Norfolk Boreas

You can filter the results to show only the items that match your interest.

Date

SourceDescription
Other
Size: 69 KB
The Old Railway Gatehouse
Deadline 7 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 209 KB
Necton Substation Action Group
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 74 KB
Necton Parish Council
Deadline 7 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 254 KB
Oulton Parish Council
Deadline 7 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 7 Submission - 8.3 Design and Access Statement (Tracked Changes) (Version 4)
Other
Size: 989 KB
Norfolk Boreas Limited
Deadline 7 Submission - Hornsea Project Three Construction Traffic Noise Assessment Clarification Note
Other
Size: 107 KB
Colin King
Deadline 7 Submission - Response to the Applicant's Comments to Deadline 5 Submission
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 7 Submission - 8.3 Design and Access Statement (Version 4) (Part 1 of 4)
Other
Size: 29 MB
Necton Substation Action Group
Deadline 7 Submission - 3D view of buildings inside one Vattenfall convertor building
Other
Size: 798 KB
Norfolk Boreas Limited
Deadline 7 Submission - Offshore Ornithology Assessment Update - Project Alone Collision Risk Modelling (Clean) (Version 2)
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 7 Submission - In Principle Habitats Regulations Derogation Provision of Evidence
Other
Size: 570 KB
Norfolk Boreas Limited
Deadline 7 Submission - 8.12 Offshore In Principle Monitoring Plan (Tracked Changes) (Version 4)
Other
Size: 301 KB
Marine Management Organisation
Deadline 7 Submission - Written Response to Deadline 7
Other
Size: 711 KB
Natural England
Deadline 7 Submission - Response to Examining Authority's third round of Written Questions
Other
Size: 232 KB
Natural England
Deadline 7 Submission - DCO Documents Submitted at Deadline 5 and 6
Other
Size: 820 KB
Norfolk Boreas Limited
Deadline 7 Submission - 8.12 Offshore In Principle Monitoring Plan (Clean) (Version 4)
Other
Size: 137 KB
Necton Substation Action Group
Deadline 7 Submission - Submission on consultation
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 7 Submission - 8.3 Design and Access Statement (Clean) (Version 4)
Other
Size: 328 KB
Cawston Parish Council
Deadline 7 Submission - Cawston Residents Survey
Other
Size: 2 MB
Natural England
Deadline 7 Submission - Risk and Issues Log
Other
Size: 664 KB
Norfolk Boreas Limited
Deadline 7 Submission - Updated Joint Position Statement Noise Sensitive Receptors
Other
Size: 83 KB
Necton Substation Action Group
Deadline 7 Submission - Lighting at Necton Substation
Other
Size: 985 KB
Norfolk Boreas Limited
Deadline 7 Submission - Applicant's Comments on Deadline 6 Submissions and Other Submissions
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 7 Submission - 3.1 Norfolk Boreas Updated Draft DCO (Clean) (Version 6)
Other
Size: 442 KB
Natural England
Deadline 7 Submission - Advice on Norfolk Boreas Updated Cumulative (EIA) and In-Combination (HRA) Collision Risk Offshore Ornithological Assessment
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 7 Submission - 8.15 Proposed Sediment Disposal Sites Site Characterisation Report (Clean) (Version 3)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 7 Submission - 8.3 Design and Access Statement - (Version 4) (Part 2 of 4)
Other
Size: 661 KB
Norfolk Boreas Limited
Deadline 7 Submission - Compulsory Acquisition Objections Schedule (Tracked Changes) (Version 3)
Other
Size: 44 KB
Norfolk Boreas Limited
Deadline 7 Submission - Cover Letter
Other
Size: 121 KB
Necton Substation Action Group
Deadline 7 Submission - Submission in relation to photomontages
Other
Size: 296 KB
Public Health England
Deadline 7 Submission - Responses to Examining Authority's third round of written questions
Other
Size: 343 KB
Natural England
Deadline 7 Submission - Updated Ornithology Advice
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 7 Submission - Applicant's Responses to the Examining Authority's Third Round of Written Questions Appendices - Section 12 - Appendix 12.1 (Q3.12.0.3)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 7 Submission - 3.1 Norfolk Boreas Updated Draft DCO (Tracked Changes) (Version 6)
Other
Size: 325 KB
Natural England
Deadline 7 Submission - Response to Applicant's Responses to Examining Authority's Further Written Questions
Other
Size: 472 KB
Environment Agency
Deadline 7 Submission - Responses to Examining Authority's third round of Written Questions
Other
Size: 299 KB
Natural England
Deadline 7 Submission - Comments on the Applicant's Haisborough Hammond and Winterton SAC Position Paper of February 2020
Other
Size: 696 KB
Norfolk Boreas Limited
Deadline 7 Submission - In Principle Habitats Regulations Derogation, Provision of Evidence - Appendix 4 Summary of Consultation
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 7 Submission - 8.3 Design and Access Statement - (Version 4) (Part 3 of 4)
Other
Size: 94 KB
Natural England
Deadline 7 Submission - Response to Updated Habitat Regulations Assessment Screening and Integrity Matrices
Other
Size: 73 MB
Necton Substation Action Group
Deadline 7 Submission - 3D view of proposed substation convertor hall Vs Necton Farm Barn and Dudgeon
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 7 Submission - 8.3 Design and Access Statement - (Version 4) (Part 4 of 4)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 7 Submission - In Principle Habitats Regulations Derogation Provision of Evidence - Appendix 2 Alde-Ore Estuary SPA In Principle Compensation
Other
Size: 70 KB
Margaret Woodall
Deadline 7 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 98 KB
Broadland District Council
Deadline 7 Submission - Response to Examining Authority's third round of Written Questions
Other
Size: 127 KB
Water Management Alliance
Deadline 7 Submission - update on response to Further Written Questions
Other
Size: 131 KB
The Royal Society for the Protection of Birds
Deadline 7 Submission - Response to Examining Authority's third round of Written Questions
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 7 Submission - Applicant's Responses to the Examining Authority's Third Round of Written Questions Appendices - Section 14 - Appendices 14.1 (Q3.14.1.8) and 14.2 (Q3.14.4.9)
Other
Size: 849 KB
Norfolk Boreas Limited
Deadline 7 Submission - Offshore Ornithology Assessment Update - Project Alone Collision Risk Modelling (Tracked Changes) (Version 2)
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 7 Submission - Applicant's Responses to the Examining Authority's Third Round of Written Questions Appendices - Section 8 - Appendix 8.1 (Q3.8.3.5)
Other
Size: 1 MB
Necton Substation Action Group
Deadline 7 Submission - Comparative sizing of the convertor buildings
Other
Size: 695 KB
National Farmers Union and Land Interest Group
Deadline 7 Submission - Response to Examining Authority's third round of Written Questions
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 7 Submission - Applicant's Responses to the Examining Authority's Third Round of Written Questions Appendices - Section 9 - Appendix 9.1 (Version 2) Appendix 9.2 (Q3.9.3.1)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 7 Submission - Applicant's Responses to the Examining Authority's Third Round of Written Questions
Other
Size: 970 KB
Norfolk Boreas Limited
Deadline 7 Submission - Schedule of Changes to the draft Development Consent Order (Clean) (Version 5)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 7 Submission - Position Statement Church Road, Colby
Other
Size: 152 KB
Necton Substation Action Group
Deadline 7 Submission - Submission on the visibility of the proposed development from Necton or Ivy Todd
Other
Size: 7 MB
Norfolk Boreas Limited
Deadline 7 Submission - Funding Agreement
Other
Size: 343 KB
Marine Management Organisation
Deadline 7 Submission - Response to Norfolk Vanguard Secretary of State Letter dated 06 December 2019
Other
Size: 817 KB
Norfolk Boreas Limited
Deadline 7 Submission - Applicant's Guide to the Application
Other
Size: 359 KB
Natural England
Deadline 7 Submission - Response to Applicant's Comments on Deadline 4 Submissions
Other
Size: 101 KB
Natural England
Deadline 7 Submission - Cover Letter
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 7 Submission - In Principle Habitats Regulation Derogation Provision Evidence - Appendix 1 Flamborough and Filey Coast SPA In Principle Compensation
Other
Size: 265 KB
Marine Management Organisation
Deadline 7 Submission - Response to Examining Authority's third round of Written Questions
Other
Size: 307 KB
Natural England
Deadline 7 Submission - Updated Ornithology Collision Risk Modelling Advice
Other
Size: 702 KB
Norfolk Boreas Limited
Deadline 7 Submission - Compulsory Acquisition Objections Schedule (Clean) (Version 3)
Other
Size: 457 KB
Norfolk County Council
Deadline 7 Submission - Response to Further Written Questions - Intended for Deadline 5
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 7 Submission - Norfolk Vanguard Environmental Assessment of Trenchless Crossings at the B1149
Other
Size: 456 KB
Necton Substation Action Group
Deadline 7 Submission - Comments on responses to Further Written Questions
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 7 Submission - In Principle Habitats Regulations Derogation, Provision of Evidence - Appendix 3 Haisborough, Hammond and Winterton SAC In Principle Compensation
Other
Size: 135 KB
Necton Substation Action Group
Deadline 7 Submission - Request for Statement of Common Ground with Necton Parish Council
Other
Size: 816 KB
Norfolk Boreas Limited
Deadline 7 Submission - Offshore Ornithology Update - Response to Natural England's Submission EV9-003 and Further Comments to REP4-040
Other
Size: 182 KB
Norfolk County Council
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 173 KB
Broadland District Council
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 186 KB
Necton Parish Council
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 91 KB
Phil Hayton
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 256 KB
Breckland Council
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 151 KB
The Royal Society for the Protection of Birds
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 172 KB
North Norfolk District Council
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 191 KB
Necton Substation Action Group
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 184 KB
Oulton Parish Council
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 510 KB
The Examining Authority's third round of Written Questions
Other
Size: 147 KB
Note of Unaccompanied Site Inspection up to 16 March 2020
The Examining Authority's updated USI record
Other
Size: 155 KB
Rule 8(3) change to the Examination Timetable
Other
Size: 286 KB
Cawston Parish Council
Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 149 KB
Oulton Parish Council
Deadline 9 Submission for Norfolk Vanguard - Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 432 KB
Oulton Parish Council
Norfolk Vanguard Noise Mitigation Measures at the Old Railway Gatehouse Position Statement - Issue Specific Hearing 6, Action Point 14 - Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 9 MB
Oulton Parish Council
Cover Email - Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 8 MB
Oulton Parish Council
Ørsted Hornsea Project Three (UK) Ltd - Appendix 23 - Construction Traffic Noise and Vibration Assessment at The Old Railway Gatehouse - Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 83 KB
Oulton Parish Council
Submission on Noise & Vibration for Ørsted Hornsea Project Three (UK) Ltd - Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 100 KB
Historic England
Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 21 KB
Natural England
Cover Letter - Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 78 KB
Natural England
Updated Ornithology Collision Risk Modelling Advice - Submission in lieu of attendance at Issue Specific Hearing 5 on Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 111 KB
Accompanied Site Inspection Itinerary 2
Other
Size: 191 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 5: Onshore and Offshore effects including the draft Development Consent Order
Other
Size: 100 KB
The Planning Inspectorate
Agenda for Compulsory Acquisition Hearing
Other
Size: 47 MB
Necton Substation Action Group
Deadline 6 - 3D view of proposed substation convertor hall with agricultural buildings at Oulton Street
Other
Size: 629 KB
Norfolk Boreas Limited
Deadline 6 Submission - Additional information for the HHW SAC position paper
Other
Size: 229 KB
Mark Lansley - Broadland Drinks Ltd
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 839 KB
Norfolk Boreas Limited
Deadline 6 Submission - Applicant's Comments on Deadline 5 Submissions
Other
Size: 704 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with The Wildlife Trusts and Norfolk Wildlife Trust (Version 3)
Other
Size: 786 KB
Norfolk Boreas Limited
Deadline 6 Submission - Offshore Ornithology - Assessment Update Cumulative and In-combination Collision Risk Modelling
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Eastern Inshore Fisheries and Conservation Authority (Version 2)
Other
Size: 698 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with National Farmers Union (Version 2)
Other
Size: 95 KB
David Vince & Nicola Draycott
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 112 KB
Ian G Nelson
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 996 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with North Norfolk District Council (Version 2)
Other
Size: 96 KB
Anna Hill
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 12 MB
Norfolk Boreas Limited
Deadline 6 Submission - Outline Norfolk Boreas Haisborough Hammond and Winterton Special Area of Conservation Cable Specification, Installation and Monitoring Plan - Annex 1
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 6 Submission - 5.3.5.3 Habitats Regulations Assessment - Appendix 5.3 - Screening Matrices (Version 4) (Tracked Changes)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 6 Submission - 6.6 Schedule of Mitigation (Version 3) (Tracked Changes)
Other
Size: 98 KB
Stephen Brown
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Broadland District Council (Version 2)
Other
Size: 2 MB
Necton Substation Action Group
Deadline 6 Submission - 3D views of Oulton barns with substation buildings
Other
Size: 764 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Natural England (Offshore Ornithology) (Version 3)
Other
Size: 85 KB
Andrew & Clare Parle
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 204 KB
Cawston Parish Council
Deadline 6 Submission - Comments on Responses to Further Written Questions
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Natural England (Version 3)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 6 Submission - Applicant's Comments on Responses to the Examining Authority's Further Written Questions
Other
Size: 682 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Orsted Hornsea Project Three (Version 2)
Other
Size: 848 KB
Norfolk Boreas Limited
