Calendar showing key events and deadlines from all projects.
Project: Five Estuaries Offshore Wind Farm
Details: Publication by the ExA of: - The Report on the Implications for European Sites (RIES) - The ExA’s proposed schedule of changes to the dDCO (if required) - The ExA’s Written Questions (ExQ3) (if required)
Start Time: 23:59:00
Project: Morecambe Offshore Windfarm Generation Assets
Details: Week commencing Monday 03 February 2025 reserved for: - Issue Specific Hearing 2 - Issue Specific Hearing 3 - Issue Specific Hearing 4 - Issue Specific Hearing 5 (if required)
Project: Outer Dowsing Offshore Wind (Generating Station)
Details: Deadline 4 Deadline for receipt by the ExA of: * Responses to ExQ2 (if published) * Comments on the Applicant’s update to the draft DCO * Comments on the Applicant’s update to the Land Rights Tracker * Applicant’s update to the draft DCO * Applicant’s update to the Land Rights Tracker * Applicant’s update to the Guide to the Application * Applicant’s update to the Statements of Commonality of Statements of Common Ground * Comments on any other submissions received at Deadline 3 * Updated report on the inter-relationship with other infrastructure projects (as described in Annex B) * Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules
Start Time: 23:59:00
Project: A46 Newark Bypass
Details: Deadline 5 For receipt by the ExA of: * Responses to ExQ2, if required * Responses on the (RIES) and any associated questions, if required * Comments on any submissions received at the previous deadline * Responses to any further information requested by the ExA for this deadline From the Applicant * Updated NPS accordance table * Updated application documents tracker * Updated BoR * Updated Schedule of Changes to the BoR * Updated Land Rights Tracker * Updated dDCO * Updated Schedule of Changes to the dDCO * Updated EM * Updated SoCG and SoC * Updated legal agreements, if identified
Start Time: 23:59:00
Project: Tillbridge Solar Project
Details: Publication by the Examining Authority (ExA) of: - The ExA's Second Written Questions (ExQ2)
Start Time: 23:59:00
Project: Morgan Offshore Wind Project Generation Assets
Details: Publication by the Examining Authority of: * Report on the Implications for European Sites (RIES) and any associated questions (if required) * Examining Authority’s commentary on, or schedule of changes to, the draft Development Consent Order (if required)
Project: Helios Renewable Energy Project
Details: Publication by the ExA of: - The ExA's First Written Questions (ExQ1)
Start Time: 23:59:00
Project: H2Teesside
Details: Deadline 7 Deadline for receipt by ExA of: * Written summaries of oral submissions at hearings (if required) * Comments on any submissions received at DL5,DL5A,DL6 and DL6A, including any additional AP(s); additional IP(s); or IP(s), as well as any RRs or WRs made pursuant to the Change Request proposed provision * Response to Applicant’s comments on RRs received at DL5A * Comments on the RIES (if required) * Comments on the ExA’s proposed schedule of changes to the dDCO (if required) * Finalised SoCGs * Final Statement of Commonality for SoCG * Final BoR in clean and tracked versions * Final Statement of Reasons in clean and tracked versions * Schedule of Changes to the BoR in clean and tracked versions * Applicant’s final update to the Land Rights Tracker (CA/ TP Schedule) * Final Application Guide (Application Document Tracker), in clean and tracked versions * Final Examination Progress Tracker * Final update to tracking documents, if required * Applicant’s Final Preferred Development Consent Order (DCO) in the SI template validation report and a validated copy of the DCO * Applicant’s preferred DCO in word format * Final Schedule of Changes to the dDCO * Any further information requested by the ExA (if required)
Start Time: 23:59:00
Project: Cory Decarbonisation Project
Details: Week commencing Monday 10 February 2025 (if required) for: - Issue Specific Hearing 2 (ISH2) draft Development Consent Order (dDCO) - Any further Issue Specific Hearings (If required) - Compulsory Acquisition Hearing 2 (CAH2) (If required) - Open Floor Hearing (OFH2) (if required) - Accompanied Site Inspection (ASI)
Project: Five Estuaries Offshore Wind Farm
