Norfolk Boreas

You can filter the results to show only the items that match your interest.

Date

SourceDescription
Other
Size: 103 KB
Accompanied Site Inspection Itinerary
Other
Size: 96 KB
Polly Brockis
Additional Submission - Nominations of suggested locations for site inspections - Accepted at the discretion of the Examining Authority
Other
Size: 128 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 3: Onshore effects including the draft Development Consent Order
Other
Size: 99 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 4: Offshore effects including the draft Development Consent Order
Other
Size: 3 MB
Norfolk Boreas Limited
Hearing Notice
Other
Size: 99 KB
Natural England
Deadline 3 Submission - Cover Letter
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 3 Submission - Comments on responses to ExA's Written Questions Appendix 1 (Part 2 of 2)
Other
Size: 250 KB
Marine Management Organisation
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 139 KB
Natural England
Deadline 3 Submission - Response to Onshore Ecology and Onshore Ornithology Documents submitted at Deadline 1 and 2
Other
Size: 257 KB
National Grid
Deadline 3 Submission - Responses to ExA's Written Questions - late response for Deadline 2
Other
Size: 521 KB
Natural England
Deadline 3 Submission - Risk and Issue Register
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Response to North Norfolk District Council's Local Impact Report
Other
Size: 433 KB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Response to Breckland Council's Local Impact Report
Other
Size: 376 KB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Response to Broadland District Council's Local Impact Report
Other
Size: 377 KB
Marine Management Organisation
Deadline 3 Submission - Other submission
Other
Size: 944 KB
Colin King
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 654 KB
Norfolk Boreas Limited
Deadline 3 Submission - Guide to the Application (Revision 5)
Other
Size: 53 KB
Natural England
Deadline 3 Submission - Advice on Cable Protection Assessment for Offshore Windfarms and Inclusion in Marine Licenses - Draft Position Paper December 2019
Other
Size: 420 KB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Response to Norfolk County Council's Local Impact Report
Other
Size: 262 KB
Norfolk Boreas Limited
Deadline 3 Submission - Cover Letter
Other
Size: 513 KB
The Royal Society for the Protection of Birds
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 194 KB
Cawston Parish Council
Deadline 3 Submission - Comments on Deadline 2 submissions
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 3 Submission - Applicant's Comments on Written Representations and Additional Submissions
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 3 Submission - Implications for the Norfolk Boreas Application for Development Consent of any Secretary of State decision on the Norfolk Vanguard Offshore Windfarm Application
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 3 Submission - Comments on responses to ExA's Written Questions Appendix 2
Other
Size: 7 MB
Norfolk Boreas Limited
Deadline 3 Submission - Comments on responses to ExA's Written Questions Appendix 1 (Part 1 of 2)
Other
Size: 101 KB
Necton Substation Action Group
Deadline 3 Submission - Other Submission
Other
Size: 179 KB
Necton Substation Action Group
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 1 MB
National Farmers Union
Deadline 3 Submission - Responses to ExA's Written Questions - Late Response for Deadline 2
Other
Size: 328 KB
The Wildlife Trusts
Deadline 3 Submission - Responses to ExA's Written Questions - Late Response for Deadline 2
Other
Size: 152 KB
Cawston Parish Council
Deadline 3 Submission - Comments on Deadline 2 Norfolk Boreas - Appendix 14.2 Norfolk Vanguard Offshore Wind Farm Alternative Construction Routes at Cawston, Applicants Comments on Deadline 6 Written Submissions: Appendix 2
Other
Size: 3 MB
Norfolk Boreas Limited
Deadline 3 Submission - Comments on responses to ExA's Written Questions
Other
Size: 164 KB
Natural England
Deadline 3 Submission - Response to Norfolk Boreas comments on Relevant Representations [AS-024] Table 26 DCO and DML
Other
Size: 259 KB
Oulton Parish Council
Deadline 3 Submission - Comments on responses to ExA’s Written Questions
Other
Size: 115 KB
Historic England
Deadline 3 Submission - Comments on responses to ExA's Written Questions
Other
Size: 119 KB
Notification of hearings and Accompanied Site Inspection - January 2020
Other
Size: 250 KB
George Freeman MP
Deadline 2 Submission - Written Representation
Other
Size: 337 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Historic England
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 4
Other
Size: 765 KB
Breckland Council
Deadline 2 Submission - Statement of Common Ground
Other
Size: 692 KB
Norfolk Boreas Limited
Deadline 2 Submission - Outline Skills and Employment Strategy
Other
Size: 128 KB
Maritime and Coastguard Agency
Deadline 2 Submission - Written Representation
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Tracked Changes) Part 2 of 4
Other
Size: 569 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Breckland Council
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 596 KB
Norfolk Boreas Limited
Deadline 2 Submission - Written Representation
Other
Size: 395 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Trinity House
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 2 Submission - Method Statement for the crossing of the River Wensum and adjacent watercourses
Other
Size: 586 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Royal Yachting Association
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 1 Crossing 1
Other
Size: 306 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Chamber of Shipping
Other
Size: 376 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the National Federation of Fishermen's Organisations and VisNed
Other
Size: 553 KB
North Norfolk District Council
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 6 Happisburgh
Other
Size: 302 KB
Broadland District Council
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 629 KB
Royal Society for the Protection of Birds
Deadline 2 Submission - Written Representation
Other
Size: 371 KB
Norfolk Boreas Limited
Deadline 2 Submission - 5.4 Consents and Licences Required Under Other Legislation (Version 2) Tracked Changes)
Other
Size: 93 KB
Ministry of Defence
Deadline 2 Submission - MoD safeguarding position - Other Submission
Other
Size: 13 MB
Norfolk County Council
Deadline 2 Submission - Local Impact Report
Other
Size: 316 KB
Norfolk Boreas Limited
Deadline 2 Submission - Clarification Note Cable Logistics Area
Other
Size: 126 KB
Necton Parish Council
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Natural England (Version 2)
Other
Size: 8 MB
North Norfolk District Council
Deadline 2 Submission - Local Impact Report
Other
Size: 335 KB
Norfolk Boreas Limited
Deadline 2 Submission - 5.4 Consents and Licences Required under Other Legislation (Version 2) Clean)
Other
Size: 108 KB
Patricia Lockwood
Deadline 2 Submission - Written Representation
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 3 Crossing 3
Other
Size: 459 KB
Norfolk Boreas Limited
Deadline 2 Submission - Clarification Note - Landfall Method
Other
Size: 436 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Environment Agency
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Tracked Changes) Part 4 of 4
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Eastern Inshore Fisheries and Conservation Authority
Other
Size: 384 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the National Farmers Union
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 4 Crossings 4 & 5
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Broadland District Council
Other
Size: 213 KB
Cawston Parish Council
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 639 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Whale and Dolphin Conservation
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Tracked Changes) Part 1 of 4
Other
Size: 84 KB
Jan Burley
Deadline 2 Submission - Other Submission
Other
Size: 38 KB
Gowling WLG on behalf of Cadent Gas Limited
Deadline 2 Submission - Written Representation
Other
Size: 483 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Maritime and Coastguard Agency
Other
Size: 642 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statutory Undertaker Update
Other
Size: 340 KB
Norfolk Boreas Limited
Deadline 2 Submission - Implications of Separate Scenario Plans
Other
Size: 647 KB
Norfolk Boreas Limited
Deadline 2 Submission - Issue Specific Hearing 1 and 2 Action Points Tracker
Other
Size: 215 KB
The Wildlife Trusts
Deadline 2 Submission - Written Representation
Other
Size: 1,024 KB
Eastern Inshore Fisheries and Conservation Authority
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 179 KB
The Coal Authority
Deadline 2 Submission - Response to information requested by the ExA
Other
Size: 601 KB
Norfolk Boreas Limited
Deadline 2 Submission - Compulsory Acquisition Objections Schedule
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Clean) Part 2 of 3
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Norfolk County Council
Other
Size: 507 KB
National Grid
Deadline 2 Submission - Written Representation
Other
Size: 11 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Tracked Changes) Part 3 of 4
Other
Size: 614 KB
N2RS
Deadline 2 Submission - Written Representation
Other
Size: 884 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Marine Management Organisation
Other
Size: 662 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with North Norfolk District Council
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 2 Submission - Offshore Ornithology Assessment Update
Other
Size: 109 KB
Diana Lockwood
Deadline 2 Submission - Written Representation
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - 6.6 Schedule of Mitigation (Version 2) (Tracked Changes)
Other
Size: 80 KB
Jenny Smedley
Deadline 2 Submission - Other Submission
Other
Size: 13 MB
Oulton Parish Council
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 191 KB
National Trust
Deadline 2 Submission - Other submission - Withdrawal of objection
Other
Size: 833 KB
Natural England
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 248 KB
Necton Substation Action Group
Deadline 2 Submission - Other Submission
Other
Size: 112 KB
Necton Substation Action Group
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 1
Other
Size: 507 KB
Broadland District Council
Deadline 2 Submission - Cover Email
Other
Size: 420 KB
Environment Agency
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Highways England
Other
Size: 1 MB
Norfolk County Council
Deadline 2 Submission - Responses to ExA's Written Questions
Other
Size: 177 KB
Trinity House
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 579 KB
Norfolk Boreas Limited
Deadline 2 Submission - Clarification Note - Temporary Structures
Other
Size: 471 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Natural England (Offshore Ornithology)
Other
Size: 318 KB
Network Rail Infrastructure Limited
Deadline 2 Submission - Written Representation
Other
Size: 245 KB
National Federation of Fishermen's Organisations
Deadline 2 Submission - Written Representation
Other
Size: 88 KB
NATS Safeguarding
Deadline 2 Submission - Written Representation
Other
Size: 57 KB
Great Yarmouth Borough Council
Deadline 2 Submission - Written Representation
Other
Size: 196 KB
Broadland District Council
Deadline 2 Submission - Local Impact Report
Other
Size: 7 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 9
Other
Size: 123 KB
Historic England
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 805 KB
Norfolk Boreas Limited
Deadline 2 Submission - Guide to the Application (Version 4)
Other
Size: 648 KB
Whale and Dolphin Conservation
Deadline 2 Submission - Written Representation
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 5 Crossings 6 & 7
Other
Size: 636 KB
Corpusty and Saxthorpe Parish Council
Deadline 2 Submission - Written Representation
Other
Size: 481 KB
Natural England
Deadline 2 Submission - Risk and Issue Log
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 2 Submission - TerraConsult Ground Investigations Report Part 2 Crossing 2
Other
Size: 296 KB
Norfolk Boreas Limited
Deadline 2 Submission - Cover Letter
Other
Size: 616 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Commonality of Statements of Common Ground
Other
Size: 220 KB
Royal Society for the Protection of Birds
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 965 KB
Breckland Council
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 144 KB
Anglian Water Services Limited
Deadline 2 Submission - Written Representation
Other