Deadline 6 Submission - Applicant's Statement of Commonality of Statements of Common Ground
Other
Size: 710 KB
Norfolk Boreas Limited
Deadline 6 Submission - Headroom Position Paper and Examples
Other
Size: 558 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Royal Society of the Protection of Birds (Version 2)
Other
Size: 110 KB
Necton Substation Action Group
Deadline 6 Submission - Comments on Appendix 9.31 [APP-068]
Other
Size: 395 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Trinity House (Version 2)
Other
Size: 2 MB
Colin King
Deadline 6 Submission - Comments on Responses to Further Written Questions
Other
Size: 275 KB
Marine Management Organisation
Deadline 6 Submission - Comments on the Draft DCO and the Applicant's submissions at Deadline 5
Other
Size: 96 KB
Graham Whiteley
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 107 KB
Dota & Alan Williams
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 6 Submission - 8.20 Outline Norfolk Boreas Haisborough Hammond and Winterton Special Area of Conservation Site Integrity Plan (Version 3) (Clean)
Other
Size: 100 KB
Elliot Marks
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Norfolk County Council (Version 2)
Other
Size: 1,020 KB
Norfolk Boreas Limited
Deadline 6 Submission - Applicant's Guide to the Application (Version 8)
Other
Size: 21 KB
Nicola Banham
Deadline 6 Submission
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 6 Submission - 5.3.6.1 Habitats Regulations Assessment - Appendix 6.1 - Integrity Matrices (Version 4) (Tracked Changes)
Other
Size: 991 KB
Norfolk Boreas Limited
Deadline 6 Submission - 3.2 Explanatory Memorandum (Version 4) (Clean)
Other
Size: 981 KB
Norfolk Boreas Limited
Deadline 6 Submission - Additional information to the HHW SAC position paper - Annex 2 - Cable Protection Decommissioning Evidence
Other
Size: 777 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Environment Agency (Version 3)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 6 Submission - Position Statement on Derogation
Other
Size: 813 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Maritime and Coastguard Agency (Version 2)
Other
Size: 801 KB
Norfolk Boreas Limited
Deadline 6 Submission - Norfolk Boreas Compulsory Acquisition Objections Schedule (Version 2)
Other
Size: 707 KB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with National Association of Producer Organisations in Dutch Demersal Fisheries (VisNed) and National Federation of Fishermen’s Organisations (NFFO) (Version 2)
Other
Size: 591 KB
Norfolk Boreas Limited
Deadline 6 Submission - Joint Position Statement with North Norfolk District Council Noise Sensitive Receptors
Other
Size: 761 KB
Norfolk Boreas Limited
Deadline 6 Submission - 3.2 Explanatory memorandum (Version 4) (Tracked Changes)
Other
Size: 156 KB
Water Management Alliance
Deadline 6 Submission - Response to Further Written Questions - Intended for Deadline 5
Other
Size: 94 KB
Colin Jarry-Ryan
Deadline 6 Submission - Accepted at the discretion of the Examining Authority
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 6 Submission - Statement of Common Ground with Marine Management Organisation (Version 3)
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 6 Submission - Additional information for the HHW SAC position paper - Annex 4 - Assessment of Additional Mitigation in the Haisborough, Hammond and Winterton Special Area of Conservation (Version 2)
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 6 Submission - Additional information to the HHW SAC position paper - Annex 3 - BT Cable Recovery Letter of Comfort
Other
Size: 491 KB
Marine Management Organisation
Deadline 6 Submission - Comments on Responses to Further Written Questions
Other
Size: 917 KB
Oulton Parish Council
Deadline 6 Submission - Comments on Responses to Further Written Questions
Other
Size: 8 MB
North Norfolk District Council
Deadline 6 Submission - Comments on Responses to Further Written Questions; Responses to Further Written Questions; and Other Matters
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 6 Submission - 6.6 Schedule of Mitigation (Version 3) (Clean)
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 6 Submission - 8.20 Outline Norfolk Boreas Haisborough Hammond and Winterton Special Area of Conservation Site Integrity Plan (Version 3) (Tracked Changes)
Other
Size: 168 KB
Marine Management Organisation
Deadline 6 Submission - Response to Notification of Hearings
Other
Size: 677 KB
Necton Substation Action Group
Deadline 6 Submission - Comments on Responses to Further Written Questions
Other
Size: 44 KB
Norfolk Boreas Limited
Deadline 6 Submission - Cover Letter
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 6 Submission - 5.3.5.3 Habitats Regulations Assessment - Appendix 5.3 -  Screening Matrices (Version 4) (Clean)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 6 Submission - 5.3.6.1 Habitats Regulations Assessment - Appendix 6.1 - Integrity Matrices (Version 4) (Clean)
Other
Size: 208 KB
Breckland Council
Deadline 6 Submission - Response to Further Written Questions - Intended for Deadline 5
Other
Size: 25 KB
Natural England
Deadline 6 Submission - Cover Letter
Other
Size: 578 KB
Natural England
Deadline 6 Submission - Risk and Issues Log
Other
Size: 50 KB
Natural England
Deadline 6 Submission - Comments in Response to Offshore Issue Specific Hearing Action Points
Other
Size: 189 KB
Jenny Smedley
Deadline 6 Submission - Comments on Responses to Further Written Questions
Other
Size: 141 KB
The Royal Society for the Protection of Birds
Deadline 6 Submission - Comments on Responses to Further Written Questions
Other
Size: 86 KB
Natural England
Deadline 6 Submission - Comments on Norfolk Boreas approach to as-built vs consented turbine numbers and headroom in cumulative/in combination collision assessments
Other
Size: 132 KB
Eni UK Limited
Deadline 5 Submission
Other
Size: 943 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.3 Design and Access Statement (Version 3) (Clean)
Other
Size: 672 KB
Norfolk Boreas Limited
Deadline 5 Submission - Applicant's Guide to the Application (Version 7)
Other
Size: 696 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.14 Outline Project Environmental Management Plan (Version 2) (Clean)
Other
Size: 955 KB
Necton Substation Action Group
Deadline 5 Submission - Submissions on earth banks, National Grid extension location and Top Farm
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.17 In Principle Norfolk Boreas Southern North Sea Special Area of Conservation (SAC) Site Integrity Plan (Version 2) (Tracked Changes)
Other
Size: 709 KB
Norfolk Boreas Limited
Deadline 5 Submission - Offshore Ornithology Assessment Update, Project Alone Collision Risk Modelling
Other
Size: 76 KB
Necton Parish Council
Deadline 5 Submission - Representation on SoCG
Other
Size: 100 KB
Natural England
Deadline 5 Submission - Cover Letter
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.5 Outline Written Scheme of Investigation (Onshore) (Version 2) (Tracked Changes)
Other
Size: 12 MB
Norfolk Boreas Limited
Deadline 5 Submission - Aerial Photographs showing instances of significant effects on trees and woodlands
Other
Size: 928 KB
Norfolk Boreas Limited
Deadline 5 Submission - 3.3 Note on Requirements (Version 3)
Other
Size: 579 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.12 Offshore In Principle Monitoring Plan (Version 3) (Clean)
Other
Size: 12 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.8 Outline Traffic Management Plan Figures (Version 3)
Other
Size: 8 MB
Norfolk Boreas Limited
Deadline 5 Submission - The Haisborough Hammond and Winterton Special Area of Conservation Position Paper - Appendix 2
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 5 Submission - Applicant's Responses to the Examining Authority's Further Written Questions
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.7 Outline Landscape and Ecological Management Strategy (Version 3) (Tracked Changes)
Other
Size: 46 KB
Natural England
Deadline 5 Submission - Updated Onshore Ecology Advice
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.6 Outline Written Scheme of Investigation (Offshore) (Version 2) (Tracked Changes)
Other
Size: 157 KB
Norfolk Boreas Limited
Deadline 5 Submission - Schedule of Changes to the draft Development Consent Order (Version 4)
Other
Size: 74 KB
Orsted Hornsea Project Three
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 88 KB
Necton Substation Action Group
Deadline 5 Submission - Meeting with Breckland Council and request for Statement of Common Ground with Necton Parish Council
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 5 Submission - 3.1 Norfolk Boreas Updated Draft DCO (Version 5) (Tracked Changes)
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.8 Outline Traffic Management Plan Appendices (Version 3) (Clean)
Other
Size: 672 KB
North Norfolk District Council
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 82 KB
Tony Smedley
Deadline 5 Submission
Other
Size: 7 MB
Norfolk Boreas Limited
Deadline 5 Submission - Applicant’s Responses to the Examining Authority’s Further Written Questions Appendices Section 9
Other
Size: 509 KB
Natural England
Deadline 5 Submission - Responses to Examining Authority's Further Written Questions and Requests for Information (ExQ2)
Other
Size: 7 MB
Necton Substation Action Group
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 398 KB
Environment Agency
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 126 KB
Chris Allhusen
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 438 KB
Norfolk County Council
Deadline 5 Submission - Response to the Applicant's clarification note on trenchless crossings
Other
Size: 1,007 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.8 Outline Traffic Management Plan (Version 3) (Tracked Changes)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.16 Outline Scour Protection and Cable Protection Plan (Version 3) (Clean)
Other
Size: 940 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.1 Outline Code of Construction Practice (Version 3) (Clean)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 5 Submission - Applicant's Comments on Deadline 4 Submissions and Additional Submissions
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 5 Submission - Applicant's Responses to the Examining Authority's Further Written Questions Appendices Section 3
Other
Size: 319 KB
Norfolk Boreas Limited
Deadline 5 Submission - Method Statement for the crossing of Little London Road and adjacent features
Other
Size: 516 KB
National Grid
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 5 Submission - 6.7 EIA and DCO Reconciliation Document (Version 3) (Tracked Changes)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.6 Outline Written Scheme of Investigation (Offshore) (Version 2) (Clean)
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 5 Submission - 6.7 EIA and DCO Reconciliation Document (Version 3) (Clean)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 5 Submission - Revised Cawston Highway Intervention Scheme Road Safety Audit Decision Log
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.15 Proposed Sediment Disposal Sites Site Characterisation Report (Version 3) (Tracked Changes)
Other
Size: 692 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.23 Development Principles Layout Design Rules
Other
Size: 643 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.13 Draft Marine Mammal Mitigation Protocol (Version 2) (Clean)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.3 Design and Access Statement Figures (Version 3) (Part 2 of 4)
Other
Size: 408 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.11 Outline Offshore Operations and Maintenance Plan (Version 3) (Clean)
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.17 In Principle Norfolk Boreas Southern North Sea Special Area of Conservation (SAC) Site Integrity Plan (Version 2) (Clean)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 5 Submission - 4.1 Statement of Reasons (Version 2) (Tracked Changes)
Other
Size: 105 KB
Necton Parish Council
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 129 KB
The Wildlife Trusts
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 993 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.8 Outline Traffic Management Plan (Version 3) (Clean)
Other
Size: 511 KB
Marine Management Organisation
Deadline 5 Submission - Response to Further Written Questions; Comments on draft DCO; update on comments raised at Deadline 4
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.5 Outline Written Scheme of Investigation (Onshore) (Version 2) (Clean)
Other
Size: 565 KB
Necton Substation Action Group
Deadline 5 Submission - Plane crash contamination
Other
Size: 63 KB
Natural England
Deadline 5 Submission - Response to the Applicant's Summary of Oral Representations at Issue Specific Hearing 4 - Agenda Item 6a(i)
Other
Size: 546 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.12 Offshore In Principle Monitoring Plan (Version 3) (Tracked Changes)
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 5 Submission - The Haisborough Hammond and Winterton Special Area of Conservation Position Paper
Other
Size: 742 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.1 Outline Code of Construction Practice (Version 3) (Tracked Changes)
Other
Size: 131 KB
The Royal Society for the Protection of Birds
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 206 KB
Patricia Lockwood
Deadline 5 Submission
Other
Size: 219 KB
Maritime & Coastguard Agency
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.7 Outline Landscape and Ecological Management Strategy (Version 3) (Clean)
Other
Size: 272 KB
Oulton Parish Council
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 118 KB
Polly Brockis
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 648 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.13 Draft Marine Mammal Mitigation Protocol (Version 2) (Tracked Changes)
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.15 Proposed Sediment Disposal Sites Site Characterisation Report (Version 3) (Clean)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 5 Submission - Applicant's Comments on Relevant Representations Appendices (Version 2)
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 5 Submission - Applicant's Comments on Relevant Representations (Version 2)
Other
Size: 718 KB
Norfolk County Council
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 596 KB
Natural England
Deadline 5 Submission - Risk and Issue Log
Other
Size: 294 KB
Cawston Parish Council
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 64 KB
Natural England
Deadline 5 Submission - Advice on Applicant's Clarification Note on Optimising Cable Routing through the HHW SAC [REP4-022]
Other
Size: 550 KB
National Farmers Union
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 1 MB
Colin King
Deadline 5 Submission
Other
Size: 797 KB
Norfolk Boreas Limited
Deadline 5 Submission - 4.1 Statement of Reasons (Version 2) (Clean)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.16 Outline Scour Protection and Cable Protection Plan (Version 3) (Tracked Changes)
Other
Size: 585 KB
Norfolk Boreas Limited