Details: Deadline 6 Receipt by the ExA of: * Post-Hearing submissions including written submissions of oral case as requested by Examining Authority * Further PADs update from Natural England (clean and tracked) * Applicant’s updated version of the dDCO (clean and tracked) (if required) * Applicant’s updated Guide to the Application documents (clean and tracked) * Any SoCG updates, either agreed updating notes or unilateral notes (if required) * Comments on any submissions received at Deadline 5 and Deadline 5A * Any other submission from the Applicant * Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
Start Time: 23:59:00
Project: Outer Dowsing Offshore Wind (Generating Station)
Details: Tuesday 11 - Friday 14 February 2025 Dates reserved (if required) for: * Any Compulsory Acquisition Hearing * A further Open Floor Hearing (if requested) * Any Issue Specific Hearing * Accompanied Site Inspection
Project: Morgan Offshore Wind Project Generation Assets
Details: Issue Specific Hearing 3 on Environmental Matters and Other Sea Users To attend Issue Specific Hearing 3 please complete the Event Participation Form by 23:59 on Wednesday 29 January 2025. [Please click on this link to register your participation at Issue Specific Hearing 3.](https://forms.office.com/e/4W3aaevaB5) Virtual only event held using Microsoft Teams. Registration available from: 09:30am and the event will commence at 10:00am. Full instructions on how to join online or by telephone will be provided in advance to those who have pre-registered. A livestream will be available for this event. [Please click on this link to view the livestream for this event.](https://cvslivestream.co.uk/morgan/) Recordings, transcripts and action points of the Issue Specific Hearing 3 are available. [View action points, recordings and transcripts.](https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010136/documents?stage-4=Issue%20Specific%20Hearing%203%20(ISH3)&stage-4=Issue%20Specific%20Hearing%203%20on%20Environmental%20Matters%20and%20Other%20Sea%20Users&itemsPerPage=9)
Start Time: 23:59:00
Project: Dogger Bank South Offshore Wind Farms
Details: Deadline 2 Receipt by the ExA of: * Responses to comments on the LIRs. * Comments on the WRs. * Comments on the updated draft DCO. * Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010. * Comments on any further information/ submissions received by Deadline 1.
Start Time: 23:59:00
Project: Outer Dowsing Offshore Wind (Generating Station)
Details: Issue by the ExA of: * The Report into the Implications for European Sites (RIES) (if required)
Project: A46 Newark Bypass
Details: Week reserved for Hearings, if required for: * Further Issue Specific Hearing(s) * Further Compulsory Acquisition Hearing(s) * Further Open Floor Hearing(s)
Start Time: 23:59:00
Project: H2Teesside
Details: Deadline 7A Deadline for receipt by the ExA of: * Responses to the Applicant’s Change Request accepted into the Examination on 10 February 2025. * Responses to questions raised under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 (EPR). * Comments on any submissions received at DL7, including any responses to comments on the Report on Implications for European Sites (RIES) received at DL7. * Applicant’s Final Preferred Development Consent Order (DCO) in the SI template validation report and a validated copy of the DCO. * Applicant’s preferred DCO in word format. * Final Schedule of Changes to the dDCO. * Final Statements of Common Ground (SoCG). * Final Statement of Commonality for SoCG. * Final BoR in clean and tracked versions. * Schedule of Changes to the BoR in clean and tracked versions. * Applicant’s final update to the Land Rights Tracker (CA/ TP Schedule), together with an agreed position statement on the Lands Rights Tracker, setting out where the Applicant and relevant Interested Parties agree or disagree with the various elements of its content, which is signed by both parties confirming their respective positions. * Final Application Guide (Application Document Tracker), in clean and tracked versions. * Final Examination Progress Tracker. * Final update to tracking documents, if required, related to any relevant developing/emerging: - National Policy Statements; - New policy intentions related to critical infrastructure; - National Planning Policy Framework; and - National Development Management Policies. * Updated Local Impact Reports (LIRs) (if required). * Any further information requested by the ExA (if required).