Size: 449 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Orsted Hornsea Project Three
Other
Size: 216 KB
Marine Management Organisation
Deadline 2 Submission - Cover Letter
Other
Size: 12 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Clean) Part 1 of 3
Other
Size: 692 KB
Historic England
Deadline 2 Submission - Written Representation
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 2 Submission - 8.3 Design and Access Statement (Version 2) (Clean) Part 3 of 3
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 2 Submission - 6.6 Schedule of Mitigation (Version 2) (Clean)
Other
Size: 289 KB
Marine Management Organisation
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 102 KB
Maritime and Coastguard Agency
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 14
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 2 Submission - Responses to ExA's Written Questions - Appendices Section 8
Other
Size: 233 KB
Marine Management Organisation
Deadline 2 Submission - Summary of Relevant Representation
Other
Size: 496 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Wildlife Trusts and Norfolk Wildlife Trust
Other
Size: 150 KB
Breckland Council
Deadline 2 Submission - Local Impact Report
Other
Size: 381 KB
Norfolk County Council
Deadline 2 Submission - Other Submission - Response to the Dudgeon and Sheringham Shoal Wind Farm scoping consultations
Other
Size: 99 KB
Ministry of Defence
Deadline 2 Submission - Responses to ExA’s Written Questions
Other
Size: 86 KB
Natural England
Deadline 2 Submission - Cover Letter
Other
Size: 117 KB
Colin King
Deadline 2 Submission - Written Representation
Other
Size: 320 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with Anglian Water
Other
Size: 379 KB
Norfolk Boreas Limited
Deadline 2 Submission - Statement of Common Ground with the Royal Society for the Protection of Birds
Other
Size: 378 KB
Norfolk Boreas Limited
Deadline 2 Submission - Clarification Note Ecological Enhancements
Other
Size: 82 KB
Jenny Smedley
Deadline 1 Submission - Nominations of suggested locations and justifications for site inspections for consideration by the ExA
Other
Size: 2 MB
Oulton Parish Council
Deadline 1 Submission - Nominations of suggested locations and justifications for site inspections for consideration by the ExA
Other
Size: 109 KB
N2RS
Deadline 1 Submission - Submission of post-hearing documents including any written submissions of oral case
Other
Size: 35 MB
Jenny Smedley
Deadline 1 Submission - Other Submission
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.4 Works Plan (Part 2 of 4) (Version 2)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 1 Submission - 5.3.6.1 Habitats Regulations Assessment - Appendix 6.1 - Integrity Matrices (Tracked Changes) (Version 3)
Other
Size: 121 KB
Oulton Parish Council
Deadline 1 Submission - Submission of post-hearing document including any written submissions of oral case
Other
Size: 150 KB
Cawston Parish Council
Deadline 1 Submission - Submission of post-hearing document including any written submissions of oral case and justification for site inspections for consideration by the ExA
Other
Size: 465 KB
Norfolk Boreas Limited
Deadline 1 Submission - Applicant's Guide to the Application (Version 3)
Other
Size: 52 KB
Glenn Berry Chairman on behalf of Happisburgh Parish Council
Deadline 1 Submission - Submission of post-hearing document including any written submission of oral case
Other
Size: 343 KB
Glenn Berry Chairman on behalf of Happisburgh Parish Council
Deadline 1 Submission - Nomination of suggested locations and justifications for site inspections for consideration by the Examining Authority
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 1 Submission - 6.7 EIA and DCO Reconciliation Document (Clean) (Version 2)
Other
Size: 518 KB
Kate Pitcher
Deadline 1 Submission - Nominations of suggested locations and justifications for site inspections for consideration by the ExA - Accepted at the discretion of the Examining Authority
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 1 Submission - 5.3.5.3 Habitats Regulations Assessment - Appendix 5.3 - Screening Matrices (Clean) (Version 3)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan Appendices (Tracked Changes) (Version 2)
Other
Size: 646 KB
Natural England
Deadline 1 Submission - Other Submission - Appendix 2.6 Natural England advice note regarding consideration of small scale habitat loss within Special Areas of Conservation (SACs) in relation to cable protection, omitted in error from Natural England's Relevant Representation
Other
Size: 96 KB
Diana Lockwood
Deadline 1 Submission - Nomination of suggested locations and justifications for site inspections for consideration by the Examining Authority
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 4.3 Book of Reference (Clean) (Version 2)
Other
Size: 99 KB
Colin King
Deadline 1 Submission - Nomination of suggested locations and justifications for site inspections for consideration by the Examining Authority
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.20 Outline Norfolk Boreas Haisborough Hammond and Winterton Special Area of Conservation Site Integrity Plan (Tracked Changes) (Version 2)
Other
Size: 678 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.12 Offshore In-Principle Monitoring Plan (Tracked Changes) (Version 2)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan Appendices (Clean) (Version 2)
Other
Size: 1 MB
Julian Pearson
Deadline 1 Submission - Submission of post-hearing documents including any written submissions of oral case - Accepted at the discretion of the Examining Authority
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 1 Submission - Applicant's Nomination of Locations to be Inspected
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.4 Works Plan (Part 4 of 4) (Version 2)
Other
Size: 318 KB
Marine Management Organisation
Deadline 1 Submission - Post-hearing document including any written submission of oral case
Other
Size: 15 MB
Oulton Parish Council
Deadline 1 Submission - Other Submission - Summary of Norfolk Vanguard issues and submissions for Norfolk Vanguard deadlines
Other
Size: 34 KB
Necton Parish Council
Deadline 1 Submission - Submission of post-hearing document including any written submission of oral case
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.7 Outline Landscape and Ecological Management Strategy (Clean) (Version 2)
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - Seabed Mobility Study
Other
Size: 158 KB
Necton Substation Action Group
Deadline 1 - Submission in lieu of attendance at Issue Specific Hearing 2 on Environmental Matters including HRA on 14 November 2019
Other
Size: 381 KB
Norfolk Boreas Limited
Deadline 1 Submission - Written Summary of the Applicant's Oral Case at Issue Specific Hearing 2 - Environmental Matters including Habitats Regulations Assessment
Other
Size: 82 KB
The Monk Family
Deadline 1 Submission -Nomination of suggested locations and justification for site inspections for consideration by the ExA
Other
Size: 434 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.11 Outline Offshore Operations and Maintenance Plan (Tracked Changes) (Version 2)
Other
Size: 10 MB
Necton Substation Action Group
Deadline 1 Submission - Other Submission
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 1 Submission - 3.1 Updated draft DCO (Clean) (Version 3)
Other
Size: 87 KB
Natural England
Deadline 1 Submission - Other Submission - Response to the Rule 8 Letter
Other
Size: 191 KB
Nicola Banham
Deadline 1 Submission - Submission of post-hearing document including any written submission of oral case
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 1 Submission - Clarification Note Trenchless Crossings and Potential Effects of Breakout on the River Wensum
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 4.3 Book of Reference (Tracked Changes) (Version 2)
Other
Size: 2 MB
Norfolk Boreas Limited
Deadline 1 Submission - 3.1 Updated draft DCO (Tracked Changes) (Version 3)
Other
Size: 426 KB
Natural England
Deadline 1 Submission - Other Submission - Updated Risk and Issues Log
Other
Size: 97 KB
Guy Pitcher
Deadline 1 Submission - Submission of post-hearing documents including any written submissions of oral case - Accepted at the discretion of the Examining Authority
Other
Size: 15 MB
Oulton Parish Council
Deadline 1 Submission - Other Submission - Dudgeon and Sheringham Shoal Offshore Wind Farm Extensions Scoping Report of October 2019
Other
Size: 665 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.16 Outline Scour Protection and Cable Protection Plan (Tracked Changes) (Version 2)
Other
Size: 904 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.1 Outline Code of Construction Practice (Tracked Changes) (Version 2)
Other
Size: 625 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.12 Offshore In-Principle Monitoring Plan (Clean) (Version 2)
Other
Size: 329 KB
Norfolk Boreas Limited
Deadline 1 Submission - Schedule of Changes to the draft Development Consent Order (Version 2)
Other
Size: 58 KB
Norfolk Boreas Limited
Deadline 1 Submission - Cover Letter
Other
Size: 29 MB
Cawston Parish Council
Deadline 1 Submission - Other Submission - Submissions made to the Hornsea 3 and Norfolk Vanguard Examinations
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 1 Submission - 6.7 EIA and DCO Reconciliation Document (Tracked Changes) (Version 2)
Other
Size: 6 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.20 Outline Norfolk Boreas Haisborough Hammond and Winterton Special Area of Conservation Site Integrity Plan (Clean) (Version 2)
Other
Size: 12 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan Figures (Version 2)
Other
Size: 10 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.4 Works Plan (Part 3 of 4) (Version 2)
Other
Size: 9 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.4 Works Plan (Part 1 of 4) (Version 2)
Other
Size: 2 MB
Oulton Parish Council
Deadline 1 Submission - Other Submission - Questions and comments made by the Parish Council at the Preliminary Meeting and copy of a letter from George Freeman MP to BEIS
Other
Size: 373 KB
Norfolk Boreas Limited
Deadline 1 Submission - Checklist of East Inshore and Offshore Marine Plans Objectives
Other
Size: 194 KB
Savills (UK) Ltd on behalf of Mr C Allhusen
Deadline 1 Submission - Nomination of suggested locations and justifications for site inspections for consideration by the ExA
Other
Size: 13 MB
Ray and Diane Pearce
Deadline 1 Submission - Submission of post-hearing document including any written submission of oral case and nomination of suggested locations and justifications for consideration by the ExA - Accepted at the discretion of the Examining Authority
Other
Size: 2 MB
George Freeman MP
Deadline 1 Submission - Other Submission
Other
Size: 900 KB
Norfolk Boreas Limited
Deadline 1 Submission - 5.3.6.1 Habitats Regulations Assessment - Appendix 6.1 - Integrity Matrices (Clean) (Version 3)
Other
Size: 133 KB
David Vince & Nicola Draycott
Deadline 1 Submission - Other Submission - Accepted at the discretion of the Examining Authority
Other
Size: 664 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.16 Outline Scour Protection and Cable Protection Plan (Clean) (Version 2)
Other
Size: 902 KB
Glenn Berry Chairman on behalf of Happisburgh Parish Council
Deadline 1 Submission - Other Submission
Other
Size: 5 MB
Norfolk Boreas Limited
Deadline 1 Submission - 5.3.5.3 Habitats Regulations Assessment - Appendix 5.3 - Screening Matrices (Tracked Changes) (Version 3)
Other
Size: 682 KB
Norfolk Boreas Limited
Deadline 1 Submission - Written Summary of the Applicant's Oral Case at Issue Specific Hearing 1 - draft Development Consent Order
Other
Size: 613 KB
Norfolk Boreas Limited
Deadline 1 Submission - Applicant's Response to the Open Floor Hearing
Other
Size: 756 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan (Tracked Changes) (Version 2)
Other
Size: 880 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.1 Outline Code of Construction Practice (Clean) (Version 2)
Other
Size: 413 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.11 Outline Offshore Operations and Maintenance Plan (Clean) (Version 2)
Other
Size: 4 MB
Norfolk Boreas Limited
Deadline 1 Submission - 2.2 Land Plan (Offshore) (Version 2)
Other
Size: 804 KB
Norfolk Boreas Limited
Deadline 1 Submission - 8.8 Outline Traffic Management Plan (Clean) (Version 2)
Other
Size: 1 MB
Norfolk Boreas Limited
Deadline 1 Submission - 8.7 Outline Landscape and Ecological Management Strategy (Tracked Changes) (Version 2)
Other
Size: 77 KB
Necton Parish Council
Deadline 1 Submission - Nominations of suggested locations and justifications for site inspections for consideration by the ExA
Other
Size: 119 KB
Preliminary Meeting Note
Other
Size: 860 KB
Written Questions