Deadline 5 Submission - Position Statement Noise Sensitive Receptors
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.8 Outline Traffic Management Plan Appendices (Version 3) (Tracked Changes)
Other
Size: 707 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.14 Outline Project Environmental Management Plan (Version 2) (Tracked Changes)
Other
Size: 411 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.11 Outline Offshore Operations and Maintenance Plan (Version 3) (Tracked Changes)
Other
Size: 109 KB
Norfolk Boreas Limited
Deadline 5 Submission - Cover Letter
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 5 Submission - 3.1 Norfolk Boreas Updated Draft DCO (Version 5) (Clean)
Other
Size: 654 KB
Norfolk Boreas Limited
Deadline 5 Submission - Kittiwake Flight Speed
Other
Size: 950 KB
Norfolk Boreas Limited
Deadline 5 Submission - 8.3 Design and Access Statement (Version 3) (Tracked Changes)
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.3 Design and Access Statement Figures (Version 3) (Part 1 of 4)
Other
Size: 204 KB
Breckland Council
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 111 KB
Historic England
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.3 Design and Access Statement Figures (Version 3) (Part 3 of 4)
Other
Size: 134 KB
Eastern Inshore Fisheries and Conservation Authority
Deadline 5 Submission - Response to Further Written Questions
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 5 Submission - 8.3 Design and Access Statement Figures (Version 3) (Part 4 of 4)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 5 Submission - Position Statement Cawston Traffic
Other
Size: 636 KB
Norfolk Boreas Limited
Deadline 5 Submission - Issue Specific Hearings 3 and 4 Action Points Tracker (Version 2)
Other
Size: 134 KB
Rule 17 - Request for Further Information
Other
Size: 123 KB
Notification of hearings and Accompanied Site Inspection - March 2020
Other
Size: 612 KB
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 4 Submission - Written Summary of the Applicant's Oral Case at Issue Specific Hearing 4 - Offshore effects including the draft Development Consent Order
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 4 Submission - Written Summary of the Applicant's Oral Case at Issue Specific Hearing 3 - Onshore effects including the draft Development Consent Order
Other
Size: 739 KB
Norfolk Boreas Limited
Deadline 4 Submission - Schedule of Changes to the draft Development Consent Order (Version 3)
Other
Size: 109 KB
Historic England
Deadline 4 Submission - Post hearing submission
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 4 Submission - 3.1 Draft DCO (Clean) (Version 4)
Other
Size: 735 KB
Norfolk Boreas Limited
Deadline 4 Submission - Explanatory Memorandum (Tracked Changes) (Version 3)
Other
Size: 138 KB
UK Chamber of Shipping
Deadline 4 Submission - Responses to ExA’s Written Questions at Deadline 2
Other
Size: 686 KB
Norfolk Boreas Limited
Deadline 4 Submission - Orsted Hornsea Project Three BEIS Letter dated 31 October 2019
Other
Size: 209 KB
Natural England
Deadline 4 Submission - Post hearing submission
Other
Size: 45 KB
Norfolk Boreas Limited
Deadline 4 Submission - Cover Letter
Other
Size: 454 KB
Natural England
Deadline 4 submission - Updated Ornithology Advice
Other
Size: 83 KB
The Monk Family
Deadline 4 Submission - Post ASI Submission
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 4 Submission - Clarification Note - Trenchless Crossings B1149 and Church Road, Colby
Other
Size: 720 KB
Norfolk Boreas Limited
Deadline 4 Submission - Applicant's Comments on Responses to the Examining Authority's Written Questions - Late Submissions and Additional Comments received at Deadline 3
Other
Size: 41 MB
Necton Substation Action Group
Deadline 4 Submission - Any other information as requested by the ExA
Other
Size: 4 MB
Necton Substation Action Group
Deadline 4 Submission - Submission following the ASI regarding light pollution
Other
Size: 134 KB
Necton Parish Council
Deadline 4 Submission - Comments on Responses to ExA's Written Questions at Deadline 3
Other
Size: 8 MB
Norfolk Boreas Limited
Deadline 4 Submission - Clarification Note - Norfolk Vanguard Consultation Report Figure
Other
Size: 530 KB
Norfolk Boreas Limited
Deadline 4 Submission - Agenda for Cawston Traffic Meeting
Other
Size: 173 KB
North Norfolk District Council
Deadline 4 Submission - Post hearing submission
Other
Size: 187 KB
Necton Substation Action Group
Deadline 4 Submission
Other
Size: 2 MB
Colin King
Deadline 4 Submission
Other
Size: 411 KB
National Farmers Union
Deadline 4 Submission - Post hearing submission
Other
Size: 361 KB
Marine Management Organisation
Deadline 4 Submission - Post hearing submission
Other
Size: 45 KB
Natural England
Deadline 4 Submission - Updated Benthic Ecology Advice
Other
Size: 80 KB
Necton Substation Action Group
Deadline 4 Submission
Other
Size: 148 KB
Cawston Parish Council
Deadline 4 Submission - Post hearing submission
Other
Size: 175 KB
Breckland Council
Deadline 4 Submission - Post hearing submission - Response to Action Point 13 of the Issue Specific Hearing on onshore effects including the draft Development Consent Order
Other
Size: 480 KB
Norfolk Boreas Limited
Deadline 4 Submission - Applicant's Comments on Deadline 3 Submissions
Other
Size: 84 KB
Necton Substation Action Group
Deadline 4 Submission - Post hearing submission
Other
Size: 666 KB
Norfolk Boreas Limited
Deadline 4 Submission - 3.3 Note on Requirements and Conditions in the Development Consent Order (Version 2)
Other
Size: 590 KB
Natural England
Deadline 4 Submission - Updated Ornithology Advice - Comments in relation to the Norfolk Boreas updated offshore ornithological assessment, submitted at Deadline 2 [REP2-035]
Other
Size: 458 KB
Necton Substation Action Group
Deadline 4 Submission
Other
Size: 82 KB
Necton Parish Council
Deadline 4 Submission - Post ASI Submission
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 4 Submission - 3.1 Draft DCO (Tracked Changes) (Version 4)
Other
Size: 84 KB
Natural England
Deadline 4 Submission - Cover letter
Other
Size: 73 KB
Eastern Inshore Fisheries and Conservation Authority
Deadline 4 Submission - Post hearing submission - Response to Action Point 4 of the Issue Specific Hearing on offshore effects including the draft Development Consent Order
Other
Size: 476 KB
Norfolk Boreas Limited
Deadline 4 Submission - Clarification Note - Archaeological Interests and survey at the Landfall Site
Other
Size: 631 KB
Norfolk Boreas Limited
Deadline 4 Submission - Clarification Note - Stages and Phases
Other
Size: 465 KB
Norfolk Boreas Limited
Deadline 4 Submission - Clarification Note - Pre-commencement Works
Other
Size: 76 KB
Natural England
Deadline 4 Submission - Position Statement Regarding the Proposed Site Integrity Plan for the Haisborough Hammond and Winterton Special Area of Conservation
Other
Size: 1,021 KB
Norfolk Boreas Limited
Deadline 4 Submission - Clarification Note - Optimising cable routeing through the HHW SAC
Other
Size: 528 KB
Natural England
Deadline 4 Submission - Risk and Issues Log
Other
Size: 356 KB
Norfolk Boreas Limited
Deadline 4 Submission - Applicant's Response to Natural England's Onshore Ecology and Onshore Ornithology Deadline 3 Submissions
Other
Size: 85 KB
Jenny Smedley
Deadline 4 Submission - Post ASI Submission
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 4 Submission - Applicant's Responses to the Examining Authority's Written Questions Appendices - Section 9 - Appendices 9.5 and 9.6
Other
Size: 105 KB
Patricia Lockwood
Deadline 4 Submission
Other
Size: 18 MB
Necton Parish Council
Deadline 4 Submission - Post hearing submission
Other
Size: 5 MB
Necton Substation Action Group
Deadline 4 Submission
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 4 Submission - Technical Note - Revised Cawston Highway Intervention Scheme
Other
Size: 676 KB
Norfolk Boreas Limited
Deadline 4 Submission - Issue Specific Hearings 3 and 4 Action Points Tracker
Other
Size: 944 KB
Norfolk Boreas Limited
Deadline 4 Submission - Explanatory Memorandum (Clean) (Version 3)
Other
Size: 284 KB
Jenny Smedley
Deadline 4 Submission
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 4 Submission - Orsted Hornsea Three Cawston Highway Intervention Scheme
Other
Size: 722 KB
Norfolk Boreas Limited
Deadline 4 Submission - Applicant's Guide to the Application (Version 6)
Other
Size: 128 KB
Oulton Parish Council
Deadline 4 Submission - Post hearing submission
Other
Size: 111 KB
Note of Accompanied Site Inspection 1 on 23 January 2020
The Examining Authority's record of Accompanied Site Inspection 1 on 23 January 2020
Other
Size: 128 KB
Note of Unaccompanied Site Inspections up to 20 January 2020
The Examining Authority's updated USI record
Other
audio recording
Size: 90 MB
The Planning Inspectorate
Recording of Issue Specific Hearing on Onshore effects including the draft Development Consent Order - Part 1 - 21 January 2020
Other
audio recording
Size: 99 MB
The Planning Inspectorate
Recording of Issue Specific Hearing on Offshore effects including the draft Development Consent Order - Part 2 - 22 January 2020
Other
audio recording
Size: 82 MB
The Planning Inspectorate
Recording of Issue Specific Hearing on Offshore effects including the draft Development Consent Order - Part 3 - 22 January 2020
Other
audio recording
Size: 116 MB
The Planning Inspectorate
Recording of Issue Specific Hearing on Onshore effects including the draft Development Consent Order - Part 3 - 21 January 2020
Other
audio recording
Size: 79 MB
The Planning Inspectorate
Recording of Issue Specific Hearing on Offshore effects including the draft Development Consent Order - Part 1 - 22 January 2020
Other
audio recording
Size: 74 MB
The Planning Inspectorate
Recording of Issue Specific Hearing on Onshore effects including the draft Development Consent Order - Part 2 - 21 January 2020
Other
audio recording
Size: 37 MB
The Planning Inspectorate
Recording of Issue Specific Hearing on Onshore effects including the draft Development Consent Order - Part 4 - 21 January 2020
Other
Size: 78 KB
The Planning Inspectorate
Action Points arising from the Issue Specific Hearing on Offshore effects including the draft Development Consent Order - 22 January 2020
Other
Size: 82 KB
The Planning Inspectorate
Action Points arising from the Issue Specific Hearing on Onshore effects including the draft Development Consent Order - 21 January 2020
Other
Size: 472 KB
The Royal Society for the Protection of Birds
Additional Submission - Further comments on the Offshore Ornithology Assessment Update - Accepted at the discretion of the Examining Authority
Other
Size: 1 MB
Lucy Sheringham
Submission in lieu of attendance at Issue Specific Hearing 3 on onshore effects including the draft Development Consent Order
Other
Size: 103 KB
Accompanied Site Inspection Itinerary
Other
Size: 96 KB
Polly Brockis
Additional Submission - Nominations of suggested locations for site inspections - Accepted at the discretion of the Examining Authority
Other
Size: 128 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 3: Onshore effects including the draft Development Consent Order
Other
Size: 99 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 4: Offshore effects including the draft Development Consent Order
Other
Size: 3 MB
Norfolk Boreas Limited
Hearing Notice
Other
Size: 99 KB
Natural England
Deadline 3 Submission - Cover Letter
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 3 Submission - Comments on responses to ExA's Written Questions Appendix 1 (Part 2 of 2)
Other
Size: 250 KB
Marine Management Organisation
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 139 KB
Natural England
Deadline 3 Submission - Response to Onshore Ecology and Onshore Ornithology Documents submitted at Deadline 1 and 2
Other
Size: 257 KB
National Grid
Deadline 3 Submission - Responses to ExA's Written Questions - late response for Deadline 2
Other
Size: 521 KB
Natural England
Deadline 3 Submission - Risk and Issue Register
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Response to North Norfolk District Council's Local Impact Report
Other
Size: 433 KB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Response to Breckland Council's Local Impact Report
Other
Size: 376 KB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Response to Broadland District Council's Local Impact Report
Other
Size: 377 KB
Marine Management Organisation
Deadline 3 Submission - Other submission
Other
Size: 944 KB
Colin King
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 654 KB
Norfolk Boreas Limited
Deadline 3 Submission - Guide to the Application (Revision 5)
Other
Size: 53 KB
Natural England
Deadline 3 Submission - Advice on Cable Protection Assessment for Offshore Windfarms and Inclusion in Marine Licenses - Draft Position Paper December 2019
Other
Size: 420 KB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Response to Norfolk County Council's Local Impact Report
Other
Size: 262 KB
Norfolk Boreas Limited
Deadline 3 Submission - Cover Letter
Other
Size: 513 KB
The Royal Society for the Protection of Birds
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 194 KB
Cawston Parish Council
Deadline 3 Submission - Comments on Deadline 2 submissions
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Comments on Written Representations and Additional Submissions
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 3 Submission - Implications for the Norfolk Boreas Application for Development Consent of any Secretary of State decision on the Norfolk Vanguard Offshore Windfarm Application
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 3 Submission - Comments on responses to ExA's Written Questions Appendix 2
Other
Size: 7 MB
Norfolk Boreas Limited
Deadline 3 Submission - Comments on responses to ExA's Written Questions Appendix 1 (Part 1 of 2)
Other
Size: 101 KB
Necton Substation Action Group
Deadline 3 Submission - Other Submission
Other
Size: 179 KB
Necton Substation Action Group
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 1 MB
National Farmers Union
Deadline 3 Submission - Responses to ExA's Written Questions - Late Response for Deadline 2
Other
Size: 328 KB
The Wildlife Trusts
Deadline 3 Submission - Responses to ExA's Written Questions - Late Response for Deadline 2
Other
Size: 152 KB
Cawston Parish Council
Deadline 3 Submission - Comments on Deadline 2 Norfolk Boreas - Appendix 14.2 Norfolk Vanguard Offshore Wind Farm Alternative Construction Routes at Cawston, Applicants Comments on Deadline 6 Written Submissions: Appendix 2
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 3 Submission - Comments on responses to ExA's Written Questions
Other
Size: 164 KB
Natural England
Deadline 3 Submission - Response to Norfolk Boreas comments on Relevant Representations [AS-024] Table 26 DCO and DML
Other
Size: 259 KB
Oulton Parish Council
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 115 KB
Historic England
Deadline 3 Submission - Comments on responses to ExA's Written Questions
Other
Size: 119 KB
Notification of hearings and Accompanied Site Inspection - January 2020
Other
Size: 250 KB
George Freeman MP
Deadline 2 Submission - Written Representation
