Hinkley Point C New Nuclear Power Station

You can filter the results to show only the items that match your interest.

Documents Published By Stage

Pre Application (1)

Developer's Application (308)

Acceptance (0)

Pre Examination (38)

Examination (599)

Decision (50)

Decided (186)

Date

SourceDescription
Other
Size: 251 KB
Department for Business, Energy and Industrial Strategy
Decision Letter
Other
Size: 315 KB
Department for Business, Energy and Industrial Strategy
Hinkley Point C (Nuclear Generating Station) (Amendment) Order 2018
Other
Size: 84 KB
EDF Energy
Further correspondence regarding Non Material Change Consultation
Other
Size: 69 KB
Environment Agency
Further correspondence regarding Non Material Change Consultation
Other
Size: 6 MB
EDF Energy
Comments on Responses to Non Material Change Consultation
Other
Size: 245 KB
Stop Hinkley
Response to Non Material Change Consultation
Other
Size: 120 KB
Edward A Heath
Late Response to Non Material Change Consultation
Other
Size: 294 KB
Stogursey Parish Council
Response to Non Material Change Consultation
Other
Size: 14 KB
D L Buller
Response to Non Material Change Consultation
Other
Size: 176 KB
Somerset County Council
Response to Non Material Change Consultation
Other
Size: 257 KB
The Fairfield Estate
Response to Non Material Change Consultation
Other
Size: 16 KB
Stephen Wardle
Response to Non Material Change Consultation
Other
Size: 14 KB
Timothy Kaye
Response to Non Material Change Consultation
Other
Size: 16 KB
Graham and Jean Howard
Response to Non Material Change Consultation
Other
Size: 170 KB
West Somerset Council
Response to Non Material Change Consultation
Other
Size: 64 KB
West Hinkley Action Group
Response to Non Material Change Consultation
Other
Size: 15 KB
Helga Staddon
Response to Non Material Change Consultation
Other
Size: 16 KB
Susan Goss
Response to Non Material Change Consultation
Other
Size: 471 KB
Quantock Hills AONB Service
Response to Non Material Change Consultation
Other
Size: 134 KB
Natural England
Response to Non Material Change Consultation
Other
Size: 298 KB
Marine Management Organisation
Response to Non Material Change Consultation
Other
Size: 321 KB
Sedgemoor District Council
Response to Non Material Change Consultation
Other
Size: 39 KB
Jane Taunton
Response to Non Material Change Consultation
Other
Size: 18 KB
Teresa Miller
Response to Non Material Change Consultation
Other
Size: 16 KB
Pauline Kaye
Response to Non Material Change Consultation
Other
Size: 40 KB
Environment Agency
Response to Non Material Change Consultation
Other
Size: 283 KB
Stogursey Parish Council
Response to Non Material Change Consultation
Other
Size: 5 MB
EDF Energy
Consultation and publicity statement in connection with the non-material change application of 28 September 2017
Other
Size: 815 KB
EDF Energy
Draft Amendment Order - Tracked Changes
Other
Size: 10 MB
EDF Energy
Appendix 6 (C) - Computer Generated Images Original Submitted With DCO Application
Other
Size: 10 MB
EDF Energy
Appendix 6 (D) - Computer Generated Images Revised Incorporating Proposed Changes
Other
Size: 911 KB
EDF Energy
Appendix 7 (A) - Indicative Jetty Plans
Other
Size: 3 MB
EDF Energy
Sea Wall (Incorporating Coastal Footpath) - HINK-A2-HSW-00-GA-004
Other
Size: 2 MB
EDF Energy
Appendix 7 (B) - HPC Jetty Discharge HRA Report
Other
Size: 1 MB
EDF Energy
Appendix 2 – Revised Development Consent Order Site Layout Plan & HPC Site Parameter Plan
Other
Size: 1 MB
EDF Energy
Somerset Otter Group Consultation Letter
Other
Size: 503 KB
EDF Energy
Appendix 5 – Landscape and Visual Impact Assessment Viewpoint Location Plans Figure 2 – Long Range Views
Other
Size: 933 KB
EDF Energy
Letters to Deposit Locations - EDF Energy Visitor Centre
Other
Size: 210 KB
EDF Energy
Stakeholder Consultee Letter
Other
Size: 2 MB
EDF Energy
Sedgemoor and West Somerset Green Party Consultation Letter
Other
Size: 1 MB
EDF Energy
Appendix 1 – Development Consent Order Consented Site Layout Plan & HPC Site Parameter Plan
Other
Size: 1 MB
EDF Energy
Application Statement
Other
Size: 20 KB
EDF Energy
Agreed Stakeholder Contact List
Other
Size: 1 MB
EDF Energy
Bridgwater Bay Wildfowlers Association Consultation Letter
Other
Size: 176 KB
EDF Energy
Emergency Diesel Generator - D/ Cooling Water Discharge Weir (Building) / Battery Load Bank - HINK-A2-HD-04-DT-001
Other
Size: 181 KB
EDF Energy
Unit 2: Reactor Bldg / Fuel Bldg / Fuel Bldg Hall / Boron Storage / Safeguard Bldgs / Nuclear Auxiliary Bldg / Access Tower - HINK-A2-HR-02-DT-001
Other
Size: 178 KB
EDF Energy
Unit 1: Reactor Bldg / Fuel Bldg / Fuel Bldg Hall / Boron Storage / Safeguard Bldgs / Nuclear Auxiliary Bldg / Access Tower - HINK-A2-HR-01-DT-001
Other
Size: 958 KB
EDF Energy
Letters to Deposit Locations - Sedgemoor District Council
Other
Size: 122 KB
EDF Energy
Interim Spent Fuel Store - HINK-A2-HHK-00-GE-001
Other
Size: 272 KB
EDF Energy
Unit 2: Gas Insulated Switch Gear / Main Transformer /Unit Transformer / Auxiliary Transformer - HINK-A2-HT-02-DT-001
Other
Size: 404 KB
EDF Energy
Unit 2: Cooling Water Pumphouse / Forebay / Outfall Pond/ Service Access Buildings 6 and 8 - HINK-A2-HP-02-GP-030
Other
Size: 426 KB
EDF Energy
Appendix 5 – Landscape and Visual Impact Assessment Viewpoint Location Plans Figure 1 – Short and Medium Range Views
Other
Size: 203 KB
EDF Energy
Emergency Diesel Generator A / Cooling Water Discharge Weir Building / Underground Tunnel Highpoint - HINK-A2-HD-01-GE-001
Other
Size: 208 KB
EDF Energy
Unit 2: Reactor Bldg / Fuel Bldg / Fuel Bldg Hall / Boron Storage/ Safeguard Bldgs / Nuclear Auxiliary Bldg / Access Tower/ Service Access Building 3 - HINK-A2-HR-02-GE-001
Other
Size: 4 MB
EDF Energy
Appendix 7 (C) - HPC Jetty Discharge Modelling
Other
Size: 175 KB
EDF Energy
Auxiliary Administration Centre - HINK-A2-HUC-00-GE-001
Other
Size: 167 KB
EDF Energy
Back Up Power Containerised Generator 2 - HINK-A2-LLV-00-GA-001
Other
Size: 233 KB
EDF Energy
Unit 1: Fire-Fighting Water Building - HINK-A2-HOJ-01-GA-003
Other
Size: 394 KB
EDF Energy
Unit 1: Cooling Water Pumphouse / Forebay / Outfall Pond/ Service Access Buildings 5 and 7 - HINK-A2-HP-01-GP-030
Other
Size: 52 KB
EDF Energy
Draft Amendment Order
Other
Size: 176 KB
EDF Energy
Emergency Diesel Generator B / Cooling Water Discharge Weir Building / Battery Load Bank - HINK-A2-HD-02-DT-001
Other
Size: 257 KB
EDF Energy
Unit 2: Cooling Water Pumphouse / Forebay / Outfall Pond/ Service Access Buildings 6 and 8 - HINK-A2-HP-02-GE-001
Other
Size: 171 KB
EDF Energy
Hot Laundry / Hot Workshop / Hot Warehouse /Facilities for Decontamination / Effluent Tanks / Refuelling Water Storage Tank / Battery Load Bank - HINK-A2-HV-00-DT-001
Other
Size: 120 KB
EDF Energy
Application Covering Letter
Other
Size: 176 KB
EDF Energy
Unit 1: Cooling Water Pumphouse / Forebay / Outfall Pond/ Service Access Buildings 5 and 7- HINK-A2-HP-01-DT-001
Other
Size: 204 KB
EDF Energy
Unit 2: Reactor Bldg / Fuel Bldg / Fuel Bldg Hall / Boron Storage/ Safeguard Bldgs / Nuclear Auxiliary Bldg / Access Tower/ Service Access Building 3 - HINK-A2-HR-02-GP-090
Other
Size: 195 KB
EDF Energy
Emergency Diesel Generator B / Cooling Water Discharge Weir Building / Battery Load Bank - HINK-A2-HD-02-GE-001
Other
Size: 177 KB
EDF Energy
Unit 2: Gas Insulated Switch Gear / Main Transformer /Unit Transformer / Auxiliary Transformer - HINK-A2-HT-02-GP-003
Other
Size: 411 KB
EDF Energy
Unit 1: Gas Insulated Switch Gear / Main Transformer /Unit Transformer / Auxiliary Transformer - HINK-A2-HT-01-GE-001
Other
Size: 173 KB
EDF Energy
Emergency Diesel Generator - C/ Cooling Water Discharge Weir Building / Underground Tunnel Highpoint - HINK-A2-HD-03-DT-001
Other
Size: 174 KB
EDF Energy
Unit 1: Fire-Fighting Water Building - HINK-A2-HOJ-01-DT-001
Other
Size: 272 KB
EDF Energy
Unit 1: Gas Insulated Switch Gear / Main Transformer /Unit Transformer / Auxiliary Transformer - HINK-A2-HT-01-DT-001
Other
Size: 191 KB
EDF Energy
Hot Laundry / Hot Workshop / Hot Warehouse /Facilities for Decontamination / Effluent Tanks / Refuelling Water Storage Tank / Battery Load Bank - HINK-A2-HV-00-GE-001
Other
Size: 199 KB
EDF Energy
Emergency Diesel Generator - C/ Cooling Water Discharge Weir Building / Underground Tunnel Highpoint - HINK-A2-HD-03-GP-040
Other
Size: 196 KB
EDF Energy
Off-site Vehicle Search Area - HINK-A2-VSA-00-GA-001
Other
Size: 202 KB
EDF Energy
Unit 2: Reactor Bldg / Fuel Bldg / Fuel Bldg Hall / Boron Storage/ Safeguard Bldgs / Nuclear Auxiliary Bldg / Access Tower/ Service Access Building 3 - HINK-A2-HR-02-GE-002
Other
Size: 174 KB
EDF Energy
Unit 2: Fire-Fighting Water Building - HINK-A2-HOJ-02-DT-001
Other
Size: 195 KB
EDF Energy
Emergency Diesel Generator - D/ Cooling Water Discharge Weir (Building) / Battery Load Bank - HINK-A2-HD-04-GE-001
Other
Size: 951 KB
EDF Energy
Letters to Deposit Locations - West Somerset District Council
Other
Size: 203 KB
EDF Energy
Emergency Diesel Generator - C/ Cooling Water Discharge Weir Building / Underground Tunnel Highpoint - HINK-A2-HD-03-GE-001
Other
Size: 232 KB
EDF Energy
Unit 2: Fire-Fighting Water Building - HINK-A2-HOJ-02-GA-003
Other
Size: 199 KB
EDF Energy
Emergency Diesel Generator A / Cooling Water Discharge Weir Building / Underground Tunnel Highpoint - HINK-A2-HD-01-GP-040
Other
Size: 178 KB
EDF Energy
Degassed Water Storage Tanks / Valve Room - HINK-A2-REA-00-GA-001
Other
Size: 200 KB
EDF Energy
Unit 1: Reactor Bldg / Fuel Bldg / Fuel Bldg Hall / Boron Storage/ Safeguard Bldgs / Nuclear Auxiliary Bldg / Access Tower/ Service Access Building 2 - HINK-A2-HR-01-GE-002
Other
Size: 206 KB
EDF Energy
Unit 1: Reactor Bldg / Fuel Bldg / Fuel Bldg Hall / Boron Storage/ Safeguard Bldgs / Nuclear Auxiliary Bldg / Access Tower/ Service Access Building 2 - HINK-A2-HR-01-GE-001
Other
Size: 176 KB
EDF Energy
Unit 1: Gas Insulated Switch Gear / Main Transformer /Unit Transformer / Auxiliary Transformer - HINK-A2-HT-01-GP-003
Other
Size: 166 KB
EDF Energy
Auxiliary Administration Centre - HINK-A2-HUC-00-GP-020
Other
Size: 16 MB
EDF Energy
Appendix 6 (B) - Illustrative Masterplan Revised Incorporating Proposed Changes.pdf
Other
Size: 922 KB
EDF Energy
Sea Wall (Incorporating Coastal Footpath) - HINK-A2-HSW-00-GA-001
Other
Size: 196 KB
EDF Energy
Emergency Diesel Generator - D/ Cooling Water Discharge Weir (Building) / Battery Load Bank - HINK-A2-HD-04-GP-040
Other
Size: 635 KB
EDF Energy
Appendix 4 – Illustrative Plans Indicating Changes Figure A - Proposed Changes Outside Parameters
Other
Size: 167 KB
EDF Energy