Start Time: 23:59:00
Project: North Falls Offshore Wind Farm
Details: For receipt by the ExA of: * Comments on relevant representations (RR) * Summaries of all RR exceeding 1500 words * Written summaries of oral submissions made at the PM or hearings * Requests to be heard at notified hearings, see Annex E of the Rule 6 letter * Requests to be heard at any subsequent OFH to be held after OFH1 * Requests by affected persons (AP) (defined in section 59(4) of the Planning Act 2008) to be heard at a CAH * Notification by any statutory parties who have not submitted a RR of their wish to be considered as an interested party * Suggested locations for site inspections (accompanied or unaccompanied), including justification, for consideration by the ExA1 * Responses to any further information requested by ExA for this deadline * Local Authorities Local Impact Report * Applicant's Suggested accompanied site inspection (ASI) itinerary * Initial completed Land Rights Tracker with separate parts for both APs and statutory undertakers (SUs) * Initial Statements of Common Ground (SoCG) * Progress with Statements of Common Ground Document (PSoCG) * National Policy Statement (NPS) Accordance Table * Updated Guide to the Application document tracker * Updated Book of Reference (BoR) * Updated Schedule of Changes to the BoR * Updated draft Development Consent Order (dDCO) * Updated Schedule of Changes to the dDCO * Updated Explanatory Memorandum (EM) * Updated legal agreements, if identified
Start Time: 23:59:00
Project: Morecambe Offshore Windfarm Generation Assets
Details: Deadline 4 (D4) For receipt by the ExA of: * Post-hearing submissions including written submissions of oral cases (if required) * Applicant’s mid-Examination Progress Tracker / update to the Statement of Commonality * Mid-Examination Report on interrelationship with other infrastructure projects * Applicant’s update to the draft DCO and EM * Any other updated documents, including the Guide to the Application, and statements from the Applicant deemed necessary following responses at Deadline 3 (if required) * Comments on any other submissions received at Deadline 3 * Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
Start Time: 23:59:00
Project: Five Estuaries Offshore Wind Farm
Details: Deadline 6A Receipt by the ExA of: * Responses to any submissions made at Deadline 6 pursuant to Action Point 9 arising from Issue Specific Hearing 6
Start Time: 23:59:00
Project: Stonestreet Green Solar
Details: Publication by the Examining Authority (ExA) of: * The ExA’s final itinerary for the accompanied site inspection (ASI) (if required)
Start Time: 23:59:00
Project: H2Teesside
Details: Deadline 8 * Applicant’s Comments on the responses to the Applicant’s Change Request accepted into the Examination on 10 February 2025. * Comments on Applicant’s Final Preferred DCO in the SI template validation report and a validated copy of the DCO and its preferred DCO in word format, including all Articles and Schedules. * Closing submissions. * Comments on any submissions received at DL7A, including on any updates on LIRs, responses to the questions raised under Rule 17 of the EPR (as referred to in Item 20 above) and responses on final SoCG. * Any further information requested by the ExA (if required).