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 14
Other
Size: 7 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 9
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 8
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 4
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 1
Other
Size: 337 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Historic England
Other
Size: 765 KB
Breckland Council
Deadline 2 Submission - Statement of Common Ground
Other
Size: 692 KB
Norfolk Boreas Limited
Deadline 2 Submission - Outline Skills and Employment Strategy
Other
Size: 128 KB
Maritime and Coastguard Agency
Deadline 2 Submission - Written Representation
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Tracked Changes) Part 2 of 4
Other
Size: 569 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Breckland Council
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 596 KB
Norfolk Boreas Limited
Deadline 2 Submission - Written Representation
Other
Size: 395 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Trinity House
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 2 Submission - Method Statement for the crossing of the River Wensum and adjacent watercourses
Other
Size: 586 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Royal Yachting Association
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 1 Crossing 1
Other
Size: 306 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Chamber of Shipping
Other
Size: 376 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the National Federation of Fishermen's Organisations and VisNed
Other
Size: 553 KB
North Norfolk District Council
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 6 Happisburgh
Other
Size: 302 KB
Broadland District Council
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 629 KB
Royal Society for the Protection of Birds
Deadline 2 Submission - Written Representation
Other
Size: 371 KB
Norfolk Boreas Limited
Deadline 2 Submission - 5.4 Consents and Licences Required Under Other Legislation (Version 2) Tracked Changes)
Other
Size: 93 KB
Ministry of Defence
Deadline 2 Submission - MoD safeguarding position - Other Submission
Other
Size: 13 MB
Norfolk County Council
Deadline 2 Submission - Local Impact Report
Other
Size: 316 KB
Norfolk Boreas Limited
Deadline 2 Submission - Clarification Note Cable Logistics Area
Other
Size: 126 KB
Necton Parish Council
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Natural England (Version 2)
Other
Size: 8 MB
North Norfolk District Council
Deadline 2 Submission - Local Impact Report
Other
Size: 335 KB
Norfolk Boreas Limited
Deadline 2 Submission - 5.4 Consents and Licences Required under Other Legislation (Version 2) Clean)
Other
Size: 108 KB
Patricia Lockwood
Deadline 2 Submission - Written Representation
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 3 Crossing 3
Other
Size: 459 KB
Norfolk Boreas Limited
Deadline 2 Submission - Clarification Note - Landfall Method
Other
Size: 436 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Environment Agency
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Tracked Changes) Part 4 of 4
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Eastern Inshore Fisheries and Conservation Authority
Other
Size: 384 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the National Farmers Union
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 4 Crossings 4 & 5
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Broadland District Council
Other
Size: 213 KB
Cawston Parish Council
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 639 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Whale and Dolphin Conservation
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Tracked Changes) Part 1 of 4
Other
Size: 84 KB
Jan Burley
Deadline 2 Submission - Other Submission
Other
Size: 38 KB
Gowling WLG on behalf of Cadent Gas Limited
Deadline 2 Submission - Written Representation
Other
Size: 483 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Maritime and Coastguard Agency
Other
Size: 642 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statutory Undertaker Update
Other
Size: 340 KB
Norfolk Boreas Limited
Deadline 2 Submission - Implications of Separate Scenario Plans
Other
Size: 647 KB
Norfolk Boreas Limited
Deadline 2 Submission - Issue Specific Hearing 1 and 2 Action Points Tracker
Other
Size: 215 KB
The Wildlife Trusts
Deadline 2 Submission - Written Representation
Other
Size: 1,024 KB
Eastern Inshore Fisheries and Conservation Authority
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 179 KB
The Coal Authority
Deadline 2 Submission - Response to information requested by the ExA
Other
Size: 601 KB
Norfolk Boreas Limited
Deadline 2 Submission - Compulsory Acquisition Objections Schedule
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Clean) Part 2 of 3
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Norfolk County Council
Other
Size: 507 KB
National Grid
Deadline 2 Submission - Written Representation
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Tracked Changes) Part 3 of 4
Other
Size: 614 KB
N2RS
Deadline 2 Submission - Written Representation
Other
Size: 884 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Marine Management Organisation
Other
Size: 662 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with North Norfolk District Council
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 2 Submission - Offshore Ornithology Assessment Update
Other
Size: 109 KB
Diana Lockwood
Deadline 2 Submission - Written Representation
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - 6.6 Schedule of Mitigation (Version 2) (Tracked Changes)
Other
Size: 80 KB
Jenny Smedley
Deadline 2 Submission - Other Submission
Other
Size: 13 MB
Oulton Parish Council
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 191 KB
National Trust
Deadline 2 Submission - Other submission - Withdrawal of objection
Other
Size: 833 KB
Natural England
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 248 KB
Necton Substation Action Group
Deadline 2 Submission - Other Submission
Other
Size: 112 KB
Necton Substation Action Group
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 507 KB
Broadland District Council
Deadline 2 Submission - Cover Email
Other
Size: 420 KB
Environment Agency
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Highways England
Other
Size: 1 MB
Norfolk County Council
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 177 KB
Trinity House
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 579 KB
Norfolk Boreas Limited
Deadline 2 Submission - Clarification Note - Temporary Structures
Other
Size: 471 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Natural England (Offshore Ornithology)
Other
Size: 318 KB
Network Rail Infrastructure Limited
Deadline 2 Submission - Written Representation
Other
Size: 245 KB
National Federation of Fishermen's Organisations
Deadline 2 Submission - Written Representation
Other
Size: 88 KB
NATS Safeguarding
Deadline 2 Submission - Written Representation
Other
Size: 57 KB
Great Yarmouth Borough Council
Deadline 2 Submission - Written Representation
Other
Size: 196 KB
Broadland District Council
Deadline 2 Submission - Local Impact Report
Other
Size: 123 KB
Historic England
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 805 KB
Norfolk Boreas Limited
Deadline 2 Submission - Guide to the Application (Version 4)
Other
Size: 648 KB
Whale and Dolphin Conservation
Deadline 2 Submission - Written Representation
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 5 Crossings 6 & 7
Other
Size: 636 KB
Corpusty and Saxthorpe Parish Council
Deadline 2 Submission - Written Representation
Other
Size: 481 KB
Natural England
Deadline 2 Submission - Risk and Issue Log
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 2 Crossing 2
Other
Size: 296 KB
Norfolk Boreas Limited
Deadline 2 Submission - Cover Letter
Other
Size: 616 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Commonality of Statements of Common Ground
Other
Size: 220 KB
Royal Society for the Protection of Birds
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 965 KB
Breckland Council
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 144 KB
Anglian Water Services Limited
Deadline 2 Submission - Written Representation
Other
Size: 449 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Orsted Hornsea Project Three
Other
Size: 216 KB
Marine Management Organisation
Deadline 2 Submission - Cover Letter
Other
Size: 12 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Clean) Part 1 of 3
Other
Size: 692 KB
Historic England
Deadline 2 Submission - Written Representation
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Clean) Part 3 of 3
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 2 Submission - 6.6 Schedule of Mitigation (Version 2) (Clean)
Other
Size: 289 KB
Marine Management Organisation
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 102 KB
Maritime and Coastguard Agency
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 233 KB
Marine Management Organisation
Deadline 2 Submission - Summary of Relevant Representation
Other
Size: 496 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Wildlife Trusts and Norfolk Wildlife Trust
Other
Size: 150 KB
Breckland Council
Deadline 2 Submission - Local Impact Report
Other
Size: 381 KB
Norfolk County Council
Deadline 2 Submission - Other Submission - Response to the Dudgeon and Sheringham Shoal Wind Farm scoping consultations
Other
Size: 99 KB
Ministry of Defence
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 86 KB
Natural England
Deadline 2 Submission - Cover Letter
Other
Size: 117 KB
Colin King
Deadline 2 Submission - Written Representation
Other
Size: 320 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Anglian Water
Other
Size: 379 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Royal Society for the Protection of Birds
Other
Size: 378 KB
Norfolk Boreas Limited
Deadline 2 Submission - Clarification Note Ecological Enhancements
Other
Size: 82 KB
Jenny Smedley
Deadline 1 Submission - Nominations of suggested locations and justifications for site inspections for consideration by the ExA
Other
Size: 2 MB
Oulton Parish Council
Deadline 1 Submission - Nominations of suggested locations and justifications for site inspections for consideration by the ExA
Other
Size: 109 KB
N2RS
Deadline 1 Submission - Submission of post-hearing documents including any written submissions of oral case
Other
Size: 35 MB
Jenny Smedley
Deadline 1 Submission - Other Submission
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.4 Works Plan (Part 2 of 4) (Version 2)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 1 Submission - 5.3.6.1 Habitats Regulations Assessment - Appendix 6.1 - Integrity Matrices (Tracked Changes) (Version 3)
Other
Size: 121 KB
Oulton Parish Council
Deadline 1 Submission - Submission of post-hearing document including any written submissions of oral case
Other
Size: 150 KB
Cawston Parish Council
Deadline 1 Submission - Submission of post-hearing document including any written submissions of oral case and justification for site inspections for consideration by the ExA
Other
Size: 465 KB
Norfolk Boreas Limited
Deadline 1 Submission - Applicant's Guide to the Application (Version 3)
Other
Size: 52 KB
Glenn Berry Chairman on behalf of Happisburgh Parish Council
Deadline 1 Submission - Submission of post-hearing document including any written submission of oral case
Other
Size: 343 KB
Glenn Berry Chairman on behalf of Happisburgh Parish Council
Deadline 1 Submission - Nomination of suggested locations and justifications for site inspections for consideration by the Examining Authority
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 1 Submission - 6.7 EIA and DCO Reconciliation Document (Clean) (Version 2)
Other
Size: 518 KB
Kate Pitcher
Deadline 1 Submission - Nominations of suggested locations and justifications for site inspections for consideration by the ExA - Accepted at the discretion of the Examining Authority
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 1 Submission - 5.3.5.3 Habitats Regulations Assessment - Appendix 5.3 - Screening Matrices (Clean) (Version 3)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan Appendices (Tracked Changes) (Version 2)
Other
Size: 646 KB
Natural England
Deadline 1 Submission - Other Submission - Appendix 2.6 Natural England advice note regarding consideration of small scale habitat loss within Special Areas of Conservation (SACs) in relation to cable protection, omitted in error from Natural England's Relevant Representation
Other
Size: 96 KB
Diana Lockwood
Deadline 1 Submission - Nomination of suggested locations and justifications for site inspections for consideration by the Examining Authority
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 4.3 Book of Reference (Clean) (Version 2)
Other
Size: 99 KB
Colin King
Deadline 1 Submission - Nomination of suggested locations and justifications for site inspections for consideration by the Examining Authority
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.20 Outline Norfolk Boreas Haisborough Hammond and Winterton Special Area of Conservation Site Integrity Plan (Tracked Changes) (Version 2)
Other
Size: 678 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.12 Offshore In-Principle Monitoring Plan (Tracked Changes) (Version 2)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan Appendices (Clean) (Version 2)
Other
Size: 1 MB
Julian Pearson
Deadline 1 Submission - Submission of post-hearing documents including any written submissions of oral case - Accepted at the discretion of the Examining Authority
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 1 Submission - Applicant's Nomination of Locations to be Inspected
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.4 Works Plan (Part 4 of 4) (Version 2)
Other
Size: 318 KB
Marine Management Organisation
Deadline 1 Submission - Post-hearing document including any written submission of oral case
Other
Size: 15 MB
Oulton Parish Council
Deadline 1 Submission - Other Submission - Summary of Norfolk Vanguard issues and submissions for Norfolk Vanguard deadlines
Other
Size: 34 KB
Necton Parish Council
Deadline 1 Submission - Submission of post-hearing document including any written submission of oral case
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.7 Outline Landscape and Ecological Management Strategy (Clean) (Version 2)
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - Seabed Mobility Study
Other
Size: 158 KB
Necton Substation Action Group
Deadline 1 - Submission in lieu of attendance at Issue Specific Hearing 2 on Environmental Matters including HRA on 14 November 2019
Other
Size: 381 KB
Norfolk Boreas Limited
Deadline 1 Submission - Written Summary of the Applicant's Oral Case at Issue Specific Hearing 2 - Environmental Matters including Habitats Regulations Assessment
Other
Size: 82 KB
The Monk Family
Deadline 1 Submission -Nomination of suggested locations and justification for site inspections for consideration by the ExA
Other
Size: 434 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.11 Outline Offshore Operations and Maintenance Plan (Tracked Changes) (Version 2)