Back Up Power Containerised Generator 3 - HINK-A2-LLW-00-GA-001
Other
Size: 254 KB
EDF Energy
Unit 1: Cooling Water Pumphouse / Forebay / Outfall Pond - HINK-A2-HP-01-GE-001
Other
Size: 197 KB
EDF Energy
Emergency Diesel Generator B / Cooling Water Discharge Weir Building / Battery Load Bank - HINK-A2-HD-02-GP-040
Other
Size: 176 KB
EDF Energy
Unit 2: Cooling Water Pumphouse / Forebay / Outfall Pond/ Service Access BuildingS 6 and 8 - HINK-A2-HP-02-DT-001
Other
Size: 177 KB
EDF Energy
Emergency Diesel Generator A / Cooling Water Discharge Weir Building / Underground Tunnel Highpoint - HINK-A2-HD-01-DT-001
Other
Size: 114 KB
EDF Energy
Equipment Store (For Spent Fuel Store) - HINK-A2-HHX-00-GA-001
Other
Size: 124 KB
EDF Energy
Interim Spent Fuel Store - HINK-A2-HHK-00-GE-002
Other
Size: 14 MB
EDF Energy
Appendix 6 (A) - Illustrative Masterplan Original Submitted with DCO Application.pdf
Other
Size: 185 KB
EDF Energy
Auxiliary Administration Centre - HINK-A2-HUC-00-GE-002
Other
Size: 177 KB
EDF Energy
Hot Laundry / Hot workshop / Hot warehouse /Facilities for Decontamination / Effluent Tanks / Refuelling Water Storage Tank / Battery Load Bank - HINK-A2-HV-00-GP-020
Other
Size: 526 KB
EDF Energy
HPC Permanent Development Site - HINK-A1-SL-00-GA-002
Other
Size: 167 KB
EDF Energy
Auxiliary Administration Centre - HINK-A2-HUC-00-DT-001
Other
Size: 166 KB
EDF Energy
Back Up Power Containerised Generator 1 - HINK-A2-LLY-00-GA-001
Other
Size: 767 KB
EDF Energy
HPC Permanent Development Site - HINK-A1-SL-00-GA-010
Other
Size: 815 KB
EDF Energy
Appendix 3 – Draft Amendments to Development Consent Order (Tracked Changes)
Other
Size: 418 KB
EDF Energy
Unit 2: Gas Insulated Switch Gear / Main Transformer /Unit Transformer / Auxiliary Transformer - HINK-A2-HT-02-GE-001
Other
Size: 200 KB
EDF Energy
Unit 1: Reactor Bldg / Fuel Bldg / Fuel Bldg Hall / Boron Storage / Safeguard Bldgs / Nuclear Auxiliary Bldg / Access Tower / Service Access Building 2 - HINK-A2-HR-01-GP-090
Other
Size: 121 KB
EDF Energy
Interim Spent Fuel Store - HINK-A2-HHK-00-GP-000
Other
Size: 197 KB
EDF Energy
Consultee List for Non Material Change 3
Other
Size: 1 MB
EDF Energy
Request for Non Material Change 3
Other
Size: 106 KB
Department for Business, Energy and Industrial Strategy
Letter to EDF Energy regarding proposed Non Material Change Application
Other
Size: 215 KB
Decision Letter
Other
Size: 113 KB
Hinkley Point C (Nuclear Generating Station) (Amendment) Order 2017
Other
Size: 1 MB
Sedgemoor Action Group for the Environment
Late Response to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 16 KB
Sedgemoor Action Group for the Environment
Late Response to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 229 KB
Sedgemoor District Council
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 4 MB
EDF Energy
Response to the concerns raised by stakeholders
Other
Size: 8 KB
Environment Agency
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 291 KB
Sedgemoor District Council
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 34 KB
Mr T Mexson
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 14 KB
Bridgwater Town Council
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 168 KB
Somerset County Council
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 32 KB
Natural England
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 2 MB
Mrs A M Gill
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 322 KB
Somerset Drainage Boards Consortium
Responses to Hinkley Point C New Power Station's application for a non-material change to the Development Consent Order
Other
Size: 2 MB
EDF Energy
Consultation and Publicity Statement – Annex 1 – Notice and Newspaper Notices
Other
Size: 470 KB
EDF Energy
Consultation and Publicity Statement
Other
Size: 2 MB
EDF Energy
Consultation and Publicity Statement - Annex 4 - Letters to Deposit Locations
Other
Size: 320 KB
EDF Energy
Consultation and Publicity Statement -Annex 3 - BRIAC NMC Stakeholder List
Other
Size: 62 KB
EDF Energy
Consultation and Publicity Statement - Annex 2 - Consultee Letter
Other
Size: 6 MB
EDF Energy
Proposed Hard and Soft Landscape Works During Operation - DRW-000116
Other
Size: 344 KB
EDF Energy
Application Statement
Other
Size: 4 MB
EDF Energy
Proposed Site Context Sections Site Context Section HH & JJ - DRW-001021
Other
Size: 7 MB
EDF Energy
Proposed Hard and Soft Landscape Works - DRW-000115
Other
Size: 5 MB
EDF Energy
Proposed Internal Street Elevations Block AA - DRW-001027
Other
Size: 2 MB
EDF Energy
Proposed Site Boundary Elevation South Elevation - DRW-001025
Other
Size: 2 MB
EDF Energy
Proposed Internal Site Elevation DD - DRW-001030
Other
Size: 4 MB
EDF Energy
Proposed Internal Street Elevation BB - DRW-001028
Other
Size: 7 MB
EDF Energy
Proposed Hard and Soft Landscape Works - DRW-000112
Other
Size: 7 MB
EDF Energy
Proposed Hard and Soft Landscape Works - DRW-000111
Other
Size: 2 MB
EDF Energy
Proposed Site Context Sections KK & LL - DRW-001022
Other
Size: 7 MB
EDF Energy
Proposed Hard and Soft Landscape Works During Operation - DRW-000113
Other
Size: 6 MB
EDF Energy
Proposed Hard and Soft Landscape Works - DRW-000110
Other
Size: 42 KB
HPCNuclear - Draft Amendment Order
Draft Amendment Order
Other
Size: 975 KB
edf
Proposed Site Setting Out - DRW-001020
Other
Size: 933 KB
EDF Energy
Development Consent Order
Other
Size: 5 MB
EDF Energy
Proposed Hard and Soft Landscape Works During Operation - DRW-000114
Other
Size: 3 MB
EDF Energy
Proposed Internal Site Street Elevation CC - DRW-001029
Other
Size: 4 MB
EDF Energy
Application Covering Letter
Other
Size: 73 KB
EDF Energy
Regulation 6 Notice
Other
Size: 708 KB
EDF Energy
Tree Retention and Removal Plan - DRW-000108
Other
Size: 123 KB
EDF Energy
Annex to the Bridgwater A Design and Access Statement
Other
Size: 189 MB
4.3 - Volume 2 - Appendices
Other
Size: 96 KB
120816 EN010001 Compulsory Acquisition Hearing 29 Aug Agenda
Other
Size: 201 KB
120321 EN010001 Note of Preliminary Meeting
Other
Size: 42 KB
120417 EN010001 Open Floor Hearing Flyer
Other
Size: 14 KB
120213 EN010001 Email re lack Stogursey hearing by Ms L S Jones (R)
Other
Size: 49 KB
120430 EN010001 RULE 17 request to SDC for innovia site permission and steart penninsula
Request by the Panel for SDC to provide a copy of the North East Bridgwater and Steart Peninsula Project planning permissions.
Other
Size: 16 KB
120213 EN010001 Email re lack Stogursey hearing by Ms Susan Goss (R)
Other
Size: 41 KB
120213 EN010001 Email re lack Stogursey hearing by Ms Lesley Flash (R)
Other
Size: 30 KB
FS006 Response to Panel's 2nd Round of Written Questions by Ben Hudson (r)
Response to the Panel's Further Written Questions
Other
Size: 13 KB
120213 EN010001 Email re lack Stogursey hearing by Mrs Oates (R)
Other
Size: 16 KB
120213 EN010001 Email re lack Stogursey hearing by Mr Richard Cuttell (R)
Other
Size: 32 KB
FS042 Submission re ISH2 by Stogursey Parish Council (Searle) (r)
Written Comments on the Panel's Questions for 2nd Issue Specific Hearing (17/18 July 2012)
Other
Other
Size: 105 KB
111219 EN010001 Outreach Meeting Note
A note of the advice given at the outreach meetings held between 5 and 14 December 2011
Other
Size: 78 KB
Hinkley Rule 4 and 6 Letters - sent 17.02.12
The Rule 4 letter contains notification of the appointment of the Examining Authority. The Rule 6 letter includes notification and details regarding the Preliminary Meeting and information about the availability of relevant representations.
Other
Size: 38 KB
120224 EN010008 Hinkley incomplete submissions letter
Other
Size: 232 KB
120301 EN010001 Bridgwater Transport SOA (Covering email) by WSC, SCC and SDC
A Strategic Options Appraisal of Transport Proposals In Bridgwater; submitted by West Somerset Council, Somerset County Council and Sedgemoor District Council.
Other
Size: 14 KB
120222 EN010001 Email re PM & STOGURSEY SV by Stogursey PC (Prowse) (R)
Other
Size: 58 KB
120829 EN010001 Statement to Open Floor Hearing by CBI (Moore)
Other
Size: 11 MB
120531 EN010001 EDF rule 17 response to compulsory aquisition questions and land issues Appendices
Response by EDF Energy to the request for further information made by the Panel on 18th May 2012
Other
Other
Size: 260 KB
111114 EN010001 S55(4)(b) - West Somerset C Somerset CC Sedgemoor DC (Cover letter)
Representation on the adequacy of the applicant?s pre-application consultation from West Somerset C_Somerset CC_Sedgemoor DC (Cover letter).
Other
Size: 196 KB
111114 EN010001 S55(4)(b) - North Dorset District Council
Representation on the adequacy of the applicant's pre-application consultation from North Dorset District Council.
Other
Size: 2 MB
OS019 Other Submission by Bridgwater and Albion Rugby Football Club Limited (S Smith) (R)
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 10 MB
120301 EN010001 Bridgwater Transport SOA (Document 2) by WSC, SCC and SDC
A Strategic Options Appraisal of Transport Proposals In Bridgwater; submitted by West Somerset Council, Somerset County Council and Sedgemoor District Council.
Other
Size: 228 KB
111108 EN010001 S55(4)(b) - Bath & North East Somerset Council
Representation on the adequacy of the applicant?s pre-application consultation from Bath & North East Somerset Council.
Other
Size: 228 KB
111116 EN010001 S55(4)(b) - Devon County Council
Representation on the adequacy of the applicant's pre-application consultation from Devon County Council.
Other
Size: 24 KB
FS024 Further Submissions on updated DCO by Stogursey Parish Council
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 407 KB
FS059 Comments by John White(r)
Comments on EDF's 12 July Docs
Other
Size: 297 KB
111103 EN010001 S55(4)(b) - Wiltshire Council
Representation on the adequacy of the applicant's pre-application consultation from Wiltshire Council.
Other
Size: 6 MB
SCOPING OPINION HINKLEY final APRIL 2010
Scoping Opinion issued by IPC
Other
Size: 46 KB
Other
Size: 56 KB
Notice of the Decision by the SoS
Other
Size: 3 MB
Decision Letter
Other
Size: 85 KB
Hinkley Point C (Nuclear Generating Station) (Amendment) Order 2015
Other
Size: 36 MB
EDF Energy
Book of Revised Plans
Other
Size: 39 KB
150529 EN010001 DECC site visit notice
Other
Size: 78 KB
Natural England
Consultation response received by the Secretary of State after 23 March 2015 regarding the proposed non material change to the Development Consent Order (DCO).
Other
Size: 26 KB
Environment Agency
Consultation response received by the Secretary of State after 23 March 2015 regarding the proposed non material change to the Development Consent Order (DCO).