Other
Size: 265 KB
Rule 8 – notification of timetable for the examination
Other
audio recording
Size: 37 MB
Recording of Issue Specific Hearing 2 - Part 3 of 3
Issue Specific Hearing on Environmental Matters including Habitats Regulations Assessment - 14 November 2019
Other
audio recording
Size: 49 MB
Recording of Issue Specific Hearing 2 - Part 1 of 3
Issue Specific Hearing on Environmental Matters including Habitats Regulations Assessment - 14 November 2019
Other
audio recording
Size: 62 MB
Recording of Open Floor Hearing 1 - 13 November 2019
Other
audio recording
Size: 63 MB
Recording of Issue Specific Hearing 2 - Part 2 of 3
Issue Specific Hearing on Environmental Matters including Habitats Regulations Assessment - 14 November 2019
Other
Size: 99 KB
The Planning Inspectorate
Action points arising from the Issue Specific Hearing on environmental matters including HRA held on 14 November 2019
Other
Size: 109 KB
Note of Unaccompanied Site Inspections up to 11 November 2019
The Examining Authority's updated USI record
Other
audio recording
Size: 101 MB
Recording of Issue Specific Hearing 1 - Part 1 of 2
Issue Specific Hearing on draft Development Consent Order - 13 November 2019
Other
audio recording
Size: 64 MB
Recording of Issue Specific Hearing 1 - Part 2 of 2
Issue Specific Hearing on draft Development Consent Order - 13 November 2019
Other
Size: 77 KB
The Planning Inspectorate
Action points arising from the Issue Specific Hearing on the draft Development Consent Order held on 13 November 2019
Other
Size: 89 KB
Norfolk Boreas Limited
List of appearances for the Applicant at the Issue Specific Hearing on environmental matters including HRA on 14 November 2019
Other
Size: 84 KB
Norfolk Boreas Limited
List of appearances for the Applicant at the Issue Specific Hearing on the draft Development Consent Order on 13 November 2019
Other
audio recording
Size: 57 MB
Recording of Preliminary Meeting - 12 November 2019
Other
Size: 138 KB
NATS Safeguarding
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 96 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 2: Environmental Matters including HRA - Thursday 14 November 2019
Other
Size: 781 KB
Examination Library
Other
Size: 8 MB
Norfolk Boreas Limited
Additional Submissions - Updated draft DCO (Revision 2) (Tracked Changes) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 529 KB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with Natural England (Offshore Ornithology) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with Marine Management Organisation - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 8 MB
Norfolk Boreas Limited
Additional Submissions - Updated draft DCO (Revision 2) (Clean) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with Natural England - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 240 KB
North Norfolk District Council
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 101 KB
Polly Brockis
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submissions - Explanatory Memorandum (Revision 2) (Clean) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 626 KB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with The Wildlife Trusts and Norfolk Wildlife Trust - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 468 KB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with The Royal Society for the Protection of Birds - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 799 KB
Norfolk Boreas Limited
Additional Submissions - Explanatory Memorandum (Revision 2) (Tracked Changes) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 664 KB
Norfolk Boreas Limited
Additional Submissions - Statement of Common Ground with Environment Agency - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 522 KB
Norfolk Boreas Limited
Additional Submissions - Applicant's guide to the Application (Revision 2) - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 142 KB
Environment Agency
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 653 KB
Norfolk Boreas Limited
Additional Submissions - Applicant's Response to the Rule 6 Letter and Cover Letter for Annex F Documents - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 176 KB
Highways England
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 3 MB
Norfolk Boreas Limited
Additional Submissions - Comments on Relevant Representations - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 256 KB
Cawston Parish Council
Additional Submissions - Comments on Relevant Representations - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 439 KB
Norfolk Boreas Limited
Additional Submissions - Applicant's Updated draft DCO Schedule of Changes - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 8 MB
Norfolk Boreas Limited
Additional Submissions - Comments on Relevant Representations Appendices - Submitted in response to the Examining Authority’s request in the Rule 6 Letter of 11 October 2019
Other
Size: 304 KB
Marine Management Organisation
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 490 KB
Natural England
Additional Submission - Response to the Rule 6 Letter of 11 October 2019
Other
Size: 151 KB
The Planning Inspectorate
Agenda for Issue Specific Hearing 1: The draft Development Consent Order - Wednesday 13 November 2019
Other
Size: 3 MB
Norfolk Boreas Limited
Notice of Preliminary Meeting and Hearings on 12 - 14 November 2019
Other
Size: 295 KB
Rule 6 letter - Notification of the preliminary meeting and matters to be discussed
Other
Size: 1 MB
Norman Lamb MP
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 94 KB
Ministry of Defence
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 83 KB
Julian Pearson
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 207 KB
Mr Geoffrey Vout
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 82 KB
Greg Peck
Additional Submission - Accepted at the discretion of the Examining Authority
Other
Size: 95 KB
Note of Unaccompanied Site Inspections up to 1 October 2019
Other
Size: 96 KB
Notification of Amendment to Panel Membership
Other
Size: 10 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Land Plans Part 3 - Accepted at the discretion of the Examining Authority
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Appendix 5.3 (Tracked Changes) - Habitats Regulations Assessment - Screening Matrices (Version 2) - Accepted at the discretion of the Examining Authority
Other
Size: 10 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Land Plans Part 2 - Accepted at the discretion of the Examining Authority
Other
Size: 123 KB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Accepted at the discretion of the Examining Authority
Other
Size: 9 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Land Plans Part 4 - Accepted at the discretion of the Examining Authority
Other
Size: 6 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Land Plans Part 5 - Accepted at the discretion of the Examining Authority
Other
Size: 988 KB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Appendix 6.1 - Habitats Regulations Assessment - Integrity Matrices Version 2 - Accepted at the discretion of the Examining Authority
Other
Size: 3 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Special Category Land Plans - Accepted at the discretion of the Examining Authority
Other
Size: 10 MB
Norfolk Boreas Limited
Additional Submission- Response to Section 51 Advice - Land Plans Part 1 - Accepted at the discretion of the Examining Authority
Other
Size: 1 MB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Appendix 5.3 - Habitats Regulations Assessment - Screening Matrices Version 2 - Accepted at the discretion of the Examining Authority
Other
Size: 465 KB
Norfolk Boreas Limited
Additional Submission - Response to Section 51 Advice - Appendix 6.1 (Tracked Changes) - Habitats Regulations Assessment - Integrity Matrices Version 2 - Accepted at the discretion of the Examining Authority
Other
Size: 170 KB
Appointment of the Examining Authority
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.11 Environmental Statement - Chapter 11 Fish and Shellfish Ecology
Other
Size: 38 KB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports Annex G Plates (2018 Survey) (Confidential)
Other
Size: 35 KB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports Annex B Badger Results (Confidential)
Other
Size: 37 KB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports Annex G Plates (2017 Survey) (Confidential)
Other
Size: 114 KB
Norfolk Boreas Limited
Section 56 Notice
Other
Size: 188 KB
South Norfolk Council
Adequacy of Consultation Representation
Other
Size: 204 KB
Broadland District Council
Adequacy of Consultation Representation
Other
Size: 184 KB
Norfolk County Council
Adequacy of Consultation Representation
Other
Size: 269 KB
North Norfolk District Council
Adequacy of Consultation Representation
Other
Size: 278 KB
Borough Council of King's Lynn and West Norfolk
Adequacy of Consultation Representation
Other
Size: 182 KB
Norwich City Council
Adequacy of Consultation Representation
Other
Size: 123 KB
Suffolk County Council
Adequacy of Consultation Representation
Other
Size: 182 KB
Great Yarmouth Borough Council
Adequacy of Consultation Representation
Other
Size: 182 KB
Section 51 advice to the Applicant
Other
Size: 363 KB
Section 55 Checklist
Other
Size: 135 KB
Notification of Decision to Accept Application
Other
Size: 20 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2018 Report Annex G Plates - Target Note Photos
Other
Size: 20 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Target Notes PART 3
Other
Size: 30 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Target Notes PART 1
Other
Size: 20 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2018 Report Annex G Plates - Bat Feature Photos by Object
Other
Size: 42 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Target Notes PART 2
Other
Size: 40 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Bats PART 2
Other
Size: 43 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports, 2017 Report Annex G Plates - Bats PART 1
Other
Size: 4 MB
Norfolk Boreas Limited
6.7 EIA and DCO Reconciliation Document
Other
Size: 4 MB
Norfolk Boreas Limited
6.5 Scoping Opinion as given by the Secretary of State in June 2017.
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.4.5 Environmental Statement - Appendix 4.5 Norfolk Vanguard and Norfolk Boreas Coastal Erosion Study
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.4.3 Environmental Statement - Appendix 4.3 Strategic approach to selecting a grid connection point
Other
Size: 442 KB
Norfolk Boreas Limited
6.3.8.1 Environmental Statement - Appendix 8.1 Particle size characteristics
Other
Size: 299 KB
Norfolk Boreas Limited
6.3.33.1 Environmental Statement - Appendix 33.1 Plans and Projects included in the Onshore CIA
Other
Size: 489 KB
Norfolk Boreas Limited
6.3.32.1 Environmental Statement - Appendix 32.1 Offshore CIA and Transboundary Impact Consultation
Other
Size: 705 KB
Norfolk Boreas Limited
6.3.31.2 Environmental Statement - Appendix 31.2 Supply Chain Assessment
Other
Size: 720 KB
Norfolk Boreas Limited
6.3.28.7 Environmental Statement - Appendix 28.7 Updated Baseline (Potential Sub-surface Archaeological Remains)
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.4.9 Environmental Statement - Appendix 4.9 Identification of Onshore Project Substation Search Sectors
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.4.7 Environmental Statement - Appendix 4.7 Identification of Onshore Cable Corridor
Other
Size: 8 MB
Norfolk Boreas Limited
6.3.5.3 Environmental Statement - Appendix 5.3 Ordtek UXO Review
Other
Size: 625 KB
Norfolk Boreas Limited
6.3.30.1 Environmental Statement - Appendix 30.1 Public rights of way and cycle routes
Other
Size: 514 KB
Norfolk Boreas Limited
6.3.29.1 Environmental Statement - Appendix 29.1 Landscape and Visual Impact Assessment Methodology
Other
Size: 448 KB
Norfolk Boreas Limited
6.3.5.5 Environmental Statement - Appendix 5.5 Underwater noise of UXO at the Norfolk Boreas sites
Other
Size: 702 KB
Norfolk Boreas Limited
6.3.31.3 Environmental Statement - Appendix 31.3 Offshore Wind Policy and Regional Sector Review
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.4.8 Environmental Statement - Appendix 4.8 Identification of Cable Relay Station Locations
Other
Size: 19 MB
Norfolk Boreas Limited
6.3.4.6 Environmental Statement - Appendix 4.6 HDD Feasibility Reports for Happisburgh and Bacton Green Landfall Sites
Other
Size: 13 MB
Norfolk Boreas Limited
6.3.4.1 Environmental Statement - Appendix 4.1 Initial HDD Feasibility Report
Other
Size: 1 MB
Norfolk Boreas Limited
6.6 Schedule of Mitigation
Other
Size: 5 MB
Norfolk Boreas Limited
6.4 Environmental Statement Non Technical Summary - Non-Technical Summary provides a lay persons' summary to the Environmental Statement.