Other
Size: 10 MB
Necton Substation Action Group
Deadline 1 Submission - Other Submission
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 1 Submission - 3.1 Updated draft DCO (Clean) (Version 3)
Other
Size: 87 KB
Natural England
Deadline 1 Submission - Other Submission - Response to the Rule 8 Letter
Other
Size: 191 KB
Nicola Banham
Deadline 1 Submission - Submission of post-hearing document including any written submission of oral case
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 1 Submission - Clarification Note Trenchless Crossings and Potential Effects of Breakout on the River Wensum
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 4.3 Book of Reference (Tracked Changes) (Version 2)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 1 Submission - 3.1 Updated draft DCO (Tracked Changes) (Version 3)
Other
Size: 426 KB
Natural England
Deadline 1 Submission - Other Submission - Updated Risk and Issues Log
Other
Size: 97 KB
Guy Pitcher
Deadline 1 Submission - Submission of post-hearing documents including any written submissions of oral case - Accepted at the discretion of the Examining Authority
Other
Size: 15 MB
Oulton Parish Council
Deadline 1 Submission - Other Submission - Dudgeon and Sheringham Shoal Offshore Wind Farm Extensions Scoping Report of October 2019
Other
Size: 665 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.16 Outline Scour Protection and Cable Protection Plan (Tracked Changes) (Version 2)
Other
Size: 904 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.1 Outline Code of Construction Practice (Tracked Changes) (Version 2)
Other
Size: 625 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.12 Offshore In-Principle Monitoring Plan (Clean) (Version 2)
Other
Size: 329 KB
Norfolk Boreas Limited
Deadline 1 Submission - Schedule of Changes to the draft Development Consent Order (Version 2)
Other
Size: 58 KB
Norfolk Boreas Limited
Deadline 1 Submission - Cover Letter
Other
Size: 29 MB
Cawston Parish Council
Deadline 1 Submission - Other Submission - Submissions made to the Hornsea 3 and Norfolk Vanguard Examinations
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 1 Submission - 6.7 EIA and DCO Reconciliation Document (Tracked Changes) (Version 2)
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.20 Outline Norfolk Boreas Haisborough Hammond and Winterton Special Area of Conservation Site Integrity Plan (Clean) (Version 2)
Other
Size: 12 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan Figures (Version 2)
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.4 Works Plan (Part 3 of 4) (Version 2)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.4 Works Plan (Part 1 of 4) (Version 2)
Other
Size: 2 MB
Oulton Parish Council
Deadline 1 Submission - Other Submission - Questions and comments made by the Parish Council at the Preliminary Meeting and copy of a letter from George Freeman MP to BEIS
Other
Size: 373 KB
Norfolk Boreas Limited
Deadline 1 Submission - Checklist of East Inshore and Offshore Marine Plans Objectives
Other
Size: 194 KB
Savills (UK) Ltd on behalf of Mr C Allhusen
Deadline 1 Submission - Nomination of suggested locations and justifications for site inspections for consideration by the ExA
Other
Size: 13 MB
Ray and Diane Pearce
Deadline 1 Submission - Submission of post-hearing document including any written submission of oral case and nomination of suggested locations and justifications for consideration by the ExA - Accepted at the discretion of the Examining Authority
Other
Size: 2 MB
George Freeman MP
Deadline 1 Submission - Other Submission
Other
Size: 900 KB
Norfolk Boreas Limited
Deadline 1 Submission - 5.3.6.1 Habitats Regulations Assessment - Appendix 6.1 - Integrity Matrices (Clean) (Version 3)
Other
Size: 133 KB
David Vince & Nicola Draycott
Deadline 1 Submission - Other Submission - Accepted at the discretion of the Examining Authority
Other
Size: 664 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.16 Outline Scour Protection and Cable Protection Plan (Clean) (Version 2)
Other
Size: 902 KB
Glenn Berry Chairman on behalf of Happisburgh Parish Council
Deadline 1 Submission - Other Submission
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 1 Submission - 5.3.5.3 Habitats Regulations Assessment - Appendix 5.3 - Screening Matrices (Tracked Changes) (Version 3)
Other
Size: 682 KB
Norfolk Boreas Limited
Deadline 1 Submission - Written Summary of the Applicant's Oral Case at Issue Specific Hearing 1 - draft Development Consent Order
Other
Size: 613 KB
Norfolk Boreas Limited
Deadline 1 Submission - Applicant's Response to the Open Floor Hearing
Other
Size: 756 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan (Tracked Changes) (Version 2)
Other
Size: 880 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.1 Outline Code of Construction Practice (Clean) (Version 2)
Other
Size: 413 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.11 Outline Offshore Operations and Maintenance Plan (Clean) (Version 2)
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.2 Land Plan (Offshore) (Version 2)
Other
Size: 804 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan (Clean) (Version 2)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.7 Outline Landscape and Ecological Management Strategy (Tracked Changes) (Version 2)
Other
Size: 77 KB
Necton Parish Council
Deadline 1 Submission - Nominations of suggested locations and justifications for site inspections for consideration by the ExA
Other
Size: 119 KB
Preliminary Meeting Note
Other
Size: 860 KB
Written Questions
Other
Size: 265 KB
Rule 8 – notification of timetable for the examination
Other
audio recording
Size: 37 MB
Recording of Issue Specific Hearing 2 - Part 3 of 3
Issue Specific Hearing on Environmental Matters including Habitats Regulations Assessment - 14 November 2019
Other
audio recording
Size: 49 MB
Recording of Issue Specific Hearing 2 - Part 1 of 3
Issue Specific Hearing on Environmental Matters including Habitats Regulations Assessment - 14 November 2019
Other
audio recording
Size: 62 MB
Recording of Open Floor Hearing 1 - 13 November 2019
Other
audio recording
Size: 63 MB
Recording of Issue Specific Hearing 2 - Part 2 of 3
Issue Specific Hearing on Environmental Matters including Habitats Regulations Assessment - 14 November 2019
Other
Size: 99 KB
The Planning Inspectorate
Action points arising from the Issue Specific Hearing on environmental matters including HRA held on 14 November 2019
Other
Size: 109 KB
Note of Unaccompanied Site Inspections up to 11 November 2019
The Examining Authority's updated USI record
Other
audio recording
Size: 101 MB
Recording of Issue Specific Hearing 1 - Part 1 of 2
Issue Specific Hearing on draft Development Consent Order - 13 November 2019
Other
audio recording
Size: 64 MB
Recording of Issue Specific Hearing 1 - Part 2 of 2
Issue Specific Hearing on draft Development Consent Order - 13 November 2019
Other
Size: 77 KB
The Planning Inspectorate
Action points arising from the Issue Specific Hearing on the draft Development Consent Order held on 13 November 2019
Other
Size: 89 KB
Norfolk Boreas Limited
List of appearances for the Applicant at the Issue Specific Hearing on environmental matters including HRA on 14 November 2019
Other
Size: 84 KB
Norfolk Boreas Limited
List of appearances for the Applicant at the Issue Specific Hearing on the draft Development Consent Order on 13 November 2019
Other
audio recording
Size: 57 MB
Recording of Preliminary Meeting - 12 November 2019
Other
Size: 988 KB
Examination Library
Other
Size: 138 KB
NATS Safeguarding
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 96 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 2: Environmental Matters including HRA - Thursday 14 November 2019
Other
Size: 8 MB
Norfolk Boreas Limited
Additional Submissions - Updated draft DCO (Revision 2) (Tracked Changes) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 529 KB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with Natural England (Offshore Ornithology) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with Marine Management Organisation - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 8 MB
Norfolk Boreas Limited
Additional Submissions - Updated draft DCO (Revision 2) (Clean) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with Natural England - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 240 KB
North Norfolk District Council
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 101 KB
Polly Brockis
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submissions - Explanatory Memorandum (Revision 2) (Clean) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 626 KB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with The Wildlife Trusts and Norfolk Wildlife Trust - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 468 KB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with The Royal Society for the Protection of Birds - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 799 KB
Norfolk Boreas Limited
Additional Submissions - Explanatory Memorandum (Revision 2) (Tracked Changes) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 664 KB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with Environment Agency - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 522 KB
Norfolk Boreas Limited
Additional Submissions - Applicant's guide to the Application (Revision 2) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 142 KB
Environment Agency
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 653 KB
Norfolk Boreas Limited
Additional Submissions - Applicant's Response to the Rule 6 Letter and Cover Letter for Annex F Documents - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 176 KB
Highways England
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 3 MB
Norfolk Boreas Limited
Additional Submissions - Comments on Relevant Representations - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 256 KB
Cawston Parish Council
Additional Submissions - Comments on Relevant Representations - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 439 KB
Norfolk Boreas Limited
Additional Submissions - Applicant's Updated draft DCO Schedule of Changes - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 8 MB
Norfolk Boreas Limited
Additional Submissions - Comments on Relevant Representations Appendices - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 304 KB
Marine Management Organisation
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 490 KB
Natural England
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 151 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 1: The draft Development Consent Order - Wednesday 13 November 2019
Other
Size: 3 MB
Norfolk Boreas Limited
Notice of Preliminary Meeting and Hearings on 12 - 14 November 2019
Other
Size: 295 KB
Rule 6 letter - Notification of the preliminary meeting and matters to be discussed
Other
Size: 1 MB
Norman Lamb MP
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 94 KB
Ministry of Defence
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 83 KB
Julian Pearson
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 207 KB
Mr Geoffrey Vout
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 82 KB
Greg Peck
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 95 KB
Note of Unaccompanied Site Inspections up to 1 October 2019
Other
Size: 96 KB
Notification of Amendment to Panel Membership
Other
Size: 10 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Land Plans Part 3 - Accepted at the discretion of the Examining Authority
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Appendix 5.3 (Tracked Changes) - Habitats Regulations Assessment - Screening Matrices (Version 2) - Accepted at the discretion of the Examining Authority
Other
Size: 10 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Land Plans Part 2 - Accepted at the discretion of the Examining Authority
Other
Size: 123 KB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Accepted at the discretion of the Examining Authority
Other
Size: 9 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Land Plans Part 4 - Accepted at the discretion of the Examining Authority
Other
Size: 6 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Land Plans Part 5 - Accepted at the discretion of the Examining Authority
Other
Size: 988 KB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Appendix 6.1 - Habitats Regulations Assessment - Integrity Matrices Version 2 - Accepted at the discretion of the Examining Authority
Other
Size: 3 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Special Category Land Plans - Accepted at the discretion of the Examining Authority
Other
Size: 10 MB
Norfolk Boreas Limited
Additional Submission- Response to Section 51 Advice - Land Plans Part 1 - Accepted at the discretion of the Examining Authority
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Appendix 5.3 - Habitats Regulations Assessment - Screening Matrices Version 2 - Accepted at the discretion of the Examining Authority
Other
Size: 465 KB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Appendix 6.1 (Tracked Changes) - Habitats Regulations Assessment - Integrity Matrices Version 2 - Accepted at the discretion of the Examining Authority
Other
Size: 170 KB
Appointment of the Examining Authority
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.11 Environmental Statement - Chapter 11 Fish and Shellfish Ecology
Other
Size: 38 KB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports Annex G Plates (2018 Survey) (Confidential)
Other
Size: 35 KB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports Annex B Badger Results (Confidential)
Other
Size: 37 KB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports Annex G Plates (2017 Survey) (Confidential)
Other
Size: 114 KB
Norfolk Boreas Limited
Section 56 Notice
Other
Size: 188 KB
South Norfolk Council
Adequacy of Consultation Representation
Other
Size: 204 KB
Broadland District Council
Adequacy of Consultation Representation
Other
Size: 184 KB
Norfolk County Council
Adequacy of Consultation Representation
Other
Size: 269 KB
North Norfolk District Council
Adequacy of Consultation Representation
Other
Size: 278 KB
Borough Council of King's Lynn and West Norfolk
Adequacy of Consultation Representation
Other
Size: 182 KB
Norwich City Council
Adequacy of Consultation Representation
Other
Size: 123 KB
Suffolk County Council
Adequacy of Consultation Representation
Other
Size: 182 KB
Great Yarmouth Borough Council
Adequacy of Consultation Representation
Other
Size: 182 KB
Section 51 advice to the Applicant
Other
Size: 363 KB
Section 55 Checklist
Other
Size: 135 KB
Notification of Decision to Accept Application
Other
Size: 20 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2018 Report Annex G Plates - Target Note Photos
Other
Size: 20 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Target Notes PART 3
Other
Size: 30 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Target Notes PART 1
Other
Size: 20 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2018 Report Annex G Plates - Bat Feature Photos by Object
Other
Size: 42 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Target Notes PART 2