Other
Size: 60 KB
English Heritage
Other
Size: 378 KB
West Somerset Council
Other
Size: 273 KB
Sedgemoor District Council
Other
Size: 69 KB
Office for Nuclear Regulation
Other
Size: 108 KB
Non Material Changes Reg 7(4) Statement of Reasons
Statement of Reasons - Exercise of discretion not to consult certain consultees
Other
Size: 458 KB
EDF Energy
APPENDIX 5 - Fig 1
Other
Size: 33 MB
EDF Energy
APPENDIX 5 - Medium Range - Principal Viewpoint 4
Other
Size: 3 MB
EDF Energy
Application Covering Letter
Other
Size: 515 KB
EDF Energy
APPENDIX 5 - Fig 2
Other
Size: 11 KB
Notice of a nonmaterial change application
Other
Size: 26 MB
EDF Energy
HPC Development Site Application Statement
Other
Size: 817 KB
EDF Energy
APPENDIX 4 - Fig A
Other
Size: 137 KB
EDF Energy
APPENDIX 5 - LANDSCAPE AND VISUAL IMPACT ASSESSEMENT VIEWPOINT LOCATION PLANS
Other
Size: 45 MB
EDF Energy
APPENDIX 5 - Short Range - Principal Viewpoint 16 (including dusk view)
Other
Size: 1 MB
EDF Energy
APPENDIX 2 - REVISED SITE LAYOUT PLAN & HPC SITE PARAMETER PLAN
Other
Size: 713 KB
EDF Energy
Application Statement
Other
Size: 102 KB
EDF Energy
APPENDIX 4 - ILLUSTRATIVE PLANS INDICATING CHANGES
Other
Size: 751 KB
EDF Energy
APPENDIX 4 - Fig B
Other
Size: 39 MB
EDF Energy
APPENDIX 5 - Medium Range - Principal Viewpoint 19 (including dusk view)
Other
Size: 788 KB
EDF Energy
APPENDIX 4 - Fig C
Other
Size: 3 MB
EDF Energy
APPENDIX 1 - DCO CONSENTED SITE LAYOUT PLAN & HPC SITE PARAMETER PLAN
Other
Size: 1 MB
EDF Energy
APPENDIX 3 - DRAFT AMENDMENTS TO DCO(TRACKED CHANGES)
Other
Size: 24 MB
EDF Energy
APPENDIX 5 - Short Range - Principal Viewpoint 1
Other
Size: 936 KB
Hinkley Point C Corrections Order
Approved by the Secretary of State on 19 November 2013.
Other
Size: 241 KB
Hinkley Point C Correction Notice
Approved by the Secretary of State on 19 November 2013.
Other
Size: 258 KB
Hinkley outreach poster
Details of outreach events taking place during December 2011 near to the proposed Hinkley Point C site.
Other
Size: 610 KB
Other
Size: 133 KB
130319 EN010001 SoS HPC Decision Letter Annex E
Other
Size: 193 KB
130319 EN010001 SoS HPC Decision Letter Annex C
Other
Size: 8 MB
130319 EN010001 SoS HPC Decision Letter
Other
Size: 3 MB
130319 EN010001 SoS HPC Decision letter Annex F
Other
Size: 567 KB
130319 EN010001 SoS HPC Decision Letter Annex B
Other
Size: 13 MB
Other
Size: 5 MB
130319 EN010001 Correspondence sent to SoS by miscellaneous
Other
Size: 309 KB
130319 EN010001 Correspondence sent to SoS by Greenpeace
Other
Other
Size: 606 KB
121219 EN010001 Panel Recommendation Report Appendix D
Other
Size: 2 MB
121219 EN010001 SoS HPC Decision Letter Annex A
Other
Size: 1 MB
130319 EN010001 SoS HPC Decision Letter Annex D
Other
Size: 631 KB
111114 EN010001 S55(4)(b) West Somerset C Somerset CC Sedgemoor DC
Representation on the adequacy of the applicant?s pre-application consultation from West Somerset Council, Somerset County Council and Sedgemoor District Council
Other
Size: 130 KB
120831 EN010001 Submission following the 3rd Issue Specific Hearing by Avon & Somerset Constabulary
Other
Size: 119 KB
120823 EN010001 Submission following the HRA & Ecology Issue Specific Hearing by the MMO
Submission by the Marine Management Organisation
Other
Size: 129 KB
120831 EN010001 Submission following the HRA & Ecology Issue Specific Hearing by the Environment Agency
Other
Size: 3 MB
120824 EN010001 Submission following the 3rd Issue Specific Hearing by the Highways Agency
Other
Size: 138 KB
120814 EN010001 Agreed Position Statement between EDF Energy and Otterhampton Parish Council
Other
Size: 407 KB
120814 EN010001 Agreed Position Statement between EDF Energy and Port of Bridgewater Harbour Master
Other
Size: 27 KB
OS015 Other Submission by Stogursey Parish Council (Prowse)
This late submission commenting on EDF's Response to the Panel's 1st Round of Written Questions has been accepted by the Hinkley Examining Authority
Other
Size: 212 KB
120817 EN010001 EA repsonse to 6 August draft DCO CoCP ISH 14 Aug Matters
Environment Agency comments on 6 Aug draft DCO, the Code of Construction Pratice and their repsonse to comments made at the Issue Specific hearing held on 14 August.
Other
Size: 86 KB
120221 EN010001 Letter to Chair IPC regarding Stogursey
Letter from Leader of West Somerset Council to Chair of IPC regarding concerns about Stogursey not being identified by the Panel in their initial assessment of principal issues.
Other
Size: 2 MB
120824 EN010001 Plan of reduced laydown area
Information used to support EDF Energy's oral submission at the Combwich Issue Specific Hearing. This is for illustrative purposes only and should be viewed in conjunction with the audio recording.
Other
Size: 8 MB
120821 EN010001 EDF Consolidated Final Form Section 106 Agreement
This superceded version of s106 agreement and supporting documents, dated 21 August 2012, was derived from the 3rd Issue Specific Hearing. It was replaced by the engrossed version, dated, 31 August 2012, which can be found in the project docs section of this website.
Other
Size: 54 KB
120418 EN010001 Rule 18 request to EDF for application docs
Other
Size: 59 KB
120504 EN010001 Rule 18 request to Councils for LIR documents
Other
Size: 419 KB
FS065 Comments on RIES by Natural England
Comments on the Report on the Implications for European Sites (RIES)
Other
Size: 187 KB
FS063 Comments on RIES by Countryside Council for Wales (Chris Uttley)
Comments on the Report on the Implications for European Sites (RIES)
Other
Size: 4 MB
120918 EN0100001 EDF Responses to Issues Raised at Compulsory Acquisition Hearing
Further Responses by the applicant to issues raised at the Compulsory Acquisition Hearing held on 29 August 2012 in regard to Combwich Pill
Other
Size: 717 KB
120914 EN01001 EDF Unilateral Undertaking
Unilateral Deed of Development Consent Obligations (dated 13/09/12) as agreed at Compulsory Acquisition Hearing held on 29 August 2012
Other
Size: 434 KB
120831 EN010001 Submission following the Combwich Issue Specific Hearing by Sedgemoor District Council
Other
Size: 599 KB
120816 EN010001 EDF's Revised Draft DCO Requirements
Applicant's updated submission following the 3rd Issue Specific Hearing held 14 August 2012
Other
Size: 276 KB
FS101 Comments on RIES & HEO by EA (McKay)
Comments on Harbour Empowerment Order (HEO) and the Report on the Implications for European Sites (RIES) following the 3rd Issue Specific Hearing by the Environment Agency
Other
Size: 374 KB
120914 EN010001 EDF Letter re s145(2) status
Further information from the applicant relating to the Harbour Empowerment Order (HEO), which has been accepted into the examination by the Panel
Other
Size: 2 MB
120917 EN010001 MMO Marine License Update
Information supplied by the Marine Management Organisation which has been accepted into the examination by the Panel
Other
Size: 1 MB
120911 EN0100001 Submission following the Traffic & Transportation Issue Specific Hearing by the Highways Agency
Other
Size: 111 KB
FS099 Comments by Fairfield Estate (Waller) on EDF's Rule 17 Responses
Comments on EDF's Responses to the Panel's Rule 17 Requests (deadline 17 September)
Other
Size: 517 KB
FS093 Comments on August ISHs by Avon & Somerset Constabulary
Comments on EDF Responses to the August Issue Specific Hearings (deadline 14 September)
Other
Size: 27 KB
FS098 Comments by EA (McKay) on EDF's Rule 17 Responses
Comments on EDF's Responses to the Panel's Rule 17 Requests (deadline 17 September)
Other
Size: 22 KB
FS100 Comments by Stogursey PC (Searle) on EDF's Rule 17 Responses
Comments on EDF's Responses to the Panel's Rule 17 Requests (deadline 17 September)
Other
Size: 960 KB
FS095 Cecily Collingridge's Comments on Responses by Applicant to matters raised at Issue Specific Hearings
Comments on EDF Responses to the August Issue Specific Hearings (deadline 14 September)
Other
Size: 337 KB
FS092 Comments by Otterhampton Parish Council
Comments on EDF Responses to the August Issue Specific Hearings (deadline 14 September)
Other
Size: 680 KB
FS097 Comments by SDC & WSC on EDF's Rule 17 Respones
Comments on EDF's Responses to the Panel's Rule 17 Requests (deadline 17 September)
Other
Size: 262 KB
FS096 Joint Council's response to EDF's response to issues raised during the Issue Specific Hearings
Comments on EDF Responses to the August Issue Specific Hearings (deadline 14 September)
Other
Size: 70 KB
FS094 Highways Agency (Ormerod) Comments upon responses by the applicant to matters raised at the issue specific hearings
Comments on EDF Responses to the August Issue Specific Hearings (deadline 14 September)
Other
Size: 950 KB
120919 EN10001 EDF Energy & Natural England Response to Rule 17 Request on Article 33C
Joint response by EDF Energy & Natural England to the Panel's request on 14/09/12 for further information on Article 33C (Agreements relating to Bridgwater Bay Nature Reserve)
Other
Size: 41 KB
120404 EN010001 RULE 17 request to WSC for preliminary works permission
Letter to West Somerset Council requesting a copy of the Preliminary Works Planning Permission and appended documents be formally submitted to the Examining Authority
Other
Size: 2 MB
120920 EN010001 EDF Letter re Marine Licences consultation responses
Information supplied by the applicant that has been accepted into the examination by the Panel
Other
Size: 72 KB
120919 EN10001 EA Response to Rule 17 Request on Article 33C
Response by the Environment Agency to the Panel's request on 14/09/12 for further information on Article 33C (Agreements relating to Bridgwater Bay Nature Reserve)
Other
Size: 189 KB
120906 EN010001 EDF letter confirming Compulsory Acquisition agreement with EA
Letter from the applicant confirming agreement with Environment Agency on outstanding Compulsory Acquisition matter
Other
Size: 53 KB
120921 EN010001 Examination close s99 notification (signed)
Letter informing Interested Parties about the closure of the Hinkley Point C Examination
Other
Size: 38 KB
120907 EN010001 Statement to Open Floor Hearing by John French
Other
Size: 42 KB
FS062 Comments on MMO Documents by EDF
Comments on Marine Management Organisation's documents: Harbour Empowerment Order and Marine Licences.
Other
Size: 100 KB
120725 EN010001 cover letter from MMO regarding Marine Licences
Other
Size: 98 KB
120916 EN010001 Letter clarifying sea wall and reactor heights by EDF (Bryant)
Other
Size: 1 MB
120914 EN010001 Code of Construction Practice (CoCP)
This is the 14 September final revision of the CoCP by EDF. This fully replaces the version from 06 August 2012.