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.32.2 Environmental Statement - Appendix 32.2 Plans and Projects included in the Offshore CIA and Transboundary Assessments
Other
Size: 671 KB
Norfolk Boreas Limited
6.3.5.1 Environmental Statement - Appendix 5.1 Onshore Scenario Comparison Table
Other
Size: 5 MB
Norfolk Boreas Limited
6.3.9.1 Environmental Statement - Appendix 9.1 Water Framework Directive Compliance Assessment-Marine WFD Water Bodies
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.4.4 Environmental Statement - Appendix 4.4 Preferred Landfall Location Technical Note
Other
Size: 30 MB
Norfolk Boreas Limited
6.3.4.2 Environmental Statement - Appendix 4.2 Cable Constructability Assessment
Other
Size: 530 KB
Norfolk Boreas Limited
6.3.31.1 Environmental Statement - Appendix 31.1 Supporting Information
Other
Size: 459 KB
Norfolk Boreas Limited
6.3.29.2 Environmental Statement - Appendix 29.2 Existing Environment
Other
Size: 3 MB
Norfolk Boreas Limited
6.3.5.2 Environmental Statement - Appendix 5.2 Cable Installation Study
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.4.10 Environmental Statement - Appendix 4.10 Onshore Project Substation Site Selection
Other
Size: 28 MB
Norfolk Boreas Limited
6.3.28.8 Environmental Statement - Appendix 28.8 Archaeological Geophysical Survey Report (Substation area)
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.28.6 Environmental Statement - Appendix 28.6 Non-Designated Heritage Assets Gazetteer
Other
Size: 279 KB
Norfolk Boreas Limited
6.3.6.1 Environmental Statement - Appendix 6.1 Statement of Competence
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.5.4 Environmental Statement - Appendix 5.4 Underwater Noise Assessment
Other
Size: 48 MB
Norfolk Boreas Limited
6.3.28.2 Environmental Statement - Appendix 28.2 Priority Archaeological Geophysical Survey Report (Part 2)
Other
Size: 48 MB
Norfolk Boreas Limited
6.3.28.2 Environmental Statement - Appendix 28.2 Priority Archaeological Geophysical Survey Report (Part 1)
Other
Size: 25 MB
Norfolk Boreas Limited
6.3.28.1 Environmental Statement - Appendix 28.1 Onshore Archaeological Desk Based (Baseline) Assessment
Other
Size: 262 KB
Norfolk Boreas Limited
6.3.24.9 Environmental Statement - Appendix 24.9 Employee Distribution (resident) Data
Other
Size: 224 KB
Norfolk Boreas Limited
6.3.24.7 Environmental Statement - Appendix 24.7 Scenario 1 - GHD Transport Assignment on Indicative Construction Programme
Other
Size: 276 KB
Norfolk Boreas Limited
6.3.26.3 Environmental Statement - Appendix 26.3 Air Quality Background Pollutant Concentrations
Other
Size: 293 KB
Norfolk Boreas Limited
6.3.26.1 Environmental Statement - Appendix 26.1 Air Quality Construction Dust Assessment
Other
Size: 7 MB
Norfolk Boreas Limited
6.3.28.3 Environmental Statement - Appendix 28.3 Geoarchaeological Watching Brief Report: Onshore Engineering Ground Investigations (GI) works (Phase 1)
Other
Size: 198 KB
Norfolk Boreas Limited
6.3.24.8 Environmental Statement - Appendix 24.8 Employee Distribution (in-migrant) Data
Other
Size: 978 KB
Norfolk Boreas Limited
6.3.25.3 Environmental Statement - Appendix 25.3 Operational Phase Assessment
Other
Size: 27 MB
Norfolk Boreas Limited
6.3.25.1 Environmental Statement - Appendix 25.1 Baseline Noise Survey
Other
Size: 714 KB
Norfolk Boreas Limited
6.3.28.5 Environmental Statement - Appendix 28.5 Designated Heritage Assets Gazetteer
Other
Size: 14 MB
Norfolk Boreas Limited
6.3.28.4 Environmental Statement - Appendix 28.4 Heritage Settings Assessment Workings (Onshore Project Substation and Associated Infrastructure)
Other
Size: 42 MB
Norfolk Boreas Limited
6.3.28.2 Environmental Statement - Appendix 28.2 Priority Archaeological Geophysical Survey Report (Part 4)
Other
Size: 43 MB
Norfolk Boreas Limited
6.3.28.2 Environmental Statement - Appendix 28.2 Priority Archaeological Geophysical Survey Report (Part 3)
Other
Size: 528 KB
Norfolk Boreas Limited
6.3.27.1 Environmental Statement - Appendix 27.1 Human Health Supporting Information
Other
Size: 649 KB
Norfolk Boreas Limited
6.3.26.4 Environmental Statement - Appendix 26.4 Cumulative ConstructionImpact Assessment Results
Other
Size: 361 KB
Norfolk Boreas Limited
6.3.26.2 Environmental Statement - Appendix 26.2 Air Quality Traffic Data
Other
Size: 293 KB
Norfolk Boreas Limited
6.3.25.4 Environmental Statement - Appendix 25.4 Norfolk Vanguard Noise and Vibration Consultation Responses
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.25.2 Environmental Statement - Appendix 25.2 Construction Phase Assessment
Other
Size: 216 KB
Norfolk Boreas Limited
6.3.24.38 Environmental Statement - Appendix 24.38 Link 41 Construction Programme and HGV Profiles
Other
Size: 217 KB
Norfolk Boreas Limited
6.3.24.36 Environmental Statement - Appendix 24.36 Link 13b Construction Programme and HGV Profiles
Other
Size: 247 KB
Norfolk Boreas Limited
6.3.24.34 Environmental Statement - Appendix 24.34 Scenario 2 - Summary of Construction Impacts
Other
Size: 350 KB
Norfolk Boreas Limited
6.3.24.20 Environmental Statement - Appendix 24.20 Scenario 2 - GHD Assumed Construction Materials and Associated HGV Delivery Derivation
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.24.18 Environmental Statement - Appendix 24.18 Scenario 1 - 2026 Development Flow Network Diagram
Other
Size: 278 KB
Norfolk Boreas Limited
6.3.24.2 Environmental Statement - Appendix 24.2 Link Sensitivity Rationale
Other
Size: 374 KB
Norfolk Boreas Limited
6.3.24.32 Environmental Statement - Appendix 24.32 PIC Cluster Summary
Other
Size: 173 KB
Norfolk Boreas Limited
6.3.24.30 Environmental Statement - Appendix 24.30 Scenario 2 - Employee Assignment Summary
Other
Size: 291 KB
Norfolk Boreas Limited
6.3.24.28 Environmental Statement - Appendix 24.28 Scenario 2 - Destination B (mobilisation areas and trenchless crossings) Employee Assignment
Other
Size: 202 KB
Norfolk Boreas Limited
6.3.24.26 Environmental Statement - Appendix 24.26 Scenario 2 - HGV Assignment
Other
Size: 212 KB
Norfolk Boreas Limited
6.3.24.40 Environmental Statement - Appendix 24.40 Link 34 Construction Programme and HGV Profiles
Other
Size: 247 KB
Norfolk Boreas Limited
6.3.24.24 Environmental Statement - Appendix 24.24 Scenario 2 - Lowestoft Port HGV Distribution
Other
Size: 294 KB
Norfolk Boreas Limited
6.3.24.22 Environmental Statement - Appendix 24.22 Scenario 2 - GHD Transport Assignment on Indicative Construction Programme
Other
Size: 232 KB
Norfolk Boreas Limited
6.3.24.6 Environmental Statement - Appendix 24.6 Scenario 1 - GHD Summary of Deliveries per Infrastructure Component
Other
Size: 343 KB
Norfolk Boreas Limited
6.3.24.4 Environmental Statement - Appendix 24.4 Scenario 1 - GHD Assumed Construction Materials and Associated HGV Delivery Derivation
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.24.31 Environmental Statement - Appendix 24.31 Scenario 2 - 2023 Development Flow Network Diagram
Other
Size: 184 KB
Norfolk Boreas Limited
6.3.24.29 Environmental Statement - Appendix 24.29 Scenario 2 - Destination C (Landfall) Employee Assignment
Other
Size: 182 KB
Norfolk Boreas Limited
6.3.24.27 Environmental Statement - Appendix 24.27 Scenario 2 - Destination A (onshore substations) Employee Assignment
Other
Size: 247 KB
Norfolk Boreas Limited
6.3.24.25 Environmental Statement - Appendix 24.25 Scenario 2 - Great Yarmouth Port HGV Distribution
Other
Size: 372 KB
Norfolk Boreas Limited
6.3.24.5 Environmental Statement - Appendix 24.5 Scenario 1 & 2 - Cable Pulling and Jointing Calculations and Access Routes
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.24.3 Environmental Statement - Appendix 24.3 2026 Forecast Background Traffic Flows
Other
Size: 216 KB
Norfolk Boreas Limited
6.3.24.39 Environmental Statement - Appendix 24.39 Link 68 Construction Programme and HGV Profiles
Other
Size: 250 KB
Norfolk Boreas Limited
6.3.24.35 Environmental Statement - Appendix 24.35 Scenario 1 - Summary of Construction Impacts
Other
Size: 214 KB
Norfolk Boreas Limited
6.3.24.41 Environmental Statement - Appendix 24.41 Link 36 Construction Programme and HGV Profiles
Other
Size: 214 KB
Norfolk Boreas Limited
6.3.24.37 Environmental Statement - Appendix 24.37 Link 32 Construction Programme and HGV Profiles
Other
Size: 246 KB
Norfolk Boreas Limited
6.3.24.23 Environmental Statement - Appendix 24.23 Scenario 2 - Kings Lynn Port HGV Distribution
Other
Size: 234 KB
Norfolk Boreas Limited
6.3.24.21 Environmental Statement - Appendix 24.21 Scenario 2 - GHD Summary of Deliveries per Infrastructure Component
Other
Size: 6 MB
Norfolk Boreas Limited
6.3.24.33 Environmental Statement - Appendix 24.33 A47 Substation Access Clarification Technical Note
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.24.19 Environmental Statement - Appendix 24.19 2023 Forecast Background Traffic Flows
Other
Size: 250 KB
Norfolk Boreas Limited
6.3.24.16 Environmental Statement - Appendix 24.16 Scenario 1 - Destination B (cable route sections) Employee Assignment
Other
Size: 212 KB
Norfolk Boreas Limited
6.3.24.14 Environmental Statement - Appendix 24.14 Scenario 1 - HGV Assignment
Other
Size: 179 KB
Norfolk Boreas Limited
6.3.24.12 Environmental Statement - Appendix 24.12 Scenario 1 - Lowestoft Port HGV Distribution
Other
Size: 200 KB
Norfolk Boreas Limited
6.3.24.10 Environmental Statement - Appendix 24.10 Employee Distribution Summary
Other
Size: 572 KB
Norfolk Boreas Limited
6.3.22.11 Environmental Statement - Appendix 22.11 Norfolk Vanguard Onshore Ecology Consultation Responses
Other
Size: 397 KB
Norfolk Boreas Limited
6.3.23.5 Environmental Statement - Appendix 23.5 Norfolk Vanguard Onshore Ornithology Consultation Responses
Other
Size: 21 MB
Norfolk Boreas Limited
6.3.22.3 Environmental Statement - Appendix 22.3 Water Vole Survey Reports
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.22.6 Environmental Statement - Appendix 22.6 Desmoulin's Whorl Snail Survey Reports
Other
Size: 15 MB
Norfolk Boreas Limited
6.3.22.4 Environmental Statement - Appendix 22.4 Bat Activity Survey Reports
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.23.3b Environmental Statement - Appendix 23.3b Whooper swan and Berwick’s swan maps for Broadland SPA
Other
Size: 10 MB
Norfolk Boreas Limited
6.3.23.2 Environmental Statement - Appendix 23.2 Wintering Bird Surveys: Final Report
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.22.7 Environmental Statement - Appendix 22.7 Botanical Survey Reports
Other
Size: 3 MB
Norfolk Boreas Limited
6.3.22.5 Environmental Statement - Appendix 22.5 Bat Emergence Re-entry Survey Reports
Other
Size: 188 KB
Norfolk Boreas Limited
6.3.24.15 Environmental Statement - Appendix 24.15 Scenario 1 - Destination A (onshore substations) Employee Assignment
Other
Size: 178 KB
Norfolk Boreas Limited
6.3.24.13 Environmental Statement - Appendix 24.13 Scenario 1 - Great Yarmouth Port HGV Distribution
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.22.9 Environmental Statement - Appendix 22.9 Norfolk Hawker Dragonfly Survey Report
Other
Size: 175 KB
Norfolk Boreas Limited
6.3.24.17 Environmental Statement - Appendix 24.17 Scenario 1 - Employee Assignment Summary
Other
Size: 442 KB
Norfolk Boreas Limited
6.3.23.3a Environmental Statement - Appendix 23.3a Pink-footed goose maps for Broadland SPA
Other
Size: 11 MB
Norfolk Boreas Limited
6.3.23.1 Environmental Statement - Appendix 23.1 Onshore Winter / Passage Bird Survey Scoping Report
Other
Size: 5 MB
Norfolk Boreas Limited
6.3.24.1 Environmental Statement - Appendix 24.1 NCC Route Hierarchy
Other
Size: 12 MB
Norfolk Boreas Limited
6.3.23.4 Environmental Statement - Appendix 23.4 Breeding Bird Survey Report
Other
Size: 27 MB
Norfolk Boreas Limited
6.3.22.2 Environmental Statement - Appendix 22.2 Great Crested Newt Survey Reports
Other
Size: 195 KB
Norfolk Boreas Limited
6.3.24.11 Environmental Statement - Appendix 24.11 Scenario 1 - Kings Lynn Port HGV Distribution
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.22.10 Environmental Statement - Appendix 22.10 Ecosystem Services Assessment
Other
Size: 3 MB
Norfolk Boreas Limited
6.3.22.8 Environmental Statement - Appendix 22.8 Reptile Survey Reports
Other
Size: 38 MB
Norfolk Boreas Limited
6.3.22.1 Environmental Statement - Appendix 22.1 Extended Phase 1 Habitat Survey Reports
Other
Size: 10 MB
Norfolk Boreas Limited
6.3.17.8 Environmental Statement - Appendix 17.8: Norfolk Boreas Offshore Wind Farm Stage 4 Paleoenvironmental Assessment