Start Time: 23:59:00
Project: Stonestreet Green Solar
Details: Issue Specific Hearing 3 (ISH3) regarding Public Rights of Way (PRoW)
Start Time: 23:59:00
Project: Stonestreet Green Solar
Details: Open Floor Hearing 2 (OFH2)
Start Time: 23:59:00
Project: Cory Decarbonisation Project
Details: Deadline 4 (D4) For receipt by the ExA of: * Post hearing submissions, including written summaries of oral submissions and any information requested by the ExA at the Hearings w/c 10 February 2025 * Comments on any other information or submissions submitted at Deadline 3 * Updated Land Rights Tracker * Updated Examination Tracker * Updated Policy Tracker (if required) * Updated SoCG and Statement of Commonality (if required) * Updated BoR and Schedule of Changes to the BoR, in clean and tracked versions (if required) * Updated dDCO in clean, tracked and Word versions, schedule of changes to the dDCO and updated Explanatory Memorandum (if required) * Updated Schedule of Changes to the dDCO (if required) * Updated Application Guide (Application Document Tracker) (if required) in clean and tracked versions * Any further information requested by ExA under Rule 17 of the Examination Rules
Start Time: 23:59:00
Project: A46 Newark Bypass
Details: Deadline 6 For receipt by the ExA of: * Written summaries of oral submissions made at the Hearings * Comments on any submissions received at the previous deadline * Responses to any further information requested by ExA From the Applicant * Updated application documents tracker * Updated Land Rights Tracker * Updated dDCO * Updated Schedule of Changes to the dDCO * Updated EM * Updated SoCG and SOC * Updated legal agreements, if identified
Start Time: 23:59:00
Project: Tillbridge Solar Project
Details: Deadline 5 (D5) For Receipt by the Examining Authority (ExA): * Comments on any submissions received by Deadline 4 * Responses to the Examining Authority's Second Written Questions (ExQ2) * Requests to be heard at ISHs in w/c 03 March 2025 (if required) * Requests by Affected Persons (defined in section 59(4( of the Planning Act 2008) to be heard at Compulsory Acquisition Hearing 2 (CAH2) in w/c 03 March 2025 (if required) * Updated Statement of Common Ground (SoCGs) * Updated Statement of Commonality for all SoCGs * Any further information requested by the ExA
Start Time: 23:59:00
Project: Stonestreet Green Solar
Details: Issue Specific Hearing 4 (ISH4) regarding Battery Storage
Start Time: 23:59:00
Project: Stonestreet Green Solar
Details: Compulsory Acquisition Hearing 2 (CAH2)
Start Time: 23:59:00
Project: Helios Renewable Energy Project
Details: For receipt by the ExA of: * Responses to the ExA’s First Written Questions (ExQ1) * Comments on any information requested/submissions received by Deadline 3 * The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001)) * Updated PADs where any substantive changes have been made * Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules
Start Time: 23:59:00
Project: Outer Dowsing Offshore Wind (Generating Station)
Details: Deadline 4a Deadline for receipt by the ExA of: * Post-hearing submissions including written summaries of oral case put at hearings during w/c 10 February 2025 * Comments on the Applicant’s latest update to the draft DCO [REP-008] * Comments on the Applicant’s latest update to the Land Rights Tracker [REP4-092] * Comments on any other submissions received at Deadline 4
Start Time: 23:59:00
Project: Morecambe Offshore Windfarm Generation Assets
Details: Publication by the ExA of: - Further Written Questions (ExQ2) (if required)
Start Time: 23:59:00
Project: Morgan Offshore Wind Project Generation Assets
Details: Deadline 6 For receipt by the Examining Authority of: * Post-hearing submissions including written submissions of oral cases (if applicable) * Comments on responses to ExQ2 (if provided) * Comments on the RIES (if provided) * Comments on the Examining Authority’s commentary on, or schedule of changes to, the draft Development Consent Order (if provided) * Finalised Statements of Common Ground * Final Statement of Commonality and Close of Examination Progress Tracker * Applicant’s Closing Statement with summary of areas of disagreement * Closing Statements from Interested Parties regarding matters that they have previously raised during the Examination and have not been resolved to their satisfaction (if desired) * Final Report on interrelationship with other infrastructure projects * Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report * Final Guide to the Application * Comments on any further information/ submissions received by Deadline 5 * Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
Project: Dogger Bank South Offshore Wind Farms
Details: Publication by the ExA of - The ExA’s First Written Questions (ExQ1).
Start Time: 23:59:00
Project: Outer Dowsing Offshore Wind (Generating Station)
Details: Issue by the ExA of: * The ExA’s preferred draft DCO, proposed schedule of changes, or commentary on the draft DCO (if required)
Project: H2Teesside
Details: The ExA is under a duty to complete the Examination of the application by the end of the period of six months.
Start Time: 23:59:00
Project: H2Teesside
Details: Deadline 9 * Applicant’s final right of reply to anything received at DL8. The ExA is under a duty to complete the Examination of the application by the end of the period of 6 months.
Start Time: 23:59:00