Other
Size: 2 MB
120913 EN010001 EDF Energy Final Response to Comments
Information supplied by the applicant that has been accepted into the examination by the Panel
Other
Size: 260 KB
120913 EN010001 Cover Letter to EDF Energy Final Response to Comments
Other
Size: 32 KB
FS087 Stockland Bristol Parish Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 15 KB
FS089 Bridgwater Town Council Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 14 KB
FS091 Mr Browning Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 87 KB
FS085 WHAG Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 112 KB
FS090 TDBC & NSC Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 81 KB
FS086 Peter Berrington Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 30 MB
120912 EN010001 Combined Heat and Power Study
Combined Heat and Power Study referred to in the Sustainability Statement
Other
Size: 25 KB
FS088 Network Rail Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 2 MB
FS084 Christopher Gwyntopher Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 53 KB
120914 EN010001 Rule 17 Request
Other
Size: 15 KB
120831 EN010001 Withdrawal notice re proposed amended plans by EDF
Other
Size: 17 KB
FS078 SPC (Searle) Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 34 KB
FS072 WSC (Goodchild) Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 2 MB
FS080 TDBC (Rhodes) Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 15 KB
FS069 Highways Agency (Ashman) Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 144 KB
FS076 CCW (Uttley) Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline) & on EDF Responses to the August Issue Specific Hearings (deadline 14 September)
Other
Size: 235 KB
FS073 SDC & SCC Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 770 KB
FS070 EA (Payne) Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 21 KB
FS083 John White Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 12 KB
FS081 Barbara Oates Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 113 KB
FS071 Natural England (Lischak) Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 186 KB
FS082 OPC Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 30 KB
FS075 Comment on s106 by Cannington Parish Council (Beasley) (r)
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 244 KB
FS077 Fairfield Estate Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 165 KB
FS079 Cllr Leigh Redman Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 21 KB
FS074 Cecily Collingridge Response to Draft DCO and Signed Planning Agreement
Comments on s106 Planning Agreement and/or draft Development Consent Order (07 September deadline)
Other
Size: 13 MB
120912 EN010001 Accompanied Site Visit Information Pack
Other
Size: 45 KB
120912 EN010001 Rule 17 CHP Document request to Applicant
A request by the Panel for a Document referred to in the Sustainability Statement
Other
Size: 50 KB
120910 EN010001 Invitation to comment on applicant's responses
Invitation to selected Interested Parties to comment on responses made by the Applicant to two Rule 17 requests for further information by the Panel
Other
Size: 50 MB
120906 EN010001 Audio Recording
Audio recording of the Open Floor Hearing held on 6 September 2012
Other
Size: 208 KB
120906 EN010001 EA letter confirming Compulsory Acquisition agreement with applicant
Letter from Environment Agency confirming agreement with applicant on outstanding Compulsory Acquisition matter
Other
Size: 939 KB
120906 EN010001 Response to Issues Raised at Compulsory Acquisition Hearing
Responses by the applicant to issues raised at the Compulsory Acquisition Hearing held on 29 August 2012
Other
Size: 91 KB
120906 EN010001 Responses to Rule 17 Requests 30 Aug and 3 Sept
Responses by the applicant (EDF) to requests for further information from the Panel made on 30 August 2012 and 3 September 2012
Other
Size: 29 KB
120903 EN010001 Copy of the correspondence from English Heritage to EDF
Other
Size: 284 KB
120903 EN010001 Copy of the correspondence from Environment Agency to EDF
Other
Size: 3 MB
120903 EN010001 Copy of the correspondence from Highways Agency to EDF
Other
Size: 103 KB
120903 EN010001 Rule 17 Article 45 questions
Request to the applicant for further information about Article 45 of the DCO
Other
Size: 17 KB
120822 EN010001 Statement to Traffic & Transportation Issue Specific Hearing by Tom Boyd
Other
Size: 4 MB
FS068 Comments on RIES by EDF
Comments on the Report on the Implications for European Sites (RIES)
Other
Size: 7 MB
120831 EN010001 Applicant Response to Issues Raised at the Issue Specific Hearings
Responses from the applicant to matters raised at the Issue Specific Hearings held between 21 and 24 August and on 14 August 2012
Other
Size: 13 MB
120831 EN010001 Navigation documents
Navigation Document which explains the Proposed Final Form DCO and related documents
Other
Size: 15 MB
120831 EN010001 Section 106 Annexes 1-16
Executed Planning Obligation Appendices
Other
Size: 20 MB
120831 EN010001 Section 106 Plans 1-10
Executed Planning Obligation Plans
Other
Size: 506 KB
120831 EN010001 Section 106 (Engrossed Version)
The executed Planning Obligation; signatures not included in this web version.
Other
Size: 4 MB
120831 EN010001 Proposed Final Form DCO and appendices
Final version of the DCO as proposed by the applicant, including appendices.
Other
Size: 52 KB
120831 EN010001 Invitation to comment on DCO and engrossed planning obligation (s106)
Letter inviting Interested Parties to comment on the Final Form DCO as proposed by the Applicant and the engrossed Planning Obligation (s.106 Agreement)
Other
audio recording
Size: 118 MB
120829 EN010001 Audio Recording 29th August Session
Recording of the Compulsory Acquisition Hearing
Other
audio recording
Size: 4 MB
120824 EN010001 Supplementary Procedural Meeting
Recording of the meeting following Issue Specific Hearing
Other
audio recording
Size: 83 MB
120824 EN010001 Audio Recording 24th August AM Session 1
Recording of the Combwich Issue Specific Hearing
Other
Size: 6 MB
120817 EN010001 EDF Response to Issues Raised at the Third Issue Specific Hearing
The applicant's response to matters raised by Interested Parties at the 3rd Issue Specific Hearing held on 14 August (DCO & mitigation)
Other
audio recording
Size: 87 MB
120824 EN010001 Audio Recording 24th August PM Session
Recording of the Combwich Issue Specific Hearing
Other
audio recording
Size: 43 MB
120823 EN010001 Audio Recording 23rd August Session 2
Recording of the Habitat Regulation Assessment (HRA) and Ecology Matters Issue Specific Hearing
Other
audio recording
Size: 37 MB
120821 EN010001 Audio Recording 21st August Session 2
Recording of the Socio-Economic Matters Issue Specific Hearing
Other
audio recording
Size: 92 MB
120822 EN010001 Audio Recording 22nd August Session 1
Recording of the Traffic & Transportation Matters Issue Specific Hearing
Other
audio recording
Size: 64 MB
120824 EN010001 Audio Recording 24th August AM Session 2
Recording of the Combwich Issue Specific Hearing
Other
audio recording
Size: 80 MB
120823 EN010001 Audio Recording 23rd August Session 1
Recording of the Habitat Regulation Assessment (HRA) and Ecology Matters Issue Specific Hearing
Other
audio recording
Size: 83 MB
120821 EN010001 Audio Recording 21st August Session 1
Recording of the Socio-Economic Matters Issue Specific Hearing
Other
Size: 152 KB
FS067 Comments on MMO Documents by Fairfield Estate (Waller)
Comments on Marine Management Organisation's documents: Harbour Empowerment Order
Other
Size: 50 KB
120830 EN010001 Rule 17 Jetty Questions
A request by the Panel for further information from the applicant about the temporary jetty
Other
audio recording
Size: 85 MB
120822 EN010001 Audio Recording 22nd August Session 2
Recording of the Traffic & Transportation Matters Issue Specific Hearing
Other
Size: 888 KB
120829 EN010001 D Johnson supporting material
Photographs and Maps which D Johnson used to support his oral submission at the Compulsory Acquisition Hearing
Other
Size: 57 KB
120822 EN010001 Statement to Traffic & Transportation Issue Specific Hearing by William Robert Cudlipp (r)
Other
Size: 313 KB
FS066 Comments on DCO requirements by Otterhampton Parish Council
Other
Size: 6 MB
120822 EN010001 EDF response to Otterhampton PC proposed requirements
Other
Size: 290 KB
FS064 Comments on MMO documents by Sedgemoor District Council
Comments on Marine Management Organisation's documents: Harbour Empowerment Order and Marine Licences.
Other
Size: 164 KB
FS061 Comments on MMO documents by Countryside Council for Wales (Chris Uttley)
Comments on Marine Management Organisation's documents: Harbour Empowerment Order and Marine Licences.
Other
Size: 77 KB
FS047 Comments on MMO documents by Steve Smith
Comments on Marine Management Organisation's documents: Harbour Empowerment Order and Marine Licences.
Other
Size: 120 KB
FS044 Comments re EDF 12 July Docs by Cllr Leigh Redman (r)
Comments on EDF's 12 July Docs
Other
Size: 100 KB
FS052 Comments by Natural England (Lischak)
Comments on EDF's 12 July documents
Other
Size: 147 KB
FS050 Comments by Fairfield Estate (Caroline Waller)
Comments on EDF's 12 July Docs & Panel's Questions from Second Issue Specific Hearing
Other
Size: 312 KB
FS053 Comments by CCW (Uttley)
Comments on EDF's 12 July Docs & Panel's Questions from Second Issue Specific Hearing
Other
Size: 178 KB
FS054 Comments by Environment Agency (McKay)
Comments on EDF's 12 July documents
Other
Size: 49 KB
120816 EN010001 Advance Notice of Matter to be raised at the CAH
Advance notice by the Panel to the Applicant about a matter they wish to raise at the Compulsory Acquisition Hearing
Other
Size: 49 KB
120816 EN010001 Advance Notice of Matter to be raised at the CAH
Notification to the applicant about a matter the Panel wish to discuss at the Compulsory Acquisition Hearing on 29 August
Other
audio recording
Size: 135 MB
120814 EN010001 Audio recording 14 August 2012 Morning session
Audio recording of the Issue Specific Hearing held on 14th August 2012 - Morning session
Other
audio recording
Size: 68 MB
120814 EN010001 Audio recording 14 August 2012 Afternoon session
Audio recording of the Issue Specific Hearing held on the 14th August 2012 - Afternoon session
Other
Size: 105 KB
120817 EN010001 Advance Notice of Matter to be raised at the Combwich Issue Specific Hearing
Letter to applicant providing advance notice of matters which the Panel wish to raise at the Combwich Issue Specific Hearing
Other
Size: 105 KB
120817 EN010001 Advance Notice of Matter to be raised at the Combwich Issue Specific Hearing
Letter to applicant providing advance notice of matters which the Panel wish to raise at the Combwich Issue Specific Hearing
Other
Size: 2 MB
Agreed position Statement between EDF Energy and the Fairfield Estate regarding MS15A - The North West Bund
Other
Size: 2 MB
Updated Highway Works Position Statement on behalf of EDF Energy and Somerset County Council
Other
Size: 178 KB
FS054 Comments by Environment Agency (Louisa McKay)
Written Comments on the Panel's Questions for 2nd Issue Specific Hearing (17/18 July 2012)
Other
Size: 9 MB
FS057 Response to Issues Specific Hearing Questions by EDF (Norwood)
Written Comments on the Panel's Questions for 2nd Issue Specific Hearing (17/18 July 2012)
Other
Size: 137 KB
FS053 Further comments by Countryside Council for Wales (Chris Uttley)
Written Comments on the Panel's Questions for 2nd Issue Specific Hearing (17/18 July 2012)
Other
Size: 243 KB
FS048 Comments by Otterhampton Parish Council
Comments on Responses to the Panel's Further Written Questions, EDF 12 July documents and Questions from the Second Issue Specific Hearing
Other
Size: 80 KB
FS049 Comments by Hallam Land Management (Freer)
Comments on Responses to the Panel's Further Written Questions & EDF 12 July documents
Other
Size: 4 MB
120814 EN010001 Application by NNB for Permit - Water Discharges
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 681 KB
120814 EN010001 Draft Permit Water Discharge
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 71 KB
FS058 Comments by Sedgemoor District Council, Somerset County Council and West Somerset Council (R)
Comments on Responses to the Panel's Further Written Questions & Questions from Second Issue Specific Hearing
Other
Size: 29 KB
FS046 Comments by Stogursey Parish Council (Prowse)
Comments on Responses to the Panel's Further Written Questions
Other
Size: 527 KB
120814 EN010001 Draft Permit Combustion Activities
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 44 KB
FS045 Comments re EDF 12 July Docs by The Coal Authority (Roberts)
Comments on EDF's 12 July Docs
Other
Size: 6 MB
FS055 Comments by EDF (Norwood)
Comments on Responses to the Panel's Further Written Questions
Other
Size: 169 KB
Other
Size: 65 KB
FS060 Comment by Taunton Deane Borough Council (Joy Wishlade)
Comments on Responses to the Panel's Further Written Questions
Other
Size: 1 MB
120814 EN010001 EA Appropriate Assesment Exec Summary
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 63 KB
FS051 Comments by Roy Pumfrey(r)
Comments on EDF's 12 July Docs
Other
Size: 3 MB
120814 EN010001 Application by NNB for Permit - Combustion Activities
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 3 MB
120814 EN010001 Application by NNB for Radioactive Substances
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 2 MB
120814 EN010001 EA Permit Consultation Summary
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 3 MB
120814 EN010001 EA Review of NNB Dose Assessment
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 729 KB
120814 EN010001 Draft Permit Radioactive Substances
Document submitted by EA at the Issue Specific Hearing held on 14 August 2012
Other
Size: 10 MB
120814 EN010001 EA Appropriate Assessment
Document submitted by the EA at the Issue Specific Hearing on 14 August 2012
Other
Size: 322 KB
120806 EN010001 Construction Workforce Travel Plan (CWTP)
This 06 August revision of the CWTP also forms Annex 13 of the Final Form s106 Agreement
Other
Size: 4 MB
120717 EN010001 Statement to 2nd Issue Specific Hearing by Barry Pricket
Other
Size: 49 KB
120717 EN010001 Statement to 2nd Issue Specific Hearing by Thomas Boyd
Other
Size: 322 KB
120806 EN010001 Construction Workforce Travel Plan (CWTP)
This 06 August revision of the CWTP also forms Annex 13 of the Final Form s106 Agreement
Other
Size: 2 MB
120806 EN010001 Code of Construction Practice (CoCP)
This 06 August revision of the CoCP, which also forms Appendix 1 of EDF's Response to Issues Raised at the 2nd ISH, has been superceded. Please see project documents for the current 14.09.12 version.