Other
Size: 40 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Bats PART 2
Other
Size: 43 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Bats PART 1
Other
Size: 4 MB
Norfolk Boreas Limited
6.7 EIA and DCO Reconciliation Document
Other
Size: 4 MB
Norfolk Boreas Limited
6.5 Scoping Opinion as given by the Secretary of State in June 2017.
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.4.5 Environmental Statement - Appendix 4.5 Norfolk Vanguard and Norfolk Boreas Coastal Erosion Study
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.4.3 Environmental Statement - Appendix 4.3 Strategic approach to selecting a grid connection point
Other
Size: 442 KB
Norfolk Boreas Limited
6.3.8.1 Environmental Statement - Appendix 8.1 Particle size characteristics
Other
Size: 299 KB
Norfolk Boreas Limited
6.3.33.1 Environmental Statement - Appendix 33.1 Plans and Projects included in the Onshore CIA
Other
Size: 489 KB
Norfolk Boreas Limited
6.3.32.1 Environmental Statement - Appendix 32.1 Offshore CIA and Transboundary Impact Consultation
Other
Size: 705 KB
Norfolk Boreas Limited
6.3.31.2 Environmental Statement - Appendix 31.2 Supply Chain Assessment
Other
Size: 720 KB
Norfolk Boreas Limited
6.3.28.7 Environmental Statement - Appendix 28.7 Updated Baseline (Potential Sub-surface Archaeological Remains)
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.4.9 Environmental Statement - Appendix 4.9 Identification of Onshore Project Substation Search Sectors
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.4.7 Environmental Statement - Appendix 4.7 Identification of Onshore Cable Corridor
Other
Size: 8 MB
Norfolk Boreas Limited
6.3.5.3 Environmental Statement - Appendix 5.3 Ordtek UXO Review
Other
Size: 625 KB
Norfolk Boreas Limited
6.3.30.1 Environmental Statement - Appendix 30.1 Public rights of way and cycle routes
Other
Size: 514 KB
Norfolk Boreas Limited
6.3.29.1 Environmental Statement - Appendix 29.1 Landscape and Visual Impact Assessment Methodology
Other
Size: 448 KB
Norfolk Boreas Limited
6.3.5.5 Environmental Statement - Appendix 5.5 Underwater noise of UXO at the Norfolk Boreas sites
Other
Size: 702 KB
Norfolk Boreas Limited
6.3.31.3 Environmental Statement - Appendix 31.3 Offshore Wind Policy and Regional Sector Review
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.4.8 Environmental Statement - Appendix 4.8 Identification of Cable Relay Station Locations
Other
Size: 19 MB
Norfolk Boreas Limited
6.3.4.6 Environmental Statement - Appendix 4.6 HDD Feasibility Reports for Happisburgh and Bacton Green Landfall Sites
Other
Size: 13 MB
Norfolk Boreas Limited
6.3.4.1 Environmental Statement - Appendix 4.1 Initial HDD Feasibility Report
Other
Size: 1 MB
Norfolk Boreas Limited
6.6 Schedule of Mitigation
Other
Size: 5 MB
Norfolk Boreas Limited
6.4 Environmental Statement Non Technical Summary - Non-Technical Summary provides a lay persons' summary to the Environmental Statement.
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.32.2 Environmental Statement - Appendix 32.2 Plans and Projects included in the Offshore CIA and Transboundary Assessments
Other
Size: 671 KB
Norfolk Boreas Limited
6.3.5.1 Environmental Statement - Appendix 5.1 Onshore Scenario Comparison Table
Other
Size: 5 MB
Norfolk Boreas Limited
6.3.9.1 Environmental Statement - Appendix 9.1 Water Framework Directive Compliance Assessment-Marine WFD Water Bodies
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.4.4 Environmental Statement - Appendix 4.4 Preferred Landfall Location Technical Note
Other
Size: 30 MB
Norfolk Boreas Limited
6.3.4.2 Environmental Statement - Appendix 4.2 Cable Constructability Assessment
Other
Size: 530 KB
Norfolk Boreas Limited
6.3.31.1 Environmental Statement - Appendix 31.1 Supporting Information
Other
Size: 459 KB
Norfolk Boreas Limited
6.3.29.2 Environmental Statement - Appendix 29.2 Existing Environment
Other
Size: 3 MB
Norfolk Boreas Limited
6.3.5.2 Environmental Statement - Appendix 5.2 Cable Installation Study
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.4.10 Environmental Statement - Appendix 4.10 Onshore Project Substation Site Selection
Other
Size: 28 MB
Norfolk Boreas Limited
6.3.28.8 Environmental Statement - Appendix 28.8 Archaeological Geophysical Survey Report (Substation area)
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.28.6 Environmental Statement - Appendix 28.6 Non-Designated Heritage Assets Gazetteer
Other
Size: 279 KB
Norfolk Boreas Limited
6.3.6.1 Environmental Statement - Appendix 6.1 Statement of Competence
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.5.4 Environmental Statement - Appendix 5.4 Underwater Noise Assessment
Other
Size: 48 MB
Norfolk Boreas Limited
6.3.28.2 Environmental Statement - Appendix 28.2 Priority Archaeological Geophysical Survey Report (Part 2)
Other
Size: 48 MB
Norfolk Boreas Limited
6.3.28.2 Environmental Statement - Appendix 28.2 Priority Archaeological Geophysical Survey Report (Part 1)
Other
Size: 25 MB
Norfolk Boreas Limited
6.3.28.1 Environmental Statement - Appendix 28.1 Onshore Archaeological Desk Based (Baseline) Assessment
Other
Size: 262 KB
Norfolk Boreas Limited
6.3.24.9 Environmental Statement - Appendix 24.9 Employee Distribution (resident) Data
Other
Size: 224 KB
Norfolk Boreas Limited
6.3.24.7 Environmental Statement - Appendix 24.7 Scenario 1 - GHD Transport Assignment on Indicative Construction Programme
Other
Size: 276 KB
Norfolk Boreas Limited
6.3.26.3 Environmental Statement - Appendix 26.3 Air Quality Background Pollutant Concentrations
Other
Size: 293 KB
Norfolk Boreas Limited
6.3.26.1 Environmental Statement - Appendix 26.1 Air Quality Construction Dust Assessment
Other
Size: 7 MB
Norfolk Boreas Limited
6.3.28.3 Environmental Statement - Appendix 28.3 Geoarchaeological Watching Brief Report: Onshore Engineering Ground Investigations (GI) works (Phase 1)
Other
Size: 198 KB
Norfolk Boreas Limited
6.3.24.8 Environmental Statement - Appendix 24.8 Employee Distribution (in-migrant) Data
Other
Size: 978 KB
Norfolk Boreas Limited
6.3.25.3 Environmental Statement - Appendix 25.3 Operational Phase Assessment
Other
Size: 27 MB
Norfolk Boreas Limited
6.3.25.1 Environmental Statement - Appendix 25.1 Baseline Noise Survey
Other
Size: 714 KB
Norfolk Boreas Limited
6.3.28.5 Environmental Statement - Appendix 28.5 Designated Heritage Assets Gazetteer
Other
Size: 14 MB
Norfolk Boreas Limited
6.3.28.4 Environmental Statement - Appendix 28.4 Heritage Settings Assessment Workings (Onshore Project Substation and Associated Infrastructure)
Other
Size: 42 MB
Norfolk Boreas Limited
6.3.28.2 Environmental Statement - Appendix 28.2 Priority Archaeological Geophysical Survey Report (Part 4)
Other
Size: 43 MB
Norfolk Boreas Limited
6.3.28.2 Environmental Statement - Appendix 28.2 Priority Archaeological Geophysical Survey Report (Part 3)
Other
Size: 528 KB
Norfolk Boreas Limited
6.3.27.1 Environmental Statement - Appendix 27.1 Human Health Supporting Information
Other
Size: 649 KB
Norfolk Boreas Limited
6.3.26.4 Environmental Statement - Appendix 26.4 Cumulative ConstructionImpact Assessment Results
Other
Size: 361 KB
Norfolk Boreas Limited
6.3.26.2 Environmental Statement - Appendix 26.2 Air Quality Traffic Data
Other
Size: 293 KB
Norfolk Boreas Limited
6.3.25.4 Environmental Statement - Appendix 25.4 Norfolk Vanguard Noise and Vibration Consultation Responses
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.25.2 Environmental Statement - Appendix 25.2 Construction Phase Assessment
Other
Size: 216 KB
Norfolk Boreas Limited
6.3.24.38 Environmental Statement - Appendix 24.38 Link 41 Construction Programme and HGV Profiles
Other
Size: 217 KB
Norfolk Boreas Limited
6.3.24.36 Environmental Statement - Appendix 24.36 Link 13b Construction Programme and HGV Profiles
Other
Size: 247 KB
Norfolk Boreas Limited
6.3.24.34 Environmental Statement - Appendix 24.34 Scenario 2 - Summary of Construction Impacts
Other
Size: 350 KB
Norfolk Boreas Limited
6.3.24.20 Environmental Statement - Appendix 24.20 Scenario 2 - GHD Assumed Construction Materials and Associated HGV Delivery Derivation
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.24.18 Environmental Statement - Appendix 24.18 Scenario 1 - 2026 Development Flow Network Diagram
Other
Size: 278 KB
Norfolk Boreas Limited
6.3.24.2 Environmental Statement - Appendix 24.2 Link Sensitivity Rationale
Other
Size: 374 KB
Norfolk Boreas Limited
6.3.24.32 Environmental Statement - Appendix 24.32 PIC Cluster Summary
Other
Size: 173 KB
Norfolk Boreas Limited
6.3.24.30 Environmental Statement - Appendix 24.30 Scenario 2 - Employee Assignment Summary
Other
Size: 291 KB
Norfolk Boreas Limited
6.3.24.28 Environmental Statement - Appendix 24.28 Scenario 2 - Destination B (mobilisation areas and trenchless crossings) Employee Assignment
Other
Size: 202 KB
Norfolk Boreas Limited
6.3.24.26 Environmental Statement - Appendix 24.26 Scenario 2 - HGV Assignment
Other
Size: 212 KB
Norfolk Boreas Limited
6.3.24.40 Environmental Statement - Appendix 24.40 Link 34 Construction Programme and HGV Profiles
Other
Size: 247 KB
Norfolk Boreas Limited
6.3.24.24 Environmental Statement - Appendix 24.24 Scenario 2 - Lowestoft Port HGV Distribution
Other
Size: 294 KB
Norfolk Boreas Limited
6.3.24.22 Environmental Statement - Appendix 24.22 Scenario 2 - GHD Transport Assignment on Indicative Construction Programme
Other
Size: 232 KB
Norfolk Boreas Limited
6.3.24.6 Environmental Statement - Appendix 24.6 Scenario 1 - GHD Summary of Deliveries per Infrastructure Component
Other
Size: 343 KB
Norfolk Boreas Limited
6.3.24.4 Environmental Statement - Appendix 24.4 Scenario 1 - GHD Assumed Construction Materials and Associated HGV Delivery Derivation
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.24.31 Environmental Statement - Appendix 24.31 Scenario 2 - 2023 Development Flow Network Diagram
Other
Size: 184 KB
Norfolk Boreas Limited
6.3.24.29 Environmental Statement - Appendix 24.29 Scenario 2 - Destination C (Landfall) Employee Assignment
Other
Size: 182 KB
Norfolk Boreas Limited
6.3.24.27 Environmental Statement - Appendix 24.27 Scenario 2 - Destination A (onshore substations) Employee Assignment
Other
Size: 247 KB
Norfolk Boreas Limited
6.3.24.25 Environmental Statement - Appendix 24.25 Scenario 2 - Great Yarmouth Port HGV Distribution
Other
Size: 372 KB
Norfolk Boreas Limited
6.3.24.5 Environmental Statement - Appendix 24.5 Scenario 1 & 2 - Cable Pulling and Jointing Calculations and Access Routes
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.24.3 Environmental Statement - Appendix 24.3 2026 Forecast Background Traffic Flows
Other
Size: 216 KB
Norfolk Boreas Limited
6.3.24.39 Environmental Statement - Appendix 24.39 Link 68 Construction Programme and HGV Profiles
Other
Size: 250 KB
Norfolk Boreas Limited
6.3.24.35 Environmental Statement - Appendix 24.35 Scenario 1 - Summary of Construction Impacts
Other
Size: 214 KB
Norfolk Boreas Limited
6.3.24.41 Environmental Statement - Appendix 24.41 Link 36 Construction Programme and HGV Profiles
Other
Size: 214 KB
Norfolk Boreas Limited
6.3.24.37 Environmental Statement - Appendix 24.37 Link 32 Construction Programme and HGV Profiles
Other
Size: 246 KB
Norfolk Boreas Limited
6.3.24.23 Environmental Statement - Appendix 24.23 Scenario 2 - Kings Lynn Port HGV Distribution
Other
Size: 234 KB
Norfolk Boreas Limited
6.3.24.21 Environmental Statement - Appendix 24.21 Scenario 2 - GHD Summary of Deliveries per Infrastructure Component