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.17.6 Environmental Statement - Appendix 17.6: Norfolk Boreas Offshore Wind Farm Stage 2 Geoarchaeological Review
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.17.4 Environmental Statement - Appendix 17.4: Norfolk Vanguard Offshore Wind Farm Marine Archaeological Technical Report
Other
Size: 308 KB
Norfolk Boreas Limited
6.3.19.1 Environmental Statement - Appendix 19.1 Norfolk Vanguard Ground Conditions and Contamination Consultation Responses
Other
Size: 345 KB
Norfolk Boreas Limited
6.3.20.4 Environmental Statement - Appendix 20.4 Watercourse Crossing Schedule
Other
Size: 13 MB
Norfolk Boreas Limited
6.3.20.2 Environmental Statement - Appendix 20.2 Water Framework Directive Compliance Assessment
Other
Size: 582 KB
Norfolk Boreas Limited
6.3.20.5 Environmental Statement - Appendix 20.5 Norfolk Vanguard Water Resources and Flood Risk Consultation Responses
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.20.3 Environmental Statement - Appendix 20.3 Geomorphological Walkover Survey
Other
Size: 1 MB
Norfolk Boreas Limited
6.3.19.3 Environmental Statement - Appendix 19.3 Waste Technical Assessment
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.17.3 Environmental Statement - Appendix 17.3: Norfolk Boreas Offshore Windfarm Archaeological Assessment of Geophysical Data-Addendum
Other
Size: 287 KB
Norfolk Boreas Limited
6.3.21.1 Environmental Statement - Appendix 21.1 Norfolk Vanguard Land Use and Agriculture Consultation Responses
Other
Size: 44 MB
Norfolk Boreas Limited
6.3.20.1 Environmental Statement - Appendix 20.1 Flood Risk Assessment
Other
Size: 17 MB
Norfolk Boreas Limited
6.3.19.2 Environmental Statement - Appendix 19.2 Land Quality Phase 1 Preliminary Risk Assessment
Other
Size: 4 MB
Norfolk Boreas Limited
6.3.17.9 Environmental Statement - Appendix 17.9: Offshore Archaeology Gazetteer
Other
Size: 5 MB
Norfolk Boreas Limited
6.3.17.7 Environmental Statement - Appendix 17.7: Norfolk Boreas Offshore Wind Farm Stage 3 Geoarchaeological Assessment
Other
Size: 3 MB
Norfolk Boreas Limited
6.3.17.5 Environmental Statement - Appendix 17.5: Norfolk Boreas Offshore Wind Farm Stage 1 Geoarchaeological Review
Other
Size: 579 KB
Norfolk Boreas Limited
6.3.15.4 Environmental Statement - Appendix 15.4 Regular Operator Consultation
Other
Size: 28 MB
Norfolk Boreas Limited
6.3.15.1 Environmental Statement - Appendix 15.1 Navigation Risk Assessment
Other
Size: 14 MB
Norfolk Boreas Limited
6.3.17.2 Environmental Statement - Appendix 17.2: Norfolk Boreas Offshore Windfarm Archaeological Assessment of Geophysical Data
Other
Size: 644 KB
Norfolk Boreas Limited
6.3.15.2 Environmental Statement - Appendix 15.2 MGN 543 Checklist
Other
Size: 470 KB
Norfolk Boreas Limited
6.3.14.2 Environmental Statement - Appendix 14.2 Commercial Fisheries Consultation Responses
Other
Size: 19 MB
Norfolk Boreas Limited
6.3.14.1 Environmental Statement - Appendix 14.1 Commercial Fisheries Technical Report
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.12.3 Environmental Statement - Appendix 12.3: Marine Mammal Cumulative Impact Assessment (CIA) screening
Other
Size: 5 MB
Norfolk Boreas Limited
6.3.12.2 Environmental Statement - Appendix 12.2: Marine Mammal Information and Survey Data
Other
Size: 302 KB
Norfolk Boreas Limited
6.3.10.3 Environmental Statement - Appendix 10.3 Comparison of MarLIN and Norfolk Boreas sensitivity definitions for benthic receptors
Other
Size: 24 MB
Norfolk Boreas Limited
6.3.10.1 Environmental Statement - Appendix 10.1 Benthic Characterisation Report
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.8.8 Environmental Statement - Figure 8.8 Location of seabed sediment samples within the Norfolk Boreas site and project interconnector cable search area
Other
Size: 674 KB
Norfolk Boreas Limited
6.3.15.5 Environmental Statement - Appendix 15.5 Hazard Log
Other
Size: 10 MB
Norfolk Boreas Limited
6.3.13.1 Environmental Statement - Appendix 13.1 Ornithology Technical Appendix
Other
Size: 478 KB
Norfolk Boreas Limited
6.3.11.2 Environmental Statement - Appendix 11.2 Fish and Shellfish Ecology Consultation Responses
Other
Size: 11 MB
Norfolk Boreas Limited
6.3.11.1 Environmental Statement - Appendix 11.1 Fish and Shellfish Ecology Technical Report
Other
Size: 611 KB
Norfolk Boreas Limited
6.3.12.1 Environmental Statement - Appendix 12.1 Marine Mammal Consultation responses
Other
Size: 493 KB
Norfolk Boreas Limited
6.3.17.1 Environmental Statement - Appendix 17.1: Offshore Archaeology and Cultural Heritage Consultation Responses
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.9 Environmental Statement - Figure 8.9 Location of seabed sediment samples along the offshore cable corridor
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.7 Environmental Statement - Figure 8.7 Regional wave observations
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.15.3 Environmental Statement - Appendix 15.3 Consequences of collision and allision
Other
Size: 462 KB
Norfolk Boreas Limited
6.3.12.5 Environmental Statement - Appendix 12.5: Additional Underwater Noise Assessments
Other
Size: 617 KB
Norfolk Boreas Limited
6.3.12.4 Environmental Statement - Appendix 12.4: Additional Assessment in relation to the Southern North Sea Special Area of Conservation (SNS SAC)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.9.1 Environmental Statement - Figure 9.1 Offshore Cable Corridor and landfall area against WFD water bodies and designated bathing waters
Other
Size: 446 KB
Norfolk Boreas Limited
6.3.12.6 Environmental Statement - Appendix 12.6: Additional Cumulative Impact Assessment (CIA) Scenarios
Other
Size: 2 MB
Norfolk Boreas Limited
6.3.10.2 Environmental Statement - Appendix 10.2 Benthic Ecology Data Analysis
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.9.2 Environmental Statement - Figure 9.2 Norfolk Boreas Contaminant Sample Analysis locations
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.8.6 Environmental Statement - Figure 8.6 Regional current roses
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.4 Environmental Statement - Figure 8.4 Bathymetry of the project interconnector search area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.2 Environmental Statement - Figure 8.2 Regional bathymetry
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.10 Environmental Statement - Figure 8.10 Regional sediment transport pathways in the vicinity of Norfolk Boreas (Kenyon and Cooper, 2005)
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.11 Environmental Statement - Figure 4.11 Onshore project substation footprint options
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.4.9 Environmental Statement - Figure 4.9 Substation search area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.4.7 Environmental Statement - Figure 4.7 Landfall location
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.4.5 Environmental Statement - Figure 4.5 Landfall search area
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.15 Environmental Statement - Figure 4.15 National Grid substation extension under Scenario 1
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.13 Environmental Statement - Figure 4.13 Onshore project substation search area under Scenario 2 as presented at PEIR
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.4.6 Environmental Statement - Figure 4.6 Landfall site options
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.4.4 Environmental Statement - Figure 4.4 Ranking of indicative landfall sites
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.2 Environmental Statement - Figure 5.2 Proposed offshore disposal sites
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.17 Environmental Statement - Figure 4.17 Project interconnector cable search area
Other
Size: 38 MB
Norfolk Boreas Limited
6.2.4.8 Environmental Statement - Figure 4.8 Onshore Infrastructure as presented at PEIR
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.6 Environmental Statement - Figure 5.6 Onshore project substation and extension to National Grid substation Scenario 2
Other
Size: 31 MB
Norfolk Boreas Limited
6.2.5.4 Environmental Statement - Figure 5.4 Onshore project area Scenario 1 and 2
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.5 Environmental Statement - Figure 8.5 Position of the amphidromic point and co-tidal lines relative to the position of Norfolk Boreas
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.8.3 Environmental Statement - Figure 8.3 Bathymetry of the Norfolk Boreas offshore cable corridor
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.4.2 Environmental Statement - Figure 4.2 Offshore constraints
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.1 Environmental Statement - Figure 8.1 Bathymetry of Norfolk Boreas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.5 Environmental Statement - Figure 5.5 Onshore project substation and extension to National Grid substation Scenario 1
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.16 Environmental Statement - Figure 4.16 National Grid substation extension under Scenario 2
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.14 Environmental Statement - Figure 4.14 Onshore project substation location under Scenario 2
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.12 Environmental Statement - Figure 8.12 Location of sand waves along the Norfolk Boreas offshore cable corridor
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.11 Environmental Statement - Figure 8.11 Marine physical processes receptors relevant to Norfolk Boreas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.16 Environmental Statement - Figure 8.16 Zones of potential influence on the wave regime for Norfolk Boreas, Norfolk Vanguard and East Anglia THREE
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.15 Environmental Statement - Figure 8.15 Zones of potential influence in the tidal regimes for Norfolk Boreas, Norfolk Vanguard and East Anglia THREE
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.3 Environmental Statement - Figure 4.3 Provisional offshore cable corridors to three landfall locations
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.4.1 Environmental Statement - Figure 4.1 The Former East Anglia Zone
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.3 Environmental Statement - Figure 5.3 Landfall
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.5.1 Environmental Statement - Figure 5.1 Offshore project areas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.17 Environmental Statement - Figure 8.17 Zones of potential influence of the combined wave and tide regimes for Norfolk Boreas, Norfolk Vanguard and East Anglia THREE
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.4.12 Environmental Statement - Figure 4.12 Onshore project substation location under Scenario 1
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.4.10 Environmental Statement - Figure 4.10 Refined substation search area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.14 Environmental Statement - Figure 8.14 Zones of potential influence on the wave regime for Norfolk Boreas site
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.8.13 Environmental Statement - Figure 8.13 Zones of potential influence in the tidal regime for the Norfolk Boreas site
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.30.4 Environmental Statement - Figure 30.4 Serviced accommodation locations
Other
Size: 38 MB
Norfolk Boreas Limited
6.2.30.3 Environmental Statement - Figure 30.3 Public Rights of Way, cycle routes and long distance trails
Other
Size: 769 KB
Norfolk Boreas Limited
6.2.29.9 Environmental Statement - Figure 29.9 Scenario 1 - Indicative Onshore Project Substation Mitigation Planting – Norfolk Boreas and Norfolk Vanguard
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.44 Environmental Statement - Figure 29.44 Scenario 2 - Viewpoint 10: Holme Hale
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.42 Environmental Statement - Figure 29.42 Scenario 2 - Viewpoint 8: Chapel Road, Necton
Other
Size: 11 MB
Norfolk Boreas Limited
6.2.29.40 Environmental Statement - Figure 29.40 Scenario 2 - Viewpoint 6: A47, Top Farm
Other
Size: 39 MB
Norfolk Boreas Limited
6.2.30.2 Environmental Statement - Figure 30.2 Tourism and recreation assets in the vicinity of onshore infrastructure