Other
Size: 7 MB
120806 EN010001 DCO Traffic Incident Management Plan (TIMP)
This 06 August revision of the TIMP also forms Appendix 3 of EDF Energy's Response to Issues Raised at the Second Issue Specific Hearing
Other
Size: 20 KB
FS056 Comments by MMO (Peters)
Written Comments on the Panel's Questions for 2nd Issue Specific Hearing (17/18 July 2012)
Other
Size: 2 MB
120806 EN010001 Code of Construction Practice (CoCP)
This is the superceded 06 August revision of the CoCP, which also forms Appendix 1 of ED F Energy's Response to Issues Raised at the Second Issue Specific Hearing.
Other
Size: 7 MB
120806 EN010001 DCO Traffic Incident Management Plan (TIMP)
This 06 August revision of the TIMP also forms Appendix 3 of EDF Energy's Response to Issues Raised at the Second Issue Specific Hearing.
Other
Size: 82 KB
120808 EN010001 Revised HRA Marine Related Requirements
EDF Energy?s Proposed Changes to the 12 July Submission of Schedule 11: Requirements (supplementary)
Other
Size: 71 KB
120810 EN010001 Response to Compulsory Acquisition Questions
Response by EDF Energy to the request for further information made by the Panel on 27 July 2012
Other
Size: 82 KB
120808 EN010001 Revised HRA Marine Related Requirements
EDF Energy?s Proposed Changes to the 12 July Submission of Schedule 11: Requirements (supplementary)
Other
Size: 164 KB
120809 EN010001 14 August ISH additonal agenda items
A letter to invited Interested Parties containing a revised agenda for the Issue Specific Hearing on 14 August 2012
Other
Size: 21 MB
120404 EN010001 WSC Prelim Works Decision
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 127 KB
120806 EN010001 Highway Works Position Statement
Document on behalf of EDF Energy and Somerset County Council. This is Appendix 3 of the larger Response to Issues Raised at the Second Issue Specific Hearing.
Other
Size: 3 MB
120806 EN010001 Comparison of Final Form s106 Agreement
Comparison of 6 August 2012 document against 31 May 2012 draft
Other
Size: 2 MB
120806 EN010001 Updated DCO Document
Draft Development Consent Order (DCO) dated 6th August 2012
Other
Size: 3 MB
120806 EN010001 Final Form DCO s106 (excludes annexes)
Full document also available
Other
Size: 37 MB
120806 EN010001 Final Form S106 Agreement
Includes full plans & appendices. Warning: Large file.
Other
Size: 4 MB
120807 EN010001 SCG014 Avon & Somerset Constabulary
Statement of Common Ground between EDF Energy and Avon & Somerset Constabulary
Other
Size: 466 KB
120806 EN010001 Revised Requirements Document
EDF Energy?s Proposed Changes to the 12 July Submission of Schedule 11: Requirements
Other
Size: 903 KB
120806 EN010001 SCG013 Host Local Authorities (SDC, WSC & SCC)
Statement of Common Ground between EDF Energy and Sedgemoor District Council, Somerset County Council & West Somerset Council
Other
Size: 127 KB
120806 EN010001 Highway Works Position Statement
Document on?behalf?of?EDF?Energy?and?Somerset?County?Council. This is Appendix 3 of the larger Response to Issues Raised at the Second Issue Specific Hearing.
Other
Size: 3 MB
120806 EN010001 Final Form DCO s106 Agreement (excludes annexes)
Full document also available online.
Other
Size: 3 MB
120806 EN010001 Comparison of Final Form s106 Agreement
Comparison of 6 August 2012 document against 31 May 2012 draft
Other
Size: 37 MB
120806 EN010001 Final Form S106 Agreement
Includes full plans & appendices. Warning: This is a large file.
Other
Size: 26 KB
120807 EN010001 Hinkley Deadline Summary
Details of deadlines for Interested Parties. This document is for information purposes only.
Other
Size: 2 MB
120806 EN010001 Updated DCO Document
Draft Development Consent Order (DCO) dated 6th August 2012
Other
Size: 466 KB
120806 EN010001 Revised Requirements Document
EDF Energy?s Proposed Changes to the 12 July Submission of Schedule 11: Requirements
Other
Size: 46 KB
120807 EN010001 Issue Specific Hearing 23 August Any Other Buisness
Letter containing further information for invited interested parties to the Issue Specific Hearing about HRA and Ecology Matters on 23 August 2012
Other
Size: 5 MB
OS020 Other Submission by Fairfield Estate (Waller)
This late submission has been accepted by the Hinkley Examining Authority as supplementaty information to their written representation
Other
Size: 127 KB
120806 EN010001 Issue Specific Hearings 21 to 24 August Agendas
Agendas and information for Interested Parties regarding Issue Specific Hearings being held between 21 - 24 August 2012 and Other Submissions accepted by the Panel
Other
Size: 53 KB
OS013 Other Submission by West Hinkley Action Group (Farmery)
This late submission commenting on EDF's Response to the Panel's 1st Round of Written Questions has been accepted by the Hinkley Examining Authority
Other
Size: 19 KB
OS014 Other Submission by Cllr Lesley Flash
This late submission commenting on EDF's Response to the Panel's 1st Round of Written Questions has been accepted by the Hinkley Examining Authority
Other
Size: 2 MB
OS018 Other Submission by Freight Quality Partnership (Bunce)
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 57 KB
FS026 Further Submissions on updated DCO by Cannington Parish Council (Gardener)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 55 KB
120731 EN010001 Covering Letter for ISH hearing 14 Aug agenda and questions
Agenda items and questions for invited participants - Issue Specific Hearing on DCO and Mitigation on 14 August 2012
Other
Size: 28 KB
FS001 Comments on Revised Draft DCO by NDA (Cole) (r)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 158 KB
FS019 Further Submissions on Local Impact Report Errata by RAC Foundation for Motoring (Durham)
Comments on revised Local Impact Report
Other
Size: 22 KB
FS012 Further Submissions on updated DCO by NHS Somerset and Bridgwater Bay Health Federation (R)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 380 KB
FS025 Further Submissions on updated DCO by Environment Agency (Payne)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 265 KB
FS021 Further Submissions on updated DCO by Natural England (Lischak)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 341 KB
FS008 Further Submissions on Local Impact Report Errata by EDF Energy
Comments on the Revised Local Impact Report
Other
Size: 22 KB
FS018 Further Submissions on updated DCO and Local Impact Report - Errata by HP Cycle Group (Perrett)
Comments on updated draft DCO (revision 1) received by 05 July 2012 and revised Local Impact Report
Other
Size: 259 KB
FS002 Comments on Revised Draft DCO by Otterhampton Parish Council (Gripton)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 193 KB
FS011 Further Submissions on Local Impact Report - Errata by Otterhampton Parish Council
Comments on the Revised Local Impact Report
Other
Size: 6 MB
FS007 Further Submissions on updated DCO by SDC, SCC & WSC (Durant)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 54 KB
120727 EN010001 RULE 17 further request to EDF regarding CA queries
A request by the Panel for further information from the applicant about Compulsory Acquisition matters.
Other
Size: 158 KB
120726 EN010001 Notification to Interested Parties re Open Floor Hearing 06.09.12 & Requests for Further Information by the Panel
Other
Size: 158 KB
120726 EN010001 Notification to Interested Parties re Open Floor Hearing 06.09.12 & Requests for Further Information by the Panel 1
Other
Size: 481 KB
120726 EN010001 RIES 1
The Report on the Implications for European Sites
Other
Size: 23 KB
120724 EN010001 Rule 13 Notice for Compulsory Acquisition and Open Floor Hearings 1
Includes notification for OFH on 06/09/12
Other
Size: 191 KB
120725 EN010001 Harbour Empowerment Order - Decision report
The Panel requested this document at the Issue Specific hearing held on 17 July 2012.
Other
Size: 922 KB
120725 EN010001 Harbour Empowerment Order - The Hinkley Point Harbour Empowerment Order 2012
Information supplied by the Marine Management Organisation which has been accepted into the examination by the Panel
Other
Size: 35 KB
120725 EN010001 Harbour Empowerment Order - Explanatory memorandum to the order
Information supplied by the Marine Management Organisation which has been accepted into the examination by the Panel
Other
Size: 1 MB
120725 EN010001 Harbour Empowerment Order - The Planning Inspectorate's inquiry report
Information supplied by the Marine Management Organisation which has been accepted into the examination by the Panel
Other
Size: 128 KB
120725 EN010001 MMO Marine Licence (Construction)
Information supplied by the Marine Management Organisation which has been accepted into the examination by the Panel
Other
Size: 124 KB
120725 EN010001 MMO Marine Licence (Dredged Material)
Information supplied by the Marine Management Organisation which has been accepted into the examination by the Panel
Other
Size: 362 KB
120725 EN010001 Harbour Empowerment Order - Environmental impact assessment consent decision
Information supplied by the Marine Management Organisation which has been accepted into the examination by the Panel
Other
Size: 5 MB
120725 EN010001 Harbour Empowerment Order - Record of Habitats Regulations assessment
Information supplied by the Marine Management Organisation which has been accepted into the examination by the Panel
Other
Size: 82 KB
FS043 Submission re EDF 12 July Docs by MMO (Peters)
Comments on EDF Draft 12 July Docs by the Marine Management Organisation
Other
Size: 23 KB
120712 EN010001 Rule 13 Notice for Issue Specific Hearings in August 4
Includes notification for ISH on 24/08/12 (Combwich)
Other
Size: 104 KB
120712 EN010001 Notification to IPs for ISH 14.08.12 & Other Submissions
Other
Size: 23 KB
120712 EN010001 Rule 13 Notice for Issue Specific Hearings in August 2
Includes notification for ISH on 22/08/12 (Transport & Transportation Matters)
Other
Size: 23 KB
120712 EN010001 Rule 13 Notice for Issue Specific Hearings in August
Includes notification for ISH on 14/08/12 (DCO and Mitigation Measures)
Other
Size: 47 KB
120720 EN010001 Notification to APs for CA hearings
Information for Affected Persons (APs) regarding a Compulsory Acquisition Hearing to be held on Wednesday 29 August 2012
Other
Size: 23 KB
120724 EN010001 Rule 13 Notice for Compulsory Acquisition and Open Floor Hearings
Includes notification for CAH on 29/08/12
Other
Size: 23 KB
120712 EN010001 Rule 13 Notice for Issue Specific Hearings in August 1
Includes notification for ISH on 21/08/12 (Socio-Economic Matters)
Other
Size: 23 KB
120712 EN010001 Rule 13 Notice for Issue Specific Hearings in August 3
Includes notification for ISH on 23/08/12 (HRA Matters & Ecology)
Other
Size: 111 KB
120716 EN010001 Notification to IPs for additional Issue Specific Hearings in August
Details for Interested Parties of ISHs in week commencing 20/8/12
Other
Size: 147 MB
EN010001-005867 Audio Recording Tuesday 17th July 2012 PM
Audio Recording of the Issue Specific Hearing
Other
Size: 147 MB
EN010001-005866 Audio Recording Tuesday 17th July 2012 AM
Audio Recording of the Issue Specific Hearing
Other
audio recording
Size: 220 MB
120717 EN010001 Audio Recording Wednesday 18th July 2012 AM
Audio Recording of the Issue Specific Hearing
Other
audio recording
Size: 119 MB
120717 EN010001 Audio Recording Wednesday 18th July 2012 PM
Audio Recording of the Issue Specific Hearing
Other
Size: 57 KB
120719 EN010001 RULE 17 request following ISH 17 July
Other
Size: 111 KB
120716 EN010001 Notification to IPs for ISHs wc 20.08.12
Other
Size: 162 KB
FS020 Further Submissions on updated DCO by Marine Management Organisation (Jonathan Peters)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 21 KB
FS023 Further Submissions on updated DCO by Bridgwater Town Council (Alan Hurford)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 176 KB
