule of changes to, the draft DCO (dDCO) - Final DCO - Final updated Explanatory Memorandum - Final updated BoR - Final updated Statement of Reasons (SoR) - Final Statement of Common Ground (SoCGs) - Final Statement of Commonality of SoCGs - List of matters not agreed where SoCG could not be finalised - Final Guide to the Application - Final Schedule of Negotiations and Powers Sought - Final Consents and Agreements Position Statement - Final signed and dated section 106 (if required) - Comments on the RIES - Any further information requested by ExA |
03 April 2025 | A46 Newark Bypass | Deadline 8 For receipt by the ExA of: - Comments on any submissions received at the previous deadline - Responses to any further information requested by ExA From the Applicant: - Final application document tracker - Final updated BoR - Final BoR (with full land registry refresh) and schedule of changes to BoR - Final Land Rights Tracker - Final dDCO, in clean and tracked versions in both MS Word and PDF - Final draft DCO to be submitted in the SI template with the SI template validation report. - Final Schedule of Changes to the dDCO - Final EM - Final SoCGs - List of matters not agreed where SoCG could not be finalised - Final SOC - Final NPS accordance table - Final signed and dated legal agreements, if any identified |
04 April 2025 | Outer Dowsing Offshore Wind (Generating Station) | Deadline 6 Deadline for receipt by the ExA of: - Post-hearing submissions including written summaries of oral case put at hearings during w/c 18 March 2025 (if held) - Final Principal Areas of Disagreement Statements - IP’s Closing Statement(s) - Post-hearing submissions including written submissions of oral cases (if applicable) - Applicant’s Closing Statement(s) - Applicant’s Close of Examination Progress Tracker - Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report - Final Explanatory Memorandum in clean and tracked versions - Final Book of Reference (BoR) and schedule of changes to BoR - Applicant’s final Schedule of Negotiations and Powers Sought in clean and tracked versions - Completed s106 Agreements (if required) - Final Land Rights Tracker - Final planning obligations and commercial side agreements tracker - Final Guide to the Application - Final schedule of changes to the draft DCO (if required) - Comments on any other submissions received at Deadline 5 - Final report on the inter-relationship with other infrastructure projects (as described in Annex B) - Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules |
07 April 2025 | A46 Newark Bypass | Deadline 9: For receipt by the ExA of: - Parties’ closing statements of final position on outstanding matters not resolved by end of examination - Responses to any further information requested by ExA |
08 April 2025 | Cory Decarbonisation Project | Publication by the ExA 3 Publication by the ExA of:- Report on the Implications for European Sites (RIES) and any associated questions (if required) - ExA’s commentary on, or schedule of changes to, the dDCO |
08 April 2025 | A46 Newark Bypass | End of Examination The ExA is under a duty to complete the Examination of the application by the end of the period of six months |
08 April 2025 | Tillbridge Solar Project | Deadline 7 (D7) For receipt by the Examining Authority (ExA) of: - Any further information requested by the ExA |
09 April 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - Responses to the ExA’s Second Written Questions (ExQ2) (if these were issued) - Comments on any information requested/submissions received by Deadline 5 - The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001)) - Updated PADs where any substantive changes have been made - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules. |
10 April 2025 | Outer Dowsing Offshore Wind (Generating Station) | End of Examination The ExA is under a duty to complete the examination of the application by the end of the period of six months.Please note that the ExA may close the Examination before the end of the six-month period if it is satisfied that all relevant matters have been addressed and discussed. |
14 April 2025 | Helios Renewable Energy Project | Hearings 2 Time reserved for hearings w/c 14 April 2025- Issue Specific Hearings (ISH) (if required) - Compulsory Acquisition Hearing 3 (CAH3) (if required) |
15 April 2025 | Stonestreet Green Solar | Deadline 5 For receipt by the ExA of: - Responses to ExQ2 - Comments on the Applicant’s revised dDCO - Comments on any additional submissions received by Deadline 4 - Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
15 April 2025 | Morecambe Offshore Windfarm Generation Assets | Deadline 6 (D6) For receipt by the ExA of: - Post-hearing submissions including written submissions of oral cases (if applicable) - Comments on responses to ExQ2 (if provided) - Comments on the RIES (if provided) - Comments on the ExA’s commentary on, or schedule of changes to, the draft DCO (if provided) - Finalised Statements of Common Ground - Final Statement of Commonality/ Close of Examination Progress Tracker - Applicant’s Summary and Signposting document with summary of areas of disagreement - Summary and Signposting documents from Interested Parties regarding matters that they have previously raised during the Examination and have not been resolved to their satisfaction (if desired) - Final Report on interrelationship with other infrastructure projects - Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report together with final draft EM - Final Guide to the Application - Any other updated documents, including the Guide to the Application, and statements from the Applicant deemed necessary following responses at Deadline 5 (if required) - Comments on any further information/ submissions received by Deadline 5 - Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
15 April 2025 | Tillbridge Solar Project | Close of Examination The ExA is under a duty to complete the Examination of the application by the end of the period of six months |
22 April 2025 | Stonestreet Green Solar | Deadline 6 For receipt by the ExA of: - Updated DCO - Updated BoR - Updated SoCG - Comments on the RIES (if required) - Comments on any additional submissions received by Deadline 5 - Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