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.29.46 Environmental Statement - Figure 29.46 Scenario 2 - Viewpoint 12: Ivy Todd
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.29.7 Environmental Statement - Figure 29.7 Scenario 1 - Cumulative Developments
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.8 Environmental Statement - Figure 29.8 Scenario 1 - Cumulative Zone of Theoretical Visibility Norfolk Vanguard Onshore Project Substation and National Grid Substation Extension / Norfolk Boreas Onshore Project Substation and National Grid Substation Extension
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.6 Environmental Statement - Figure 29.6 Scenario 1 - Zone of Theoretical Visibility National Grid Substation Extension
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.5 Environmental Statement - Figure 29.5 Scenario 1 – Zone of Theoretical Visibility Onshore Project Substation
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.30.1 Environmental Statement - Figure 30.1 Coastal tourism and recreation assets
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.29.45 Environmental Statement - Figure 29.45 Scenario 2 - Viewpoint 11: Hale Road, East of Holme Hale Hall
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.29.4 Environmental Statement - Figure 29.4 Scenario 1 – Viewpoints Onshore Project Substation / National Grid Substation Extension
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.43 Environmental Statement - Figure 29.43 Scenario 2 - Viewpoint 9: St Andrews Lane, Necton
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.29.41 Environmental Statement - Figure 29.41 Scenario 2 - Viewpoint 7: Ivy Todd Road east
Other
Size: 11 MB
Norfolk Boreas Limited
6.2.29.39 Environmental Statement - Figure 29.39 Scenario 2 - Viewpoint 5: A47, Spicer’s Corner
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.29.35 Environmental Statement - Figure 29.35 Scenario 2 - Viewpoint 1: Ivy Todd Road west
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.38 Environmental Statement - Figure 29.38 Scenario 2 - Viewpoint 4: Necton Substation Access
Other
Size: 16 MB
Norfolk Boreas Limited
6.2.29.37 Environmental Statement - Figure 29.37 Scenario 2 - Viewpoint 3: Lodge Lane north
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.29.33 Environmental Statement - Figure 29.33 Scenario 1 - Viewpoint 11: Hale Road, East of Holme Hale Hall
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.32 Environmental Statement - Figure 29.32 Scenario 1 - Viewpoint 10: Holme Hale
Other
Size: 12 MB
Norfolk Boreas Limited
6.2.29.36 Environmental Statement - Figure 29.36 Scenario 2 - Viewpoint 2: Lodge Lane south
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.29.34 Environmental Statement - Figure 29.34 Scenario 1 - Viewpoint 12: Ivy Todd
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.31 Environmental Statement - Figure 29.31 Scenario 1 - Viewpoint 9: St Andrews Lane, Necton
Other
Size: 23 MB
Norfolk Boreas Limited
6.2.29.3 Environmental Statement - Figure 29.3 Scenario 1 - Visual Receptors
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.30 Environmental Statement - Figure 29.30 Scenario 1 - Viewpoint 8: Chapel Road, Necton
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.29.29 Environmental Statement - Figure 29.29 Scenario 1 - Viewpoint 7: Ivy Todd Road east
Other
Size: 9 MB
Norfolk Boreas Limited
6.2.29.25 Environmental Statement - Figure 29.25 Scenario 1 - Viewpoint 3: Lodge Lane north
Other
Size: 46 MB
Norfolk Boreas Limited
6.2.29.23 Environmental Statement - Figure 29.23 Scenario 1 - Viewpoint 1: Ivy Todd Road west
Other
Size: 532 KB
Norfolk Boreas Limited
6.2.29.21b Environmental Statement - Figure 29.21b Scenario 2 – Indicative A47 Mitigation Planting
Other
Size: 11 MB
Norfolk Boreas Limited
6.2.29.27 Environmental Statement - Figure 29.27 Scenario 1 - Viewpoint 5: A47, Spicer’s Corner
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.21a Environmental Statement - Figure 29.21a Scenario 2 – Indicative A47 Planting Removals
Other
Size: 12 MB
Norfolk Boreas Limited
6.2.29.24 Environmental Statement - Figure 29.24 Scenario 1 - Viewpoint 2: Lodge Lane south
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.29.22 Environmental Statement - Figure 29.22 Scenario 2 - Strategic Plan of Indicative Mitigation Planting
Other
Size: 12 MB
Norfolk Boreas Limited
6.2.29.28 Environmental Statement - Figure 29.28 Scenario 1 - Viewpoint 6: A47, Top Farm
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.26 Environmental Statement - Figure 29.26 Scenario 1 - Viewpoint 4: Necton Substation Access
Other
Size: 750 KB
Norfolk Boreas Limited
6.2.29.19 Environmental Statement - Figure 29.19 Scenario 2 - Indicative Onshore Project Substation Mitigation Planting
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.17 Environmental Statement - Figure 29.17 Scenario 2 - Zone of Theoretical Visibility National Grid Substation Extension
Other
Size: 24 MB
Norfolk Boreas Limited
6.2.29.2 Environmental Statement - Figure 29.2 Scenario 1 - Landscape Designations and Landscape Character Areas (Map 1 of 9)
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.29.15 Environmental Statement - Figure 29.15 - Scenario 2 - Viewpoints Onshore Project Substation / National Grid Substation Extension
Other
Size: 24 MB
Norfolk Boreas Limited
6.2.29.13 Environmental Statement - Figure 29.13 Scenario 2 - Landscape Designations and Landscape Character Areas (Map 1 of 9)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.29.18 Environmental Statement - Figure 29.18 Scenario 2 - Cumulative Developments
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.29.16 Environmental Statement - Figure 29.16 Scenario 2 - Zone of Theoretical Visibility Onshore Project Substation
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.20a Environmental Statement - Figure 29.20a Scenario 2 - Indicative National Grid Substation Extension Planting Removals
Other
Size: 788 KB
Norfolk Boreas Limited
6.2.29.20b Environmental Statement - Figure 29.20b Scenario 2 - Indicative National Grid substation extension Mitigation Planting
Other
Size: 23 MB
Norfolk Boreas Limited
6.2.29.14 Environmental Statement - Figure 29.14 Scenario 2 - Visual Receptors (Map 1 of 9)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.29.11 Environmental Statement - Figure 29.11 Scenario 1 – Strategic Plan of Indicative Mitigation Planting
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.12 Environmental Statement - Figure 29.12 Scenario 2 - Study Area
Other
Size: 45 MB
Norfolk Boreas Limited
6.2.28.3 Environmental Statement - Figure 28.3 Historic Landscape Characterisation
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.1 Environmental Statement - Figure 29.1 Scenario 1 - Study Area
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.9 Environmental Statement - Figure 24.9 Employee Distribution Destination B
Other
Size: 26 MB
Norfolk Boreas Limited
6.2.24.7 Environmental Statement - Figure 24.7 Scenario 1 - Onshore Infrastructure
Other
Size: 9 MB
Norfolk Boreas Limited
6.2.28.5 Environmental Statement - Figure 28.5 Settings Survey: Norfolk Boreas Onshore Project Substation (3km LVIA study area, including ZTV)
Other
Size: 730 KB
Norfolk Boreas Limited
6.2.29.10b Environmental Statement - Figure 29.10b Scenario 1 - Indicative National Grid Substation Extension Mitigation Planting – Norfolk Boreas and Norfolk Vanguard
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.29.10a Environmental Statement - Figure 29.10a Scenario 1 - Indicative National Grid Substation Extension Planting Removals
Other
Size: 27 MB
Norfolk Boreas Limited
6.2.24.5 Environmental Statement - Figure 24.5 Link Sensitivity
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.26.6 Environment Statement - Figure 26.6 Construction phase dust assessment distance bands –worst case scenario area
Other
Size: 39 MB
Norfolk Boreas Limited
6.2.28.4 Environmental Statement - Figure 28.4 Aerial photographic assessment (key sites) across the Norfolk Boreas onshore project area
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.25.1 Environmental Statement - Figure 25.1 Noise and vibration study area
Other
Size: 49 MB
Norfolk Boreas Limited
6.2.28.7 Environment Statement - Figure 28.7 Archaeological Interpretation of Geophysical Survey Data across the Norfolk Boreas onshore project area
Other
Size: 43 MB
Norfolk Boreas Limited
6.2.28.2 Environmental Statement - Figure 28.2 Non-designated heritage assets within 500m of the Norfolk Boreas onshore project area
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.8 Environmental Statement - Figure 24.8 Employee Distribution Destination A
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.6 Environmental Statement - Figure 24.6 Collision Cluster Location Plan
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.26.1 Environmental Statement - Figure 26.1 Road links considered in the air quality assessment under Scenario 2
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.26.4 Environmental Statement - Figure 26.4 Sensitive human receptor locations considered in the air quality assessment under Scenario 1
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.4 Environmental Statement - Figure 24.4 Traffic Surveys
Other
Size: 26 MB
Norfolk Boreas Limited
6.2.26.5 Environmental Statement - Figure 26.5 Transects in designated ecological sites
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.26.3 Environmental Statement - Figure 26.3 Road links considered in the air quality assessment under Scenario 1
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.28.6 Environmental Statement - Figure 28.6 Geophysical (Magnetometer) Survey Greyscales across the Norfolk Boreas onshore project area
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.26.2 Environmental Statement - Figure 26.2 Sensitive human receptor locations considered in the air quality assessment under Scenario 2
Other
Size: 38 MB
Norfolk Boreas Limited
6.2.25.2 Environmental Statement - Figure 25.2 Noise Receptor Locations
Other
Size: 41 MB
Norfolk Boreas Limited
6.2.28.1 Environmental Statement - Figure 28.1 Designated heritage assets within 1km of Norfolk Boreas onshore project area
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.16 Environmental Statement - Figure 24.16 Highway links jointly used by Norfolk Boreas (Scenario 2) and Hornsea Project Three
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.14 Environmental Statement - Figure 24.14 Scenario 2 - HGV Construction Traffic Flows
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.24.15 Environmental Statement - Figure 24.15 Location of Norfolk Boreas and Hornsea Project Three
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.1 Environmental Statement - Figure 24.1 Sensitive Junctions Plan
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.23.5 Environmental Statement - Figure 23.5 Wintering bird survey results: North Norfolk Coast between Eccles-on-Sea and Paston
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.23.4 Environmental Statement - Figure 23.4 Wintering bird survey results: Hundred Stream
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.17 Environmental Statement - Figure 24.17 Norfolk Boreas (Scenario 2) and Hornsea Project Three Collision Cluster Location Plan
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.10 Environmental Statement - Figure 24.10 Employee Distribution Destination C
Other
Size: 26 MB
Norfolk Boreas Limited
6.2.24.12 Environmental Statement - Figure 24.12 Scenario 2 - Onshore Infrastructure
Other
Size: 27 MB
Norfolk Boreas Limited
6.2.24.11 Environmental Statement - Figure 24.11 Scenario 1 - HGV Construction Traffic Flows
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.13 Environmental Statement - Figure 24.13 Scenario 2 - Primary Route Classification Plan
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.24.3 Environmental Statement - Figure 24.3 Scenario 2 Access Strategy Core Highway Links
Other
Size: 27 MB
Norfolk Boreas Limited
6.2.24.2 Environmental Statement - Figure 24.2 Scenario 1 Access Strategy Core Highway Links
Other
Size: 11 MB
Norfolk Boreas Limited
6.2.23.6 Environmental Statement - Figure 23.6 Breeding Bird Survey Locations
Other
Size: 21 MB
Norfolk Boreas Limited
6.2.22.9 Environmental Statement - Figure 22.9 Bat emergence/re-entry surveys (Map 1 of 15)
Other