FS022 Further Submissions on updated DCO by Countryside Council for Wales (Susan Howard)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 2 MB
120712 EDF Energy Doc 1 Updated Requirements
Submission by the applicant setting out proposed amendments to the requirements in the DCO
Other
Size: 133 KB
120712 EN010001 CCW response to updated requirements received 5 July 2012
Submission about suggested amendments proposed by the applicant and other Interested Parties to the requirements in the DCO
Other
Size: 13 MB
120712 EN010001 EDF Energy Doc 2 Updated DCO FINAL 120712
Submission by the applicant which shows a revised proposed Development Consent Order
Other
Size: 1 MB
120712 EN010001 EDF Energy Doc 3 responses to matters raised at issue specific hearing 26 June and other correspondence
Submission by the applicant which contains their repsonse to points raised at the Issue Specific Hearing on 26 June 2012 by participants and also their repsonse to other correspondence received
Other
Size: 66 KB
120712 EN010001 Natural England response to updated requirements received 5 July 2012
Submission about suggested amendments proposed by the applicant and other Interested Parties to the requirements in the DCO
Other
Size: 62 KB
120711 EN010001 Fairfield Estate response to updated requirements received 5 July 2012
Submission about suggested amendments proposed by the applicant and other Interested Parties to the requirements in the DCO
Other
Size: 114 KB
120712 EN010001 Letter re Questions for ISH 17 July
Other
Size: 60 KB
120626 EN010001 Statement to Issue Specific Hearing by Sheila Allen (r)
Other
Size: 22 KB
120618 EN010001 Statement to Issue Specific Hearing by Tom Boyd (r)
Other
Size: 246 KB
OS012 Other Submission by Bridgewater Sports and Social Club (Farkas)(r)
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 1 MB
OS016 Other Submission by Sue Flint
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 12 KB
OS017 Other Submission by John White
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 68 KB
FS034 Response to Panel's 2nd Round of Written Questions by Fairfield Estate (Waller) (r)
Response to the Panel's Further Written Questions
Other
Size: 3 MB
FS027 Response to Panel's 2nd Round of Written Questions by SDC, WSC & SCC (Durant) (r)
Response to the Panel's Further Written Questions
Other
Size: 81 KB
FS032 Response to Panel's 2nd Round of Written Questions by Somerset Tourism Association (Smart) (r)
Response to the Panel's Further Written Questions
Other
Size: 33 KB
FS039 Response to Panel's 2nd Round of Written Questions by West Hinkley Action Group (Cllr Flash) (r)
Response to the Panel's Further Written Questions
Other
Size: 171 KB
120613 EN010001 Panel's Further Written Questions
Other
Size: 181 KB
FS017 Further Submissions on updated DCO by Cllr Leigh Redman(r)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 136 KB
FS040 Response to Panel's 2nd Round of Written Questions by CCW (Uttley) (r)
Response to the Panel's Further Written Questions
Other
Size: 18 MB
FS026 Response to Panel's 2nd Round of Written Questions by EDF (Norwood) (r)
Response to the Panel's Further Written Questions
Other
Size: 37 KB
FS036 Response to Panel's 2nd Round of Written Questions by Stogursey PC (Prowse) (r)
Response to the Panel's Further Written Questions
Other
Size: 14 KB
FS016 Further Submissions on updated DCO by Hallam Land Management (Nick Freer)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 129 KB
FS038 Response to Panel's 2nd Round of Written Questions by Natural England (Lischak) (r)
Response to the Panel's Further Written Questions
Other
Size: 23 KB
FS031 Response to Panel's 2nd Round of Written Questions by Combe House Hotel (Weed) (r)
Response to the Panel's Further Written Questions
Other
Size: 3 MB
FS037 Response to Panel's 2nd Round of Written Questions by Taunton Deane Borough Council (Rhodes) (r)
Response to the Panel's Further Written Questions
Other
Size: 107 KB
FS033 Response to Panel's 2nd Round of Written Questions by MMO (Peters) (r)
Response to the Panel's Further Written Questions
Other
Size: 48 KB
FS028 Response to Panel's 2nd Round of Written Questions by Highways Agency (Ashman) (r)
Response to the Panel's Further Written Questions
Other
Size: 707 KB
FS030 Response to Panel's 2nd Round of Written Questions by Avon & Somerset Constabulary (Beard) (r)
Response to the Panel's Further Written Questions
Other
Size: 58 KB
FS035 Response to Panel's 2nd Round of Written Questions by EA (McKay) (r)
Response to the Panel's Further Written Questions
Other
Size: 296 KB
FS029 Response to Panel's 2nd Round of Written Questions by Otterhampton Parish Council (Gripton) (r)
Response to the Panel's Further Written Questions
Other
Size: 17 KB
120625 EN010001 Statement to Issue Specific Hearing by Cllr Val Bannister (r)
Other
Size: 22 KB
FS041 Response to Panel's 2nd Round of Written Questions by Insitute of Directors (Taylor) (r)
Response to the Panel's Further Written Questions
Other
Size: 166 KB
FS015 Further Submissions on updated DCO by Fairfield Estate (Clarke Willmott LLP)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 2 MB
FS013 Further Submissions on updated DCO by Highways Agency
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 51 KB
FS014 Further Submissions on updated DCO by Avon & Somerset Constabulary (R)
Comments on updated draft DCO (revision 1) received by 05 July 2012
Other
Size: 104 KB
OS011 Other Submission by Innovia (Dagg) (r)
Other
Size: 31 KB
120327 EN010001 Panel 1st Written Questions (Annex to Rule 8 Letter)
Other
Size: 141 KB
120706 EN010001 Details of Combwich planning permission from Sedgemoor District Council
Cover letter and planning permissions relating to private access road between Combwich Wharf and the C182 highway
Other
Size: 166 MB
120627 EN010001 Audio Recording Day 2 - 27 June pm
Audio recording of Issue Specific Hearing held on 27 June (continued from 26 June), part 2
Other
Size: 161 MB
120626 EN010001 Audio Recording Day 1 - 26 June am
Audio recording of Issue Specific Hearing held on 26 June, part 1
Other
Size: 147 MB
120626 EN010001 Audio Recording Day 1 - 26 June pm
Audio recording of Issue Specific Hearing held on 26 June, part 2
Other
Size: 152 MB
120627 EN010001 Audio Recording Day 2 - 27 June am
Audio recording of Issue Specific Hearing held on 27 June (continued from 26 June), part 1
Other
Size: 170 KB
120703 EN010001 Issue Specific Hearing 17th July - Notification to IPs
Agenda and information for Interested Parties about an Issue Specific Hearing on 17 July 2012
Other
Size: 99 KB
120627 EN010001 Letter re examination timetable by Councils (r)
Correspondence regarding examination timetable and planning obligations by Sedgemoor District Council, Somerset County Council & West Somerset Council
Other
Size: 195 KB
Other
Size: 55 KB
120629 EN010001 Reply re Councils' Examination Timetable Queries
Correspondence regarding examination timetable and planning obligations queries on 27 June by Sedgemoor District Council, Somerset County Council & West Somerset Council
Other
Size: 493 KB
FS005 EN01001 Comment on EDF's Response ExA Further Qs on Compulsory Acquisition by SSC, WSC & SDC (r)
Comments on EDF?s Response to Rule 17 Request for Further Information on Compulsory Acquisition and Land Issues
Other
Size: 27 KB
FS004 EN01001 Comment on EDF's Response ExA Further Qs on Compulsory Acquisition by EA (McKay) (r)
Comments on EDF?s Response to Rule 17 Request for Further Information on Compulsory Acquisition and Land Issues
Other
Size: 52 KB
120613 EN010001 Panel's 2nd Written Questions Cover Letter
Other
Size: 146 KB
120614 EN010001 Issue Specific Hearing 26th June - Further Information
Issue Specific Hearing 26th June 2012 - Questions for Selected Interested Parties
Other
Size: 124 KB
120613 EN010001 Panel's 2nd Written Questions (Annex to letter)
Other
Size: 47 KB
120611 EN010001 reply to Councils' letter of 8 June re revised DCO
Reply to Councils' letter 8 June requesting clarification about their opportunity to comment on revisions to the DCO and other documents proposed by the applicant
Other
Size: 270 KB
120608 EN010001 Councils request to comment on revised DCO etc
Councils' letter 8 June requesting clarification about their opportunity to comment on revisions to the DCO and other documents proposed by the applicant
Other
Size: 110 KB
Other
Size: 304 KB
120531 EN010001 SCC SDC WSC LIR004 01 Addendum Errata CovLet Final 2012-05-31
Cover letter explaining the submission of revisions to the Local Impact Report submitted jointly by SDC, WSC and SCC
Other
Size: 788 KB
120531 EN010001 SCC SDC WSC LIR004 02 ERRATA
Errata - revised Local Impact Report by SDC, WSC and SCC in response to the post submission changes to the application
Other
Size: 82 MB
120531 EN010001 SCC SDC WSC LIR004 03 ADDENDUM A QoL
Addendum A - revised Local Impact Report by SDC, WSC and SCC in response to the post submission changes to the application
Other
Size: 16 MB
120531 EN010001 SCC SDC WSC LIR004 04 ADDENDUM B
Addendum B - revised Local Impact Report by SDC, WSC and SCC in response to the post submission changes to the application
Other
Size: 63 KB
CM005 Comments by Avon and Somerset Constabulary (Beard) (r)
Comments on Local Impact Reports & Written Representation(s)
Other
Size: 29 MB
CM008 Comments by EDF (EDF Updated DCO and Proposed Mitigation) (r)
EDF Comment 3 of 3 - Updated Draft Development Consent Order and Proposed Mitigation
Other
Size: 2 MB
CM008 Comments by EDF (EDF Response to Other Interested Parties) (r)
EDF Comment 2 of 3 - Comment on Other Interested Parties Submissions
Other
Size: 21 MB
120531 EN010001 EDF Response to LIRs (r)
EDF Comment 1 of 3 - Comments on Local Impact Report(s)
Other
Size: 46 KB
CM003 Comments by Natural England (Gillespie) (r)
Comments on Relevant Representation(s) and Written Representation(s)
Other
Size: 1 MB
CM007 Comments by Environment Agency (McKay) (r)
Comments on Local Impact Reports, Relevant Representation(s) & Written Representation(s)
Other
Size: 110 KB
CM010 Comments by Innovia Cellophane Limited and Innovia Films Limited (Dagg) (r)
Comments on Local Impact Report(s) and Written Representation(s)
Other
Size: 4 MB
CM009 Comments by Clarke Willmott LLP on behalf of Fairfield Estate (r)
Comments on Local Impact Report and Written Representation(s)
Other
Size: 13 KB
CM002 Comments by Stop Hinkley (Aubrey)(r)
Comments on ExA's First Written Questions
Other
Size: 2 MB
CM011 Comments by Somerset County Council, West Somerset Council and Sedgemoor District Council (Durant) (r)
Comments on Local Impact Report(s), Relevant Representation(s), Written Representation(s) and ExA's First Written Questions.
Other
Size: 714 KB
CM004 Comments by RAC Foundation for Motoring (Durham) (r)
Comments on Local Impact Reports, Relevant Representation(s), Written Representation(s) and ExA's Written Questions.
Other
Size: 349 KB
CM006 Comments by Paul Gripton (r)
Comments on Local Impact Report and Written Representation(s)
Other
Size: 5 MB
120531 EN010001 SCG012 BBWA
Statement of Common Ground between Bridgwater Bay Wildfowling Association and EDF Energy
Other
Size: 158 KB
120531 EN010001 EDF rule 17 Response to Compulsory Acquisition Questions and Land Issues
Response by EDF Energy to the request for further information made by the Panel on 18th May 2012
Other
Size: 29 KB
120531 EN010001 EDF rule 17 response to compulsory aquisition and land issues Executive Summary
Response by EDF Energy to the request for further information made by the Panel on 18th May 2012.
Other
Size: 101 KB
120528 EN010001 Issue Specific Hearing 26th June Notification to IPs
Issue Specific Hearing 26th June 2012 - Agenda and Information for Interested Parties
Other
Size: 211 KB
CM001 Comments by Otterhampton Parish Council (Leathwood) (r)
Comments on Local Impact Report, Written Representation(s) and ExA's Written Questions.