23 April 2025 | Morecambe Offshore Windfarm Generation Assets | Close of Examination The ExA is under a duty to complete the Examination of the application by the end of the period of six months |
24 April 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - Post-Hearing Submissions, comprising written summaries of oral submissions made at the Hearings held on the w/c 14 April 2025 (if these hearings were held) - Comments on any information requested/submissions received by Deadline 6 - The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001)) - Updated PADs where any substantive changes have been made - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules |
29 April 2025 | Stonestreet Green Solar | Deadline 7 For receipt by the ExA of: - Comments on Deadline 6 submissions |
29 April 2025 | Cory Decarbonisation Project | Deadline 6 (D6) For receipt by the ExA of: - Comments on the RIES and responses to any associated questions (if issued) - Comments on any other information submitted at D5 - Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
May 2025 | ||
02 May 2025 | Cory Decarbonisation Project | Deadline 7 For receipt by the ExA of: - Final Land Rights Tracker - Final Examination Tracker - Final Policy Tracker (if required) - Final SoCG and Statement of Commonality - List of matters not agreed where SoCG could not be finalised - Final BoR and Schedule of Changes to the BoR, in clean and tracked versions - Final dDCO to be submitted by the Applicant in the SI template. Applicant to provide the email notification from https://publishing.legislation.gov.uk/validation confirming the document has successfully passed validation, and the PDF version of the SI validation report obtained from the link in the notification email. Final dDCO in clean, tracked and Word versions. - Final schedule of changes to the dDCO and updated Explanatory Memorandum - Final Application Guide (Application Document Tracker) in clean and tracked versions - Final Statement of Reasons in clean and tracked versions - Final Status of Negotiations with Statutory Undertakers - Completed section 106 agreement - Closing Statements - Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
02 May 2025 | Helios Renewable Energy Project | Publications by ExA Publication by the ExA of:- The ExA's Third Written Questions (ExQ3) (if required) - The ExA's commentary n, or schedule of changes to, the dDCO (if required) - Report on the Implications for European Sites (RIES) and any associated questions (if required) |
05 May 2025 | Cory Decarbonisation Project | Close of Examination The ExA is under a duty to complete the Examination of the application by the end of the period of six months |
06 May 2025 | Stonestreet Green Solar | Deadline 8 For receipt by the ExA of: - Final DCO to be submitted by the Applicant in the SI MS Word template. Applicant to provide the email notification from https://publishing.legislation.gov.uk/validation confirming the document has successfully passed validation, and the PDF version of the SI validation report obtained from the link in the notification email. The Applicant should also provide a clean (all tracking removed) standalone MS Word version of the dDCO, with no header or cover page. - Final updated BoR and schedule of changes to BoR - Final SoCG - Final Statement of Commonality of SoCG - List of matters not agreed where SoCG could not be finalised - Final Navigation Document/Guide to the application - Final Status of Negotiations CA Schedule - Final Status of Negotiations with Statutory Undertakers - Final NPS tracker - Final signed and dated section 106 – if needed - Comments on any further information received - Comments on any additional information/submissions received by Deadline 5 - Responses to ExQ2 and RIES (if issued) - Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
16 May 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - Responses to the ExA’s Third Written Questions (ExQ3) (if these were issued) - Comments on the ExA’s commentary on, or schedule of changes to, the dDCO (if these were issued) - Comments on Report on the Implications for European Sites (RIES) and any associated questions (if it were issued) - Comments on any information requested/submissions received by Deadline 7 - The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001)) - Updated PADs where any substantive changes have been made - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules |
19 May 2025 | Stonestreet Green Solar | Close of Examination by the Examining Authority Close of Examination by the Examining Authority The ExA is under a duty to complete the Examination of the application by the end of the period of six months |
23 May 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - Comments on any information requested/submissions received by Deadline 8 - Final DCO and Explanatory Memorandum. Final DCO to be submitted by the Applicant in the SI template. Applicant to provide the email notification from https://publishing.legislation.gov.uk/validation confirming the document has successfully passed validation, and the PDF version of the SI validation report obtained from the link in the notification email. The Applicant should also provide a clean (all tracking removed) standalone MS Word version of the dDCO, with no header or cover page - Final updated BoR. Final BoR and schedule of changes to BoR - Final Statement of Reasons - Final SoCGs - Final Statement of Commonality of SoCG - List of matters not agreed where SoCG could not be finalised - Final Guide to the application - Final Status of Negotiations CA Schedule - Final Status of Negotiations with Statutory Undertakers - Final NPS tracker - Final Consents and Licences Position Statement - Final signed and dated section 106s - Final versions of any other of the Applicant’s documents that have been updated - Summary statement from the Applicant setting out any outstanding matters - Final PADs submitted by the relevant IPs - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 |
June 2025 | ||
02 June 2025 | Helios Renewable Energy Project | For receipt by the ExA of: - Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010. |
03 June 2025 | Helios Renewable Energy Project | Close of Examination The ExA is under a duty to complete the Examination of the application by the end of the period of six months |