Size: 12 MB
Norfolk Boreas Limited
6.2.22.7 Environmental Statement - Figure 22.7 Water vole and Otter survey results
Other
Size: 56 MB
Norfolk Boreas Limited
6.2.22.8 Environmental Statement - Figure 22.8 Bat activity survey locations
Other
Size: 41 MB
Norfolk Boreas Limited
6.2.22.6 Environmental Statement - Figure 22.6 Great crested newt presence/absence survey results
Other
Size: 42 MB
Norfolk Boreas Limited
6.2.23.1 Environmental Statement - Figure 23.1 Onshore ornithology study areas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.23.3 Environmental Statement - Figure 23.3 Wintering bird survey results: Dereham Rush Meadow SSSI
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.23.2 Environmental Statement - Figure 23.2 Wintering bird survey results: Agricultural fields in North Walsham District
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.22.11 Environmental Statement - Figure 22.11 Botanical survey results
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.22.12 Environmental Statement - Figure 22.12 Invertebrate results
Other
Size: 22 MB
Norfolk Boreas Limited
6.2.22.10 Environmental Statement - Figure 22.10 Reptile survey results
Other
Size: 38 MB
Norfolk Boreas Limited
6.2.21.6 Environmental Statement - Figure 21.6 Utilities
Other
Size: 42 MB
Norfolk Boreas Limited
6.2.22.1 Environment Statement - Figure 22.1 Norfolk Boreas study areas
Other
Size: 41 MB
Norfolk Boreas Limited
6.2.21.5 Environmental Statement - Figure 21.5 Environmental Stewardship Scheme agreements
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.22.5 Environmental Statement - Figure 22.5 Extended Phase 1 Habitat survey(including Norfolk living map)
Other
Size: 37 MB
Norfolk Boreas Limited
6.2.22.4 Environmental Statement - Figure 22.4 Habitats of Principal Importance
Other
Size: 40 MB
Norfolk Boreas Limited
6.2.22.3 Environmental Statement - Figure 22.3 Non-statutory designated sites
Other
Size: 40 MB
Norfolk Boreas Limited
6.2.22.2 Environmental Statement - Figure 22.2 Statutory designated sites
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.20.2 Environmental Statement - Figure 20.2 Main surface water catchments
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.20.1 Environmental Statement - Figure 20.1 Water resources and flood risk: Study area
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.21.1 Environmental Statement - Figure 21.1 Study Area
Other
Size: 40 MB
Norfolk Boreas Limited
6.2.20.5 Environmental Statement - Figure 20.5 Environment Agency Flood Zones map
Other
Size: 40 MB
Norfolk Boreas Limited
6.2.21.4 Environmental Statement - Figure 21.4 Agricultural Land Classifications
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.20.3 Environmental Statement - Figure 20.3 Surface water sub-catchments
Other
Size: 38 MB
Norfolk Boreas Limited
6.2.21.2 Environmental Statement - Figure 21.2 Land cover mapping
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.20.6 Environmental Statement - Figure 20.6 Groundwater bodies
Other
Size: 39 MB
Norfolk Boreas Limited
6.2.20.4 Environmental Statement - Figure 20.4 Main Rivers, IDB Drains and other ordinary watercourses
Other
Size: 40 MB
Norfolk Boreas Limited
6.2.21.3 Environmental Statement - Figure 21.3 Policies and designations
Other
Size: 40 MB
Norfolk Boreas Limited
6.2.19.4 Environmental Statement - Figure 19.4 Bedrock and superficial aquifers
Other
Size: 40 MB
Norfolk Boreas Limited
6.2.19.2 Environmental Statement - Figure 19.2 Superficial geology and Ground investigation locations
Other
Size: 40 MB
Norfolk Boreas Limited
6.2.19.5 Environmental Statement - Figure 19.5 Source Protection Zones
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.18.3 Environmental Statement - Figure 18.3 Aggregate dredging and marine disposal activity
Other
Size: 38 MB
Norfolk Boreas Limited
6.2.19.1 Environmental Statement - Figure 19.1 Bedrock geology
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.18.2 Environmental Statement - Figure 18.2 Other offshore infrastructure
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.19.3 Environmental Statement - Figure 19.3 Designated geological sites
Other
Size: 39 MB
Norfolk Boreas Limited
6.2.19.6 Environmental Statement - Figure 19.6 Minerals Safeguarding Areas
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.17.2 Environmental Statement - Figure 17.2 Palaeogeographic features of archaeological potential in the Norfolk Boreas site
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.17.3 Environmental Statement - Figure 17.3 Palaeogeographic features of archaeological potential in the Offshore cable corridor and Project interconnector search area (Maps 1 to 4)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.18.1 Environmental Statement - Figure 18.1 Other offshore wind farm developments
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.17.5 Environmental Statement - Figure 17.5 Seabed features of archaeological potential in the Offshore cable corridor and Project interconnector search area (Maps 1 to 4)
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.17.6 Environmental Statement - Figure 17.6 Intertidal heritage assets
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.17.4 Environmental Statement - Figure 17.4 Seabed features of archaeological potential in the Norfolk Boreas site
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.15.9 Environmental Statement - Figure 15.9 Fishing Vessels
Other
Size: 906 KB
Norfolk Boreas Limited
6.2.15.7 Environmental Statement - Figure 15.7 Recreational Vessels
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.9 Environmental Statement - Figure 14.9 Dutch VMS Value (€) Seine Nets¹ Average 2013-2017
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.15.3 Environmental Statement - Figure 15.3 Marine Traffic Survey Data (Summer)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.15.1 Environmental Statement - Figure 15.1 Study Areas
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.15.4 Environmental Statement - Figure 15.4 Marine Traffic Survey Data (Winter)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.15.2 Environmental Statement - Figure 15.2 Navigational Features
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.15.5 Environmental Statement - Figure 15.5 Main Routes
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.15.8 Environmental Statement - Figure 15.8 RYA Coastal Atlas
Other
Size: 8 MB
Norfolk Boreas Limited
6.2.15.6 Environmental Statement - Figure 15.6 Offshore Cable Corridor Marine Traffic Data
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.16.2 Environmental Statement - Figure 16.2 HMR and Oil and Gas Platforms in in the vicinity to Norfolk Boreas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.17.1 Environmental Statement - Figure 17.1 Study Area
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.16.1 Environmental Statement - Figure 16.1 Division of Airspace
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.7 Environmental Statement - Figure 14.7 Dutch VMS Effort (Days) Beam Trawls¹ Average 2013-2017
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.14.5 Environmental Statement - Figure 14.5 Dutch Landings (€) by Species¹ Average 2012-2016
Other
Size: 9 MB
Norfolk Boreas Limited
6.2.14.50 Environmental Statement - Figure 14.50 Locations of Other Projects/Activities included in the Cumulative Assessment with French Fishing Effort (days) by Over 18m Vessels Using Bottom Otter Trawls in 20145
Other
Size: 9 MB
Norfolk Boreas Limited
6.2.14.41 Environmental Statement - Figure 14.41 Locations of Other Projects/Activities included in the Cumulative Assessment with Annual Average Dutch VMS Effort (Days) Beam Trawls (2013-2017)
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.14.8 Environmental Statement - Figure 14.8 Interim Spatial Separation Agreement between Dutch Pulse Trawlers and English East Coast Inshore Fishermen (NNFO, 2019)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.43 Environmental Statement - Figure 14.43 Locations of Other Projects/Activities included in the Cumulative Assessment with Annual Average Dutch VMS Effort (Days) Seine Nets (2013-2017)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.42 Environmental Statement - Figure 14.42 Locations of O the r Projects /Activities included in the Cumulative Assessment with Annual Average Dutch VMS Value (€) Seine Nets (2013-2017)
Other
Size: 13 MB
Norfolk Boreas Limited
6.2.14.46 Environmental Statement - Figure 14.46 Locations of Other Projects/Activities included in the Cumulative Assessment with Annual Average UK VMS Value (£) Beam Trawl (2012-2016)
Other
Size: 10 MB
Norfolk Boreas Limited
6.2.14.44 Environmental Statement - Figure 14.44 Locations of O the r Projects /Activities included in the Cumulative Assessment with Annual Ave rage Belgian VMS Value (€) Be am Trawl (2010-2014)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.47 Environmental Statement - Figure 14.47 Locations of Other Projects/Activities included in the Cumulative Assessment with Annual Average UK VMS Effort (Hours) Beam Trawl (2012-2016)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.45 Environmental Statement - Figure 14.45 Locations of Other Projects/Activities included in the Cumulative Assessment with Annual Average Belgian VMS Effort (Days) Beam Trawl (2010-2014)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.48 Environmental Statement - Figure 14.48 Locations of Other Projects/Activities included in the Cumulative Assessment with Bottom and Pelagic Trawls 2008 Fishing time (hours) per 10' by 10' Rectangles
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.6 Environmental Statement - Figure 14.6 Dutch VMS Value (€) Beam Trawls¹ Average 2013-2017
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.51 Environmental Statement - Figure 14.51 Locations of Other Projects/Activities included in the Cumulative Assessment with French Fishing Effort (days) Over 18m Using Pelagic Trawls in 20145
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.49 Environmental Statement - Figure 14.49 Locations of Other Projects/Activities included in the Cumulative Assessment with Bottom Otter Trawls 2008 Fishing time (hours) per 10' by 10' Rectangles
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.40 Environmental Statement - Figure 14.40 Locations of O the r Projects /Activities included in the Cumulative Assessment with Dutch VMS Value (€) Be am Trawls
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.14.37 Environmental Statement - Figure 14.37 Danish VMS Effort (Days) Midwater Trawl¹ Average 2011-2015
Other
Size: 8 MB
Norfolk Boreas Limited
6.2.14.39 Environmental Statement - Figure 14.39 Locations of Other Projects/Activities included in the Cumulative Assessment
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.14.38 Environmental Statement - Figure 14.38 German Fishing Density (No. Vessel)¹ Average 2011-2015
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.14.4 Environmental Statement - Figure 14.4 Dutch Landings (€) by Method¹ Average 2012-2016
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.14.36 Environmental Statement - Figure 14.36 Danish VMS Effort (Days) Sandeel Trawl¹ Average 2011-2015
Other
Size: 7 MB
Norfolk Boreas Limited
6.2.14.34 Environmental Statement - Figure 14.34 French Fishing Effort (days) by Over 18m Vessels Using Bottom Otter Trawls in 2014
Other
Size: 857 KB
Norfolk Boreas Limited
6.2.14.32 Environmental Statement - Figure 14.32 French VMS (hours fished) by Bottom and Pelagic Trawls, 2008
Other
Size: 875 KB
Norfolk Boreas Limited
6.2.14.35 Environmental Statement - Figure 14.35 French Fishing Effort (days) Over18m Using Pelagic Trawls in 2014
Other
Size: 855 KB
Norfolk Boreas Limited
6.2.14.33 Environmental Statement - Figure 14.33 French VMS Effort (hours fished) by Bottom Otter Trawls, 2008
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.14.31 Environmental Statement - Figure 14.31 UK VMS Effort (Hours) Otter Twin Trawl¹ Average 2012-2016
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.14.30 Environmental Statement - Figure 14.30 UK VMS Value (£) Otter Twin Trawl¹ Average 2012-2016
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.14.28 Environmental Statement - Figure 14.28 UK VMS Value (£) Otter Bottom Trawl¹ Average 2012-2016
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.14.26 Environmental Statement - Figure 14.26 UK VMS Value (£) Beam Trawl¹ Average 2012-2016