Other
Size: 21 KB
120528 EN010001 Rule 13 for June and July FINAL 1
Notification of Issue Specific Hearings on 26th June and 17th July regarding the Development Consent Order and mitigation measures
Other
Size: 21 KB
120528 EN010001 Rule 13 for June and July FINAL
Notification of Issue Specific Hearings on 26th June and 17th July regarding the Development Consent Order and mitigation measures
Other
Size: 788 KB
120524 EN010001 Clarification from SDC about oral representations made by Councillors
Other
Size: 72 KB
OS002 Other Submission by Cheddar Parish Council (Paul Fineran)(r)
This submission by an non-Interested Party was accepted by the Hinkley Examining Authority
Other
Size: 63 KB
OS008 Other Submission by Matthew Willis (r)
This late submission by a non-Interested Party has been accepted by the Hinkley Examining Authority
Other
Size: 3 MB
OS003 Other Submission by John Coxon on behalf of Martin Bunney (r)
This submission by an non-Interested Party has been accepted by the Hinkley Examining Authority
Other
Size: 276 KB
OS010 Other Submission by Steve Smith (r)
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 39 KB
OS004 Other Submission by Adrian Goolden (r)
This submission by an non-Interested Party has been accepted by the Hinkley Examining Authority
Other
Size: 48 KB
OS001 Other Submission by David Coles (r)
This submission by an non-Interested Party has been accepted by the Hinkley Examining Authority
Other
Size: 50 KB
OS009 Other Submission by Andrew Vickery (r)
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 73 KB
OS006 Other Submission by John White (r)
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 128 KB
OS005 Other Submission by Durleigh Parish Council (Sidaway) (r)
This late submission has been accepted by the Hinkley Examining Authority
Other
Size: 84 KB
OS007 Other Submission by Janet M Willis (r)
This late submission by a non-Interested Party has been accepted by the Hinkley Examining Authority
Other
Size: 172 MB
EN010001-005862 Audio Recording AM
Other
Size: 152 MB
EN010001-005860 Audio Recording AM
Other
Size: 172 MB
120516 EN010001 Audio Recording PM
Other
Size: 118 MB
120517 EN010001 Audio Recording PM
Other
Size: 529 KB
120517 EN010001 John Lucas survey (R)
Public Rights of Way usage data referred to in John Lucas' oral submission made on behalf of West Hinkley Action Group
Other
Size: 2 MB
120517 EN010001 submission from Mr A Sellick
Speaking notes used by Sarah Dray on behalf of Brandon Sellick which contain data that was referred to in her oral submission
Other
Size: 70 MB
120522 EN010001 Steart EA planning application plans
Plans which accompany the planning permission granted by SDC for the Environment Agency's Steart Peninsula planning application
Other
Size: 10 MB
120411 EN010001 Site Visit - Main Site Information by EDF
Hinkley Point C site visit itinerary and site details supplied by the applicant.
Other
Size: 13 MB
120412 EN010001 Site Visit - Associated Development Plans by EDF
Hinkley Point C site visit itinerary and site details supplied by the applicant.
Other
Size: 53 KB
120515 EN010001 RULE 17 request to EDF regarding CA queries
Request for further information by the Examining Authority to EDF
Other
audio recording
Size: 126 MB
120509 EN010001 Audio Recording AM - Part 1
Other
audio recording
Size: 148 MB
120509 EN010001 Audio Recording PM
Other
audio recording
Size: 104 MB
120509 EN010001 Audio Recording AM - Part 2
Other
audio recording
Size: 154 MB
120510 EN010001 Audio Recording AM
Other
audio recording
Size: 94 MB
120510 EN010001 Audio Recording PM
Other
Size: 78 KB
120503 EN010001 SCG001 North Somerset Council
Statement of Common Ground between EDF Energy and North Somerset Council
Other
Size: 1 MB
120503 EN010001 SCG009 Natural England
Statement of Common ground between EDF Energy and Natural England
Other
Size: 144 KB
120503 EN010001 LIR003 Taunton Deane BC
Local Impact Report submitted by Taunton Deane BC
Other
Size: 3 MB
WR064 Written Representation by Lyn Macnab
Other
Size: 79 KB
120503 EN010001 SCG007 02 WSC & SDC Letter
Statement of Common ground Explanatory schedule (02) letter from West Somerset Council & Sedgemoor District Council
Other
Size: 183 KB
WR030 Written Representation by Bridgwater Bay Wildfowlers Association
Other
Size: 19 MB
WR037 Written Representation by Crispin Aubrey (Stop Hinkley)
Other
Size: 2 MB
WR015 Written Representation by Sean Morris (Nuclear Free Local Authorities)
Other
Size: 1 MB
WR023 Written Representation by Sheila Allen
Other
Size: 17 KB
WR011 Written Representation by John French
Other
Size: 4 MB
WR041 Written Representation by Devon and Somerset Fire & Rescue Service
Other
Size: 1 MB
WR012 Written Representation by Peter Smith
Other
Size: 3 MB
WR051 Written Representation by Avon and Somerset Constabulary
Other
Size: 362 KB
120503 EN010001 SCG011 CCW
Statement of Common ground between EDF Energy and the Countryside Council for Wales
Other
Size: 7 MB
120503 EN010001 SCG007 WSC SDC SCC
Statement of common ground between EDF Energy and Somerset County Council, West Somerset Coucil & Sedgemoor District Council
Other
Size: 333 KB
120503 EN010001 SCG010 Environment Agency
Statement of Common ground between EDF Energy and the Environment Agency
Other
Size: 168 KB
WR049 Written Representation by Marine Management Organisation (Peters)
Other
Size: 576 KB
WR009 Written Representation by Grant Edwards
Other
Size: 3 MB
120305 EN010001 SCG005 Quantock AONB
Statement of Common ground between EDF Energy and Quantock AONB
Other
Size: 812 KB
120503 EN010001 SCG008 MMO
Statement of Common ground between EDF Energy and the Marine Management Organisation.
Other
Size: 1 MB
120503 EN010001 SCG006 Taunton Deane BC
Statement of Common ground between EDF Energy and Taunton Deane BC
Other
Size: 293 KB
120503 EN010001 SCG007 01 SCC Letter
Statement of Common ground Explanatory schedule (01) letter from Somerset County Council
Other
Size: 2 MB
WR019 Written Representation by Richard and Marion Oerton
Other
Size: 44 KB
WR032 Written Representation by Richard Evans (Cumbria County Council)
Other
Size: 454 KB
120503 EN010001 SCG002 Highways Agency
Statement of Common ground between EDF Energy and the Highways Agency
Other
Size: 45 MB
WR043 Written Representation by Fairfield Estate
Other
Size: 26 KB
WR053 Written Representation by Valerie Boxall
Other
Size: 14 KB
WR057 Written Representation by Kathleen Edwards
Other
Size: 473 KB
WR025 Written Representation by Barry Prickett
Other
Size: 2 MB
WR040 Written Representation by Nick Freer (Hallam Land Management)
Other
Size: 3 MB
WR033 Written Representation by Richard Cuttell
Other
Size: 10 MB
WR060 Written Representation by EDF Energy NNB
Other
Size: 1 MB
WR020 Written Representation by Barry Leathwood (Otterhampton Parish Council)
Other
Size: 52 KB
120503 EN010001 LIR001 North Somerset Council
Local Impact Report submitted by North Somerset Council
Other
Size: 16 KB
WR063 Written Representation by NATS (En Route) Ltd
Other
Size: 711 KB
WR052 Written Representation by Greenpeace (George)
Other
Size: 186 KB
WR034 Written Representation by Somerset PCT and Bridgwater Bay Health Federation
Other
Size: 711 KB
Other
Size: 98 KB
WR010 Written Representation by Eileen Shaw (Burnham and Highbridge Town Council)
Other
Size: 7 MB
WR048 Written Representation by The Highways Agency
Other
Size: 5 MB
WR014 Written Representation by Steve Smith
Other
Size: 5 MB
WR058 Written Representation by Nicola Clark
Other
Size: 15 KB
WR044 Written Representation by Ornella Saibene
Other
Size: 7 MB
WR007 Written Representation by David Penney
Other
Size: 12 MB
WR065 Written Representation by Natural England
Other
Size: 402 KB
120503 EN010001 SCG003 Internal Drainage Board
Statement of Common ground between EDF Energy and the Internal Drainage Board
Other
Size: 708 KB
WR024 Written Representation by Linda Allen
Other
Size: 118 KB
WR050 Written Representation by South Somerset District Council (Cardnell)
Other
Size: 64 KB
120503 EN010001 LIR002 Bath and North East Somerset Council
Local Impact Report submitted by Bath and North East Somerset Council
Other
Size: 69 KB
WR062 Written Representation by Fulcrum Pipelines Limited
Other
Size: 1 MB
WR004 Written Representations by Mrs Aly Prowse
Other
Size: 21 KB
WR017 Written Representation by Gary Perrett (HP Cycle Group)
Other
Size: 58 KB
WR039 Written Representation by Charles Graham
Other
Size: 576 KB
WR047 Written Representation by Countryside Council for Wales
Other
Size: 15 KB
WR008 Written Representation by Peter Nicholson (Burnham Water Users Forum)
Other
Size: 2 MB
WR022 Written Representation by Thomas Boyd
Other
Size: 55 KB
WR026 Written Representation by John Lucas
Other
Size: 224 KB
WR056 Written Representation by Office for Nuclear Regulation (Potter)
Other
Size: 683 KB
Other
Size: 10 MB
WR013 Written Representation by Cecily Collingridge
Other
Size: 165 KB
WR031 Written Representation by Cllr John Edwards (Spaxton Parish Council)
Other
Size: 59 MB
120514 EN010001 SDC RULE 17 NE Bridgwater Application
Planning permission and legal agreement in respect of the NE Bridgwater application.
Other
Size: 143 KB
120514 EN010001 SDC RULE 17 Steart Peninsula Project Decision Notice
Planning Permission Decision Notice by SDC for the Steart Peninsula Environment Agency application
Other
Size: 199 KB
120503 EN010001 SCG007 03 WSC SDC SCC Explanatory schedule
Statement of common ground Explanatory schedule (03) between EDF Energy and Somerset County Council, West Somerset Coucil & Sedgemoor District Council
Other
Size: 15 KB
WR005 Written Representation by David Griffiths
Other
Size: 2 MB
WR006 Written Representation by Jo Brown (PCAH)
Other
Size: 2 MB
WR036 Written Representation by Josephine Smoldon and Ian Horsfield
Other
Size: 32 KB
WR003 Written Representation by the Civil Aviation Authority
Other
Size: 976 KB
WR002 Written Representation by Ronald Allen
Other
Size: 602 KB
WR028 Written Representation by Greta Kendrick
Other
Size: 558 KB
WR027 Written Representation by Susan Lilienthal
Other
Size: 18 KB
WR038 Written Representation by Parrett Internal Drainage Board (Iain Sturdy)
Other
Size: 706 KB
WR018 Written Representation by Michael John Short
Other
Size: 589 KB
120503 EN010001 SCG004 English Heritage
Statement of Common ground between EDF Energy and English Heritage
Other
Size: 231 KB
WR035 Written Representation by Cllr Anne Reed (Wembdon Parish Council)
Other
Size: 8 MB
WR001 Written Representation by West Hinkley Action Group (WHAG)
Other
Size: 52 KB
WR054 Written Representation by Blackwater Against New Nuclear Group (Blowers)
Other
Size: 272 KB
WR046 Written Representation by Peter Greig (Quantock Cluster Parishes)
Other
Size: 19 MB
WR061 Written Representation by Innovia Cellophane Limited and Innovia Films Limited
Other
Size: 862 KB
WR016 Written Representation by John Andrews (Chilton Trinity Parish Council)
Other
Size: 113 KB
WR029 Written Representation by Stuart Hill
Other
Size: 511 KB
WR059 Written Representation by Jon Goodson
Other
Size: 481 KB
WR021 Written Representation by John and Maureen Randall
Other
Size: 783 KB
WR045 Written Representation by Environment Agency (Gupta)
Representation from Nick Gupta on behalf of The Environment Agency
Other
Size: 61 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 2.22 - 2.36
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 2.22 - 2.36.
Other
Size: 48 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 2.7 - 2.21
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 2.7 - 2.21.
Other
Size: 50 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 10 - 12
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 10 - 12.
Other
Size: 45 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 2.37 - 2.44
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 2.37 - 2.44.
Other
Size: 50 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 4 - 9
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 4 - 9.
Other
Size: 81 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 2.45
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 2.45.
Other
Size: 48 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 3
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 3.
Other
Size: 27 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 2.49 - 2.60
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 2.49 - 2.60.
Other
Size: 39 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 2.1 - 2.6 and document list
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes appendix C 2.1 - 2.6 and document list.
Other
Size: 34 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 13 - 23
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 13 - 23.
Other
Size: 72 MB
120503 EN010001 SDC WSC SCC Joint LIR - Local Impact Report, Executive summary and Appendix A
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes local impact report, executive summary and appendix A.
Other
Size: 55 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix C 2.46 - 2.48
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes Appendix C 2.46 - 2.48.