Other
Size: 6 MB
Norfolk Boreas Limited
6.3.24.33 Environmental Statement - Appendix 24.33 A47 Substation Access Clarification Technical Note
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.24.19 Environmental Statement - Appendix 24.19 2023 Forecast Background Traffic Flows
Other
Size: 250 KB
Norfolk Boreas Limited
6.3.24.16 Environmental Statement - Appendix 24.16 Scenario 1 - Destination B (cable route sections) Employee Assignment
Other
Size: 212 KB
Norfolk Boreas Limited
6.3.24.14 Environmental Statement - Appendix 24.14 Scenario 1 - HGV Assignment
Other
Size: 179 KB
Norfolk Boreas Limited
6.3.24.12 Environmental Statement - Appendix 24.12 Scenario 1 - Lowestoft Port HGV Distribution
Other
Size: 200 KB
Norfolk Boreas Limited
6.3.24.10 Environmental Statement - Appendix 24.10 Employee Distribution Summary
Other
Size: 572 KB
Norfolk Boreas Limited
6.3.22.11 Environmental Statement - Appendix 22.11 Norfolk Vanguard Onshore Ecology Consultation Responses
Other
Size: 397 KB
Norfolk Boreas Limited
6.3.23.5 Environmental Statement - Appendix 23.5 Norfolk Vanguard Onshore Ornithology Consultation Responses
Other
Size: 21 MB
Norfolk Boreas Limited
6.3.22.3 Environmental Statement - Appendix 22.3 Water Vole Survey Reports
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.22.6 Environmental Statement - Appendix 22.6 Desmoulin's Whorl Snail Survey Reports
Other
Size: 15 MB
Norfolk Boreas Limited
6.3.22.4 Environmental Statement - Appendix 22.4 Bat Activity Survey Reports
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.23.3b Environmental Statement - Appendix 23.3b Whooper swan and Berwick’s swan maps for Broadland SPA
Other
Size: 10 MB
Norfolk Boreas Limited
6.3.23.2 Environmental Statement - Appendix 23.2 Wintering Bird Surveys: Final Report
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.22.7 Environmental Statement - Appendix 22.7 Botanical Survey Reports
Other
Size: 3 MB
Norfolk Boreas Limited
6.3.22.5 Environmental Statement - Appendix 22.5 Bat Emergence Re-entry Survey Reports
Other
Size: 188 KB
Norfolk Boreas Limited
6.3.24.15 Environmental Statement - Appendix 24.15 Scenario 1 - Destination A (onshore substations) Employee Assignment
Other
Size: 178 KB
Norfolk Boreas Limited
6.3.24.13 Environmental Statement - Appendix 24.13 Scenario 1 - Great Yarmouth Port HGV Distribution
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.22.9 Environmental Statement - Appendix 22.9 Norfolk Hawker Dragonfly Survey Report
Other
Size: 175 KB
Norfolk Boreas Limited
6.3.24.17 Environmental Statement - Appendix 24.17 Scenario 1 - Employee Assignment Summary
Other
Size: 442 KB
Norfolk Boreas Limited
6.3.23.3a Environmental Statement - Appendix 23.3a Pink-footed goose maps for Broadland SPA
Other
Size: 11 MB
Norfolk Boreas Limited
6.3.23.1 Environmental Statement - Appendix 23.1 Onshore Winter / Passage Bird Survey Scoping Report
Other
Size: 5 MB
Norfolk Boreas Limited
6.3.24.1 Environmental Statement - Appendix 24.1 NCC Route Hierarchy
Other
Size: 12 MB
Norfolk Boreas Limited
6.3.23.4 Environmental Statement - Appendix 23.4 Breeding Bird Survey Report
Other
Size: 27 MB
Norfolk Boreas Limited
6.3.22.2 Environmental Statement - Appendix 22.2 Great Crested Newt Survey Reports
Other
Size: 195 KB
Norfolk Boreas Limited
6.3.24.11 Environmental Statement - Appendix 24.11 Scenario 1 - Kings Lynn Port HGV Distribution
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.22.10 Environmental Statement - Appendix 22.10 Ecosystem Services Assessment
Other
Size: 3 MB
Norfolk Boreas Limited
6.3.22.8 Environmental Statement - Appendix 22.8 Reptile Survey Reports
Other
Size: 38 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports
Other
Size: 10 MB
Norfolk Boreas Limited
6.3.17.8 Environmental Statement - Appendix 17.8: Norfolk Boreas Offshore Wind Farm Stage 4 Paleoenvironmental Assessment
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.17.6 Environmental Statement - Appendix 17.6: Norfolk Boreas Offshore Wind Farm Stage 2 Geoarchaeological Review
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.17.4 Environmental Statement - Appendix 17.4: Norfolk Vanguard Offshore Wind Farm Marine Archaeological Technical Report
Other
Size: 308 KB
Norfolk Boreas Limited
6.3.19.1 Environmental Statement - Appendix 19.1 Norfolk Vanguard Ground Conditions and Contamination Consultation Responses
Other
Size: 345 KB
Norfolk Boreas Limited
6.3.20.4 Environmental Statement - Appendix 20.4 Watercourse Crossing Schedule
Other
Size: 13 MB
Norfolk Boreas Limited
6.3.20.2 Environmental Statement - Appendix 20.2 Water Framework Directive Compliance Assessment
Other
Size: 582 KB
Norfolk Boreas Limited
6.3.20.5 Environmental Statement - Appendix 20.5 Norfolk Vanguard Water Resources and Flood Risk Consultation Responses
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.20.3 Environmental Statement - Appendix 20.3 Geomorphological Walkover Survey
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.19.3 Environmental Statement - Appendix 19.3 Waste Technical Assessment
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.17.3 Environmental Statement - Appendix 17.3: Norfolk Boreas Offshore Windfarm Archaeological Assessment of Geophysical Data-Addendum
Other
Size: 287 KB
Norfolk Boreas Limited
6.3.21.1 Environmental Statement - Appendix 21.1 Norfolk Vanguard Land Use and Agriculture Consultation Responses
Other
Size: 44 MB
Norfolk Boreas Limited
6.3.20.1 Environmental Statement - Appendix 20.1 Flood Risk Assessment
Other
Size: 17 MB
Norfolk Boreas Limited
6.3.19.2 Environmental Statement - Appendix 19.2 Land Quality Phase 1 Preliminary Risk Assessment
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.17.9 Environmental Statement - Appendix 17.9: Offshore Archaeology Gazetteer
Other
Size: 5 MB
Norfolk Boreas Limited
6.3.17.7 Environmental Statement - Appendix 17.7: Norfolk Boreas Offshore Wind Farm Stage 3 Geoarchaeological Assessment
Other
Size: 3 MB
Norfolk Boreas Limited
6.3.17.5 Environmental Statement - Appendix 17.5: Norfolk Boreas Offshore Wind Farm Stage 1 Geoarchaeological Review
Other
Size: 579 KB
Norfolk Boreas Limited
6.3.15.4 Environmental Statement - Appendix 15.4 Regular Operator Consultation
Other
Size: 28 MB
Norfolk Boreas Limited
6.3.15.1 Environmental Statement - Appendix 15.1 Navigation Risk Assessment
Other
Size: 14 MB
Norfolk Boreas Limited
6.3.17.2 Environmental Statement - Appendix 17.2: Norfolk Boreas Offshore Windfarm Archaeological Assessment of Geophysical Data
Other
Size: 644 KB
Norfolk Boreas Limited
6.3.15.2 Environmental Statement - Appendix 15.2 MGN 543 Checklist
Other
Size: 470 KB
Norfolk Boreas Limited
6.3.14.2 Environmental Statement - Appendix 14.2 Commercial Fisheries Consultation Responses
Other
Size: 19 MB
Norfolk Boreas Limited
6.3.14.1 Environmental Statement - Appendix 14.1 Commercial Fisheries Technical Report
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.12.3 Environmental Statement - Appendix 12.3: Marine Mammal Cumulative Impact Assessment (CIA) screening
Other
Size: 5 MB
Norfolk Boreas Limited
6.3.12.2 Environmental Statement - Appendix 12.2: Marine Mammal Information and Survey Data
Other
Size: 302 KB
Norfolk Boreas Limited
6.3.10.3 Environmental Statement - Appendix 10.3 Comparison of MarLIN and Norfolk Boreas sensitivity definitions for benthic receptors
Other
Size: 24 MB
Norfolk Boreas Limited
6.3.10.1 Environmental Statement - Appendix 10.1 Benthic Characterisation Report
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.8.8 Environmental Statement - Figure 8.8 Location of seabed sediment samples within the Norfolk Boreas site and project interconnector cable search area
Other
Size: 674 KB
Norfolk Boreas Limited
6.3.15.5 Environmental Statement - Appendix 15.5 Hazard Log
Other
Size: 10 MB
Norfolk Boreas Limited
6.3.13.1 Environmental Statement - Appendix 13.1 Ornithology Technical Appendix
Other
Size: 478 KB
Norfolk Boreas Limited
6.3.11.2 Environmental Statement - Appendix 11.2 Fish and Shellfish Ecology Consultation Responses
Other
Size: 11 MB
Norfolk Boreas Limited
6.3.11.1 Environmental Statement - Appendix 11.1 Fish and Shellfish Ecology Technical Report
Other
Size: 611 KB
Norfolk Boreas Limited
6.3.12.1 Environmental Statement - Appendix 12.1 Marine Mammal Consultation responses
Other
Size: 493 KB
Norfolk Boreas Limited
6.3.17.1 Environmental Statement - Appendix 17.1: Offshore Archaeology and Cultural Heritage Consultation Responses
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.9 Environmental Statement - Figure 8.9 Location of seabed sediment samples along the offshore cable corridor
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.7 Environmental Statement - Figure 8.7 Regional wave observations
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.15.3 Environmental Statement - Appendix 15.3 Consequences of collision and allision
Other
Size: 462 KB
Norfolk Boreas Limited
6.3.12.5 Environmental Statement - Appendix 12.5: Additional Underwater Noise Assessments
Other
Size: 617 KB
Norfolk Boreas Limited
6.3.12.4 Environmental Statement - Appendix 12.4: Additional Assessment in relation to the Southern North Sea Special Area of Conservation (SNS SAC)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.9.1 Environmental Statement - Figure 9.1 Offshore Cable Corridor and landfall area against WFD water bodies and designated bathing waters
Other
Size: 446 KB
Norfolk Boreas Limited
6.3.12.6 Environmental Statement - Appendix 12.6: Additional Cumulative Impact Assessment (CIA) Scenarios
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.10.2 Environmental Statement - Appendix 10.2 Benthic Ecology Data Analysis
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.9.2 Environmental Statement - Figure 9.2 Norfolk Boreas Contaminant Sample Analysis locations
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.8.6 Environmental Statement - Figure 8.6 Regional current roses
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.4 Environmental Statement - Figure 8.4 Bathymetry of the project interconnector search area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.2 Environmental Statement - Figure 8.2 Regional bathymetry
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.10 Environmental Statement - Figure 8.10 Regional sediment transport pathways in the vicinity of Norfolk Boreas (Kenyon and Cooper, 2005)
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.11 Environmental Statement - Figure 4.11 Onshore project substation footprint options
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.4.9 Environmental Statement - Figure 4.9 Substation search area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.4.7 Environmental Statement - Figure 4.7 Landfall location
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.4.5 Environmental Statement - Figure 4.5 Landfall search area
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.15 Environmental Statement - Figure 4.15 National Grid substation extension under Scenario 1
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.13 Environmental Statement - Figure 4.13 Onshore project substation search area under Scenario 2 as presented at PEIR
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.4.6 Environmental Statement - Figure 4.6 Landfall site options
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.4.4 Environmental Statement - Figure 4.4 Ranking of indicative landfall sites