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.14.24 Environmental Statement - Figure 14.24 Main Longlining Fishing Grounds From Consultation Brown & May Marine 2017
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.14.29 Environmental Statement - Figure 14.29 UK VMS Effort (Hours) Otter Bottom Trawl¹ Average 2012-2016
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.14.27 Environmental Statement - Figure 14.27 UK VMS Effort (Hours) Beam Trawl¹ Average 2012-2016
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.14.3 Environmental Statement - Figure 14.3 Surveillance Sightings by Method¹ Average 2011-2015
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.14.22 Environmental Statement - Figure 14.22 Potting Grounds based on Consultations 2017
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.14.25 Environmental Statement - Figure 14.25 Fishing Grounds Identified by Caister Fishermen during Consultation
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.14.23 Environmental Statement - Figure 14.23 ESJFC District - Crustacean Fisheries Grounds 2010
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.14.20 Environmental Statement - Figure 14.20 UK Landings by Method¹ Average 2012-2016
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.18 Environmental Statement - Figure 14.18 Belgian VMS Value (€) Seine Nets¹ Average 2010-2014
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.16 Environmental Statement - Figure 14.16 Belgian VMS Value (€) Demersal Trawl¹ Average 2010-2014
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.14.21 Environmental Statement - Figure 14.21 UK Landings by Species¹ Average 2012-2016
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.19 Environmental Statement - Figure 14.19 Belgian VMS Effort (days) Seine Nets¹ Average 2010-2014
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.17 Environmental Statement - Figure 14.17 Belgian VMS Effort (Days) Demersal Trawl¹ Average 2010-2014
Other
Size: 8 MB
Norfolk Boreas Limited
6.2.14.2 Environmental Statement - Figure 14.2 Surveillance Sightings by Nationality¹ Average 2011-2015
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.15 Environmental Statement - Figure 14.15 Belgian VMS Effort (Days) Beam Trawl¹ Average 2010-2014
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.14.11 Environmental Statement - Figure 14.11 Belgian Landings (€) by Method ¹ Average 2010-2014
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.14 Environmental Statement - Figure 14.14 Belgian VMS Value (€) Beam Trawl¹ Average 2010-2014
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.12.4 Environmental Statement - Grey and harbour seal haul-out sites around Norfolk Boreas offshore project area
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.14.10 Environmental Statement - Figure 14.10 Dutch VMS Effort (Days) Seine Nets¹ Average 2013-2017
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.13.2 Environment Statement - Figure 13.2 Special Protection Areas Assessed in Relation to Norfolk Boreas
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.13.1 Environmental Statement - Figure 13.1 Norfolk Boreas Offshore Wind Farm and 4km Buffer
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.14.12 Environmental Statement - Figure 14.12 Belgian Landings (€) by Species¹ Average 2010-2014
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.14.13 Environmental Statement - Figure 14.13 Historic Fishing Rights
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.13.4 Environmental Statement - Figure 13.4 Sites of Special Scientific Interest Assessed in Relation to Norfolk Boreas
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.13.3 Environmental Statement - Figure 13.3 Ramsar Sites Assessed in Relation to Norfolk Boreas
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.14.1 Environmental Statement - Figure 14.1 Study area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.12.8 Environmental Statement - Figure 12.8 Concurrent piling based on worst-case scenario
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.12.7 Environmental Statement - Figure 12.7 Grey and harbour seal PTS, TTS and disturbance ranges based on worst case scenarios
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.11.30 Environmental Statement - Figure 11.30 Tope and Thornback Ray Spawning Grounds and nursery Grounds in Relation to Monopile Noise Impact Contours (5000KJ)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.12.6 Environmental Statement - Figure 12.6 Harbour porpoise TTS and disturbance range based on worst case scenarios
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.12.5 Environmental Statement Figure 12.5 Harbour porpoise PTS ranges based on worst case scenario
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.9 Environment Statement - Figure 11.9 Sprat Spawning and Nursery Grounds
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.12.2 Environmental Statement - Figure 12.2 Mean grey seal at-sea around Norfolk Boreas offshore project area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.12.3 Environmental Statement - Figure 12.3 Mean harbour seal at-sea usage around Norfolk Boreas offshore project area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.12.1 Environmental Statement - Figure 12.1 Southern North Sea SAC for harbour porpoise
Other
Size: 886 KB
Norfolk Boreas Limited
6.2.11.20 Environmental Statement - Figure 11.20 IHLS Herring Small Larvae Abundance (2015-2017) and Herring Spawning Intensity
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.5 Environmental Statement - Figure 11.5 Whiting spawning and nursery grounds (Coull et al., 1998 and Ellis et al., 2010)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.3 Environmental Statement - Figure 11.3 Plaice Spawning and Nursery Grounds
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.11.28 Environmental Statement - Figure 11.28 Sprat Spawning Grounds and Nursery Grounds in Relation to Monopile Noise Impact Contours (5000KJ)
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.11.24 Environmental Statement - Figure 11.24 Mackerel Spawning Grounds and nursery Grounds in Relation to Monopile Noise Impact Contours (5000KJ)
Other
Size: 1,009 KB
Norfolk Boreas Limited
6.2.11.22 Environmental Statement - Figure 11.22 Plaice Spawning Grounds and Nursery Grounds in Relation to Monopile Noise Impact Contours (5000KJ)
Other
Size: 951 KB
Norfolk Boreas Limited
6.2.11.21 Environmental Statement - Figure 11.21 Dover Sole Spawning Grounds and Nursery Grounds in Relation to Monopile Noise Impact Contours (5000KJ)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.7 Environmental Statement - Figure 11.7 Herring spawning and nursery grounds (Coull et al., 1998; Ellis et al., 2010)
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.11.26 Environmental Statement - Figure 11.26 Cod Spawning Grounds and Nursery Grounds in Relation to Monopile Noise impact Contours (5000KJ)
Other
Size: 6 MB
Norfolk Boreas Limited
6.2.11.25 Environmental Statement - Figure 11.25 Sandeel Spawning Grounds and Nursery Grounds in Relation to Monopile Noise Impact Contours (5000KJ)
Other
Size: 962 KB
Norfolk Boreas Limited
6.2.11.23 Environmental Statement - Figure 11.23 Lemon Sole Spawning Grounds and Nursery Grounds in Relation to Monopile Noise Impact Contours (5000KJ)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.8 Environmental Statement - Figure 11.8 Mackerel spawning and nursery grounds (Coull et al., 1998 and Ellis et al., 2010)
Other
Size: 986 KB
Norfolk Boreas Limited
6.2.11.18 Environmental Statement - Figure 11.18 IHLS Herring Small Larvae Abundance (2007-2010) and Herring Spawning Intensity
Other
Size: 847 KB
Norfolk Boreas Limited
6.2.11.17 Environmental Statement - Figure 11.17 ICES Sandeel Assessment Areas in the North Sea (1-2) and the Sandeel Habitat Areas and locations of Fishing Grounds Described by Jensen et al (2011)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.16 Environmental Statement - Figure 11.16 Danish VMS Effort (days) for Sandeel Average 2011 - 2015
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.2 Environmental Statement - Figure 11.2 Dover Sole Spawning and Nursery Grounds
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.11.29 Environmental Statement - Figure 11.29 Herring Spawning Grounds and Nursery Grounds in Relation to Monopile Noise Impact Contours (5000KJ)
Other
Size: 3 MB
Norfolk Boreas Limited
6.2.11.27 Environmental Statement - Figure 11.27 Whiting Spawning Grounds and Nursery Grounds in Relation to Monopile Noise Impact Contours
Other
Size: 988 KB
Norfolk Boreas Limited
6.2.11.19 Environmental Statement - Figure 11.19 IHLS Herring Larvae Abundance (2011-2014) and Herring Spawning Intensity
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.6 Environmental Statement - Figure 11.6 Lemon sole spawning and nursery grounds (Coull et al., 1998)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.4 Environmental Statement - Figure 11.4 Cod spawning and nursery grounds (Coull et al., 1998 and Ellis et al., 2010)
Other
Size: 936 KB
Norfolk Boreas Limited
6.1.9 Environmental Statement - Chapter 9 Marine Water and Sediment Quality
Other
Size: 636 KB
Norfolk Boreas Limited
6.1.7 Environmental Statement - Chapter 7 Technical Consultation
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.34 Environmental Statement - Chapter 34 Summary
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.29 Environmental Statement - Chapter 29 Landscape and Visual Impact Assessment
Other
Size: 3 MB
Norfolk Boreas Limited
6.1.5 Environmental Statement - Chapter 5 Project Description
Other
Size: 612 KB
Norfolk Boreas Limited
6.1.3 Environmental Statement - Chapter 3 Policy and Legislative Context
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.13 Environmental Statement - Figure 10.13 Designated Sites
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.28 Environmental Statement - Chapter 28 Onshore Archaeology and Cultural Heritage
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.27 Environmental Statement - Chapter 27 Human Health
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.4 Environmental Statement - Chapter 4 Site Selection and Assessment of Alternatives
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.11.15 Environmental Statement - Figure 11.15 Smooth Sandeel CPUE 2008-2017 (10 Year Average)
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.11.14 Environmental Statement - Figure 11.14 Lesser Sandeel CPUE 2008-2017 (10 Year Average)
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.11.12 Environmental Statement - Figure 11.12 Greater Sandeel CPUE 2008-2017 (10 Year Average)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.11 Environmental Statement - Figure 10.11 Sabellaria spinulosa abundance
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.9 Environmental Statement - Figure 10.9 Epifaunal groups
Other
Size: 656 KB
Norfolk Boreas Limited
6.1.32 Environmental Statement - Chapter 32 Offshore Cumulative and Transboundary Impacts
Other
Size: 3 MB
Norfolk Boreas Limited
6.1.8 Environmental Statement - Chapter 8 Marine Geology, Oceanography and Physical Processes
Other
Size: 731 KB
Norfolk Boreas Limited
6.1.6 Environmental Statement - Chapter 6 Environmental Impact Assessment Methodology
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.11.10 Environmental Statement - Figure 11.10 Sandeel spawning and nursery grounds (Coull et al., 1998 and Ellis et al., 2010)
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.11.13 Environmental Statement - Figure 11.13 Small Sandeel CPUE 2008-2017 (10 Year Average)
Other
Size: 1 MB
Norfolk Boreas Limited
6.2.11.11 Environmental Statement - Figure 11.11 Thornback ray and tope nursery grounds (Ellis et al., 2010)
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.10 Environmental Statement - Figure 10.10 Biotape map
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.8 Environmental Statement - Figure 10.8 Epifaunal diversity
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.6 Environmental Statement - Figure 10.6 Infaunal groups
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.4 Environmental Statement - Figure 10.4 Infaunal diversity
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.31 Environmental Statement - Chapter 