Other
Size: 32 MB
120503 EN010001 SDC WSC SCC Joint LIR - Appendix B
Local Impact Report submitted by Sedgemoor District Council, West Somerset Council and Somerset County Council. This part includes appendix B.
Other
Size: 277 KB
120411 EN010001 Proposed SV view points by Stogursey PC
Hinkley Point C site visit - suggested viewing points / site locations by Stogursey Parish Council
Other
Size: 52 MB
Addendum Combwich - Junction 23 Flood Risk Assessment Modelling Report 1
Other
Size: 554 KB
120404 EN010001 WSC Prelim works Plan-6.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 393 KB
120404 EN010001 WSC Prelim works Annex-10.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 2 MB
120404 EN010001 WSC Prelim works Annex-13.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 541 KB
120404 EN010001 WSC Prelim works Plan-7.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 1 MB
120404 EN010001 WSC Deed-of-Planning-Obligations-pages-45-to-85.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 349 KB
120404 EN010001 WSC Prelim works Annex-3.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 523 KB
120404 EN010001 WSC Prelim works Plan-8.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 453 KB
120404 EN010001 WSC Prelim works Annex-12.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 555 KB
120404 EN010001 WSC Prelim works Plan-1.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 226 KB
120404 EN010001 WSC Prelim works Annex-11.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 33 MB
Subsitute Plans 1
Other
Size: 686 KB
120404 EN010001 WSC Prelim works Plan-3.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 12 MB
Cover Letter to Addenda - Plans and Associated Schedules 1
Other
Size: 410 KB
120404 EN010001 WSC Prelim works decison notice
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 236 KB
120404 EN010001 WSC Prelim works Annex-5.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 400 KB
120404 EN010001 WSC Prelim works Plan-9.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 45 KB
120404 EN010001 WSC Prelim works Annex-7.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 25 MB
Addendum to the Environmental Statement-Appendices 1
Other
Size: 6 MB
120404 EN010001 WSC Prelim works Annex-6.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 898 KB
120404 EN010001 WSC Prelim works Plan-5.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 2 MB
120404 EN010001 WSC Deed-of-Planning-Obligations-pages-1-to-44.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 773 KB
120404 EN010001 WSC Prelim works Annex-4.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 466 KB
Part 1 Schedule of Application Documents and Reference Documents 1
Other
Size: 876 KB
Part 2 Revised Drawing Schedule 1
Other
Size: 1 MB
120404 EN010001 WSC Prelim works Annex-2.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 60 KB
Part 4 Amendments to Highways Improvements Flood Risk Assessment 1
Other
Size: 1 MB
120404 EN010001 WSC Prelim works Plan-10.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 2 MB
120404 EN010001 WSC Prelim works Annex-1.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 527 KB
120404 EN010001 WSC Prelim works Plan-2.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 848 KB
120404 EN010001 WSC Prelim works Annex-8.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 130 KB
120404 EN010001 WSC Prelim works Annex 9.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 2 MB
120404 EN010001 WSC Prelim works Plan-4.PDF
Further information requested by the Panel under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010
Other
Size: 6 MB
Addendum to the Environmental Statement 1
Other
Size: 45 KB
Part 3 Amendments to Book of Reference 1
Other
Size: 3 MB
EN010001 Response to First Round of ExA Questions by Parent Concerned aBout Hinkley (PCAH)
Other
Size: 7 MB
EN010001 Response to First Round of ExA Questions by EDF
Other
Size: 642 KB
Other
Size: 107 KB
EN010001 Response to First Round of ExA Questions by Office for Nuclear Regulation (ONR)
Other
Size: 67 KB
120424 EN010001 Procedural Decision Correction
Other
Size: 55 KB
120424 EN010001 Procedural decision regarding proposed changes to the application
Other
Size: 255 KB
120314 EN010001 letter to IPC from WSC and SDC about funding(r)
Other
Size: 23 KB
120314 EN010001 Email re PM issues by Stop Hinkley (Attwater) (R)
Other
Size: 5 MB
120314 EN010001 Email re PM attendance by Stop Hinkley2(r)
Other
Size: 27 KB
120308 EN010001 Email re PM attendance by Steve Smith (R)
Other
Size: 25 KB
120313 EN010001 Email re PM attendance by Bown (R)
Other
Size: 40 KB
120217 EN010001 Email re Stogursey SV by Ms Lesley Flash (R)
Other
Size: 28 KB
120218 EN010001 Email re rule 6 principal issues Stogursey by Mr John Lucas (R)
Other
Size: 15 KB
120229 EN010001 Email re PM attendance by R H Allen (R)
Other
Size: 22 KB
120314 EN010001 Email re PM attendance by Bown (R)
Other
Size: 14 KB
120214 EN010001 Email re PM Issues by Ms Cecily Collingridge.(R)
Other
Size: 184 KB
120314 EN010001 response to Rule 6 from Sedgemooor and West Somerset Councils(r)
Other
Size: 16 KB
120310 EN010001 Email re PM attendance by Elizabeth Browning 2 (R)
Other
Size: 42 KB
120217 EN010001 Email re PM venue by Mr Roy Pumfrey (R)
Other
Size: 14 KB
120217 EN010001 Email re Stogursey SV by L S Jones (R)
Other
Size: 47 KB
120319 EN010001 Hinkley PM submission by Richard George of Greenpeace UK(r)
Other
Size: 64 KB
Other
Size: 367 KB
120314 EN010001 Email re PM attendance by CCW (R)
Other
Size: 60 KB
120224 EN010001 Email re IPC refs by Cllr Lesley Flash (R)
Other
Size: 48 KB
120316 EN010001 Hinkley PM submission by STA (r)
Other
Size: 14 KB
120314 EN010001 Email re PM attendance by Dr Jill Sutcliffe (R)
Other
Size: 808 KB
120220 EN010001 Letter re PM by West Somerset Council (R)
Other
Size: 20 KB
120316 EN010001 Hinkley PM submission by Cannington PC(r)
Other
Size: 54 KB
120314 EN010001 Email re PM attendance by PCAH (r)
Other
Size: 112 KB
120319 EN010001 Hinkley PM submission by Alan Debenham (r)
Other
Size: 66 KB
120321 EN010001 Hinkley PM submission by Alan Debenham(r)
Other
Size: 1 MB
120222 EN010001 Letter to Kerry Rickards from EDF (Mayson) (R)
Other
Size: 25 KB
120312 EN010001 Email re PM attendance by Lesley Susan Jones (R)
Other
Size: 14 KB
120304 EN010001 Email re STOGURSEY by Mr & Mrs Bartlett (R)
Other
Size: 14 KB
120305 EN010001 Email re STOGURSEY issues by Aubrey Knowles (R)
Other
Size: 15 KB
120316 EN010001 Email re PM attendance by Quantock Hills AONB Service(r)
Other
Size: 15 KB
120314 EN010001 Email re PM attendance by G Davis (R)
Other
Size: 38 KB
120308 EN010001 Email re PM attendance by Julian Taylor (R)
Other
Size: 14 KB
120312 EN010001 Email re PM attendance by Bridgwater Town Council (R)
Other
Size: 15 KB
120222 EN010001 Email re SV before preliminary works by Julian Lewis (R)
Other
Size: 35 KB
120314 EN010001 Email re PM attendance by Alex Reed (R)
Other
Size: 141 KB
120227 EN010001 Letter re scheme from John Atton (R)
Other
Size: 37 KB
120314 EN010001 Email re PM attendance by Gifford (R)
Other
Size: 15 KB
120314 EN010001 Email re PM attendance by Highways Agency (R)
Other
Size: 12 KB
120302 EN010001 Email re STOGURSEY (inc SV) issues by Mr Peter Montague (R)
Other
Size: 45 KB
120301 EN010001 Email re STOGURSEY issues status by WHAG (Farmery) (R)
Other
Size: 18 KB
120213 EN010001 Email re scheme changes by Cllr Val Bannister (R)
Other
Size: 57 KB
120310 EN010001 Email re PM attendance by Devon & Somerset Fire and Rescue (R)
Other
Size: 470 KB
120217 EN010001 Letter to MP from Leader of West Somerset Council re Stogursey & Hinkley Point (R)
Letter from the Leader of West Somerset Council to Sir Michael Pitt (Chair of the IPC) regarding the Parish of Stogursey
Other
Size: 24 KB
120301 EN010001 Email re representation by John Busby (R)
Other
Other
Size: 15 KB
120314 EN010001 Email re PM attendance by Rev Chadwick (r)
Other
Size: 381 KB
120314 EN010001 Email re PM attendance by Innovia Cellophane (r)
Other
Size: 358 KB
120312 EN010001 Follow letter re Stogursey issues by Margaret Brown (R)
Other
Size: 106 KB
120316 EN010001 Email re PM attendance by Avon & Somerset Police(r)
Other
Size: 15 KB
120304 EN010001 Email re STOGURSEY by Ms Davina Williams (AP) (R)
Other
Size: 42 KB
120316 EN010001 Hinkley PM submission by North Somerset NHS(r)
Other
Size: 11 KB
120316 EN010001 Email re PM attendance by Frances Fawkes(r)
Other
Size: 12 KB
120310 EN010001 Email re PM attendance by Elizabeth Browning 1 (R)
Other
Size: 60 KB
120321 EN010001 Hinkley PM submission by Somerset Tourism Association(r)
Other
Size: 854 KB
120314 EN010001 Letter re PM ISSUES by Somerset County Council (R)
Other
Size: 150 KB
120319 EN010001 Hinkley PM submission by PCAH(r)
Other
Size: 18 KB
120306 EN010001 Email re STOGURSEY SV by Cllr Val Bannister (R)
Other
Size: 17 KB
120214 EN010001 Email re lack of Stogursey issue or hearing by Mr John Lucas (R)
Other
Size: 15 KB
120309 EN010001 Email re PM attendance by David Griffiths (R)
Other
Size: 25 KB
120316 EN010001 Email re PM attendance by Nick Freer (r)
Other
Size: 25 KB
120316 EN010001 Hinkley PM submission byTracey Pike(r)
Other
Size: 281 KB
120316 EN010001 Email re PM attendance by Fiddington Parish Council(r)
Other
Size: 14 KB
120306 EN010001 Email re STOGURSEY (Shurton) by Cara Lynch-Blosse (non-IP) (R)
Other
Size: 407 KB
120221 EN010001 Letter re PM by Christopher Gifford re Hinkley Point (R)
Other
Size: 351 KB
120227 EN010001 Letter re nuclear safety by Christopher Gifford (R)
Other
Size: 46 KB
120214 EN010001 Email re PM Issues by Mr Roy Pumfrey (R)
Other
Size: 25 KB
120314 EN010001 Email re PM attendance by Durleigh PC (R)
Other
Size: 45 KB
120309 EN010001 Email re PM attendance by Lucinda Garrett (R)
Other
Size: 24 KB
120301 EN010001 Email re PM attendance by Cllr Trollope-Bellew (R)
Other
Size: 15 KB
120215 EN010001 Email re PM ISSUES by Mr Boyd. (R)
Other
Size: 185 KB
120305 EN010001 Letter re PM attendance by Mrs S E Jones (R)
Other
Size: 242 KB
120217 EN010001 Letter re PM & other queries by Margaret Roberts (R)
Other
Size: 14 KB
120314 EN010001 Email re PM attendance by Embelton (R)
Other
Size: 46 KB
120302 EN010001 Email follow up re PM attendance by PCAH (Brown) (R)
Other
Size: 14 KB
120218 EN010001 Email re STOGURSEY SV by Graham & Jean Howard (R)
Other
Size: 92 KB
120313 EN010001 Email re PM attendance by Reed (R)
Other
Size: 17 KB
120214 EN010001 Email re lack Stogursey hearing by Jean & Graham Howard (R)
Other
Size: 25 KB
120313 EN010001 Email re PM attendance by Magnox Ltd and NDA.(R)
Other
Size: 428 KB
120316 EN010001 Email re PM attendance by South Glos LA (r)
Other
Size: 42 KB
120314 EN010001 Email re PM attendance by Malcolm Reid (r)
Other
Size: 17 KB
120219 EN010001 Email re governance issue by Mrs Jane Crowe (R)
Other
Size: 538 KB
120210 EN010001 Greenpeace Letter (PM Issues) (R)
Other
Size: 16 KB
120221 EN010001 Email to Sir Michael re ExA appointment by Jane Taunton (R)
Other
Size: 14 KB
120217 EN010001 Email re STOGURSEY SV by Cara Lynch-Blosse (R)
Other
Size: 14 KB
120316 EN010001 Email re PM attendance by Cllr David Baker(r)
Other
Size: 141 KB
120321 EN010001 PM Submission by Combwich Area Immediate Residents(r)
Other