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.2 Environmental Statement - Figure 5.2 Proposed offshore disposal sites
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.17 Environmental Statement - Figure 4.17 Project interconnector cable search area
Other
Size: 38 MB
Norfolk Boreas Limited
6.2.4.8 Environmental Statement - Figure 4.8 Onshore Infrastructure as presented at PEIR
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.6 Environmental Statement - Figure 5.6 Onshore project substation and extension to National Grid substation Scenario 2
Other
Size: 31 MB
Norfolk Boreas Limited
6.2.5.4 Environmental Statement - Figure 5.4 Onshore project area Scenario 1 and 2
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.5 Environmental Statement - Figure 8.5 Position of the amphidromic point and co-tidal lines relative to the position of Norfolk Boreas
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.8.3 Environmental Statement - Figure 8.3 Bathymetry of the Norfolk Boreas offshore cable corridor
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.4.2 Environmental Statement - Figure 4.2 Offshore constraints
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.1 Environmental Statement - Figure 8.1 Bathymetry of Norfolk Boreas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.5 Environmental Statement - Figure 5.5 Onshore project substation and extension to National Grid substation Scenario 1
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.16 Environmental Statement - Figure 4.16 National Grid substation extension under Scenario 2
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.14 Environmental Statement - Figure 4.14 Onshore project substation location under Scenario 2
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.12 Environmental Statement - Figure 8.12 Location of sand waves along the Norfolk Boreas offshore cable corridor
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.11 Environmental Statement - Figure 8.11 Marine physical processes receptors relevant to Norfolk Boreas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.16 Environmental Statement - Figure 8.16 Zones of potential influence on the wave regime for Norfolk Boreas, Norfolk Vanguard and East Anglia THREE
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.15 Environmental Statement - Figure 8.15 Zones of potential influence in the tidal regimes for Norfolk Boreas, Norfolk Vanguard and East Anglia THREE
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.3 Environmental Statement - Figure 4.3 Provisional offshore cable corridors to three landfall locations
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.4.1 Environmental Statement - Figure 4.1 The Former East Anglia Zone
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.3 Environmental Statement - Figure 5.3 Landfall
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.1 Environmental Statement - Figure 5.1 Offshore project areas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.17 Environmental Statement - Figure 8.17 Zones of potential influence of the combined wave and tide regimes for Norfolk Boreas, Norfolk Vanguard and East Anglia THREE
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.12 Environmental Statement - Figure 4.12 Onshore project substation location under Scenario 1
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.4.10 Environmental Statement - Figure 4.10 Refined substation search area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.14 Environmental Statement - Figure 8.14 Zones of potential influence on the wave regime for Norfolk Boreas site
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.13 Environmental Statement - Figure 8.13 Zones of potential influence in the tidal regime for the Norfolk Boreas site
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.30.4 Environmental Statement - Figure 30.4 Serviced accommodation locations
Other
Size: 38 MB
Norfolk Boreas Limited
6.2.30.3 Environmental Statement - Figure 30.3 Public Rights of Way, cycle routes and long distance trails
Other
Size: 769 KB
Norfolk Boreas Limited
6.2.29.9 Environmental Statement - Figure 29.9 Scenario 1 - Indicative Onshore Project Substation Mitigation Planting – Norfolk Boreas and Norfolk Vanguard
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.44 Environmental Statement - Figure 29.44 Scenario 2 - Viewpoint 10: Holme Hale
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.42 Environmental Statement - Figure 29.42 Scenario 2 - Viewpoint 8: Chapel Road, Necton
Other
Size: 11 MB
Norfolk Boreas Limited
6.2.29.40 Environmental Statement - Figure 29.40 Scenario 2 - Viewpoint 6: A47, Top Farm
Other
Size: 39 MB
Norfolk Boreas Limited
6.2.30.2 Environmental Statement - Figure 30.2 Tourism and recreation assets in the vicinity of onshore infrastructure
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.29.46 Environmental Statement - Figure 29.46 Scenario 2 - Viewpoint 12: Ivy Todd
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.29.7 Environmental Statement - Figure 29.7 Scenario 1 - Cumulative Developments
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.8 Environmental Statement - Figure 29.8 Scenario 1 - Cumulative Zone of Theoretical Visibility Norfolk Vanguard Onshore Project Substation and National Grid Substation Extension / Norfolk Boreas Onshore Project Substation and National Grid Substation Extension
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.6 Environmental Statement - Figure 29.6 Scenario 1 - Zone of Theoretical Visibility National Grid Substation Extension
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.5 Environmental Statement - Figure 29.5 Scenario 1 – Zone of Theoretical Visibility Onshore Project Substation
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.30.1 Environmental Statement - Figure 30.1 Coastal tourism and recreation assets
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.29.45 Environmental Statement - Figure 29.45 Scenario 2 - Viewpoint 11: Hale Road, East of Holme Hale Hall
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.29.4 Environmental Statement - Figure 29.4 Scenario 1 – Viewpoints Onshore Project Substation / National Grid Substation Extension
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.43 Environmental Statement - Figure 29.43 Scenario 2 - Viewpoint 9: St Andrews Lane, Necton
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.29.41 Environmental Statement - Figure 29.41 Scenario 2 - Viewpoint 7: Ivy Todd Road east
Other
Size: 11 MB
Norfolk Boreas Limited
6.2.29.39 Environmental Statement - Figure 29.39 Scenario 2 - Viewpoint 5: A47, Spicer’s Corner
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.29.35 Environmental Statement - Figure 29.35 Scenario 2 - Viewpoint 1: Ivy Todd Road west
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.38 Environmental Statement - Figure 29.38 Scenario 2 - Viewpoint 4: Necton Substation Access
Other
Size: 16 MB
Norfolk Boreas Limited
6.2.29.37 Environmental Statement - Figure 29.37 Scenario 2 - Viewpoint 3: Lodge Lane north
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.29.33 Environmental Statement - Figure 29.33 Scenario 1 - Viewpoint 11: Hale Road, East of Holme Hale Hall
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.32 Environmental Statement - Figure 29.32 Scenario 1 - Viewpoint 10: Holme Hale
Other
Size: 12 MB
Norfolk Boreas Limited
6.2.29.36 Environmental Statement - Figure 29.36 Scenario 2 - Viewpoint 2: Lodge Lane south
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.29.34 Environmental Statement - Figure 29.34 Scenario 1 - Viewpoint 12: Ivy Todd
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.31 Environmental Statement - Figure 29.31 Scenario 1 - Viewpoint 9: St Andrews Lane, Necton
Other
Size: 23 MB
Norfolk Boreas Limited
6.2.29.3 Environmental Statement - Figure 29.3 Scenario 1 - Visual Receptors
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.30 Environmental Statement - Figure 29.30 Scenario 1 - Viewpoint 8: Chapel Road, Necton
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.29.29 Environmental Statement - Figure 29.29 Scenario 1 - Viewpoint 7: Ivy Todd Road east
Other
Size: 9 MB
Norfolk Boreas Limited
6.2.29.25 Environmental Statement - Figure 29.25 Scenario 1 - Viewpoint 3: Lodge Lane north
Other
Size: 46 MB
Norfolk Boreas Limited
6.2.29.23 Environmental Statement - Figure 29.23 Scenario 1 - Viewpoint 1: Ivy Todd Road west
Other
Size: 532 KB
Norfolk Boreas Limited
6.2.29.21b Environmental Statement - Figure 29.21b Scenario 2 – Indicative A47 Mitigation Planting
Other
Size: 11 MB
Norfolk Boreas Limited
6.2.29.27 Environmental Statement - Figure 29.27 Scenario 1 - Viewpoint 5: A47, Spicer’s Corner
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.21a Environmental Statement - Figure 29.21a Scenario 2 – Indicative A47 Planting Removals
Other
Size: 12 MB
Norfolk Boreas Limited
6.2.29.24 Environmental Statement - Figure 29.24 Scenario 1 - Viewpoint 2: Lodge Lane south
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.29.22 Environmental Statement - Figure 29.22 Scenario 2 - Strategic Plan of Indicative Mitigation Planting
Other
Size: 12 MB
Norfolk Boreas Limited
6.2.29.28 Environmental Statement - Figure 29.28 Scenario 1 - Viewpoint 6: A47, Top Farm
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.26 Environmental Statement - Figure 29.26 Scenario 1 - Viewpoint 4: Necton Substation Access
Other
Size: 750 KB
Norfolk Boreas Limited
6.2.29.19 Environmental Statement - Figure 29.19 Scenario 2 - Indicative Onshore Project Substation Mitigation Planting
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.17 Environmental Statement - Figure 29.17 Scenario 2 - Zone of Theoretical Visibility National Grid Substation Extension
Other
Size: 24 MB
Norfolk Boreas Limited
6.2.29.2 Environmental Statement - Figure 29.2 Scenario 1 - Landscape Designations and Landscape Character Areas (Map 1 of 9)
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.29.15 Environmental Statement - Figure 29.15 - Scenario 2 - Viewpoints Onshore Project Substation / National Grid Substation Extension
Other
Size: 24 MB
Norfolk Boreas Limited
6.2.29.13 Environmental Statement - Figure 29.13 Scenario 2 - Landscape Designations and Landscape Character Areas (Map 1 of 9)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.29.18 Environmental Statement - Figure 29.18 Scenario 2 - Cumulative Developments
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.16 Environmental Statement - Figure 29.16 Scenario 2 - Zone of Theoretical Visibility Onshore Project Substation
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.20a Environmental Statement - Figure 29.20a Scenario 2 - Indicative National Grid Substation Extension Planting Removals
Other
Size: 788 KB
Norfolk Boreas Limited
6.2.29.20b Environmental Statement - Figure 29.20b Scenario 2 - Indicative National Grid substation extension Mitigation Planting
Other
Size: 23 MB
Norfolk Boreas Limited
6.2.29.14 Environmental Statement - Figure 29.14 Scenario 2 - Visual Receptors (Map 1 of 9)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.29.11 Environmental Statement - Figure 29.11 Scenario 1 – Strategic Plan of Indicative Mitigation Planting
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.12 Environmental Statement - Figure 29.12 Scenario 2 - Study Area
Other
Size: 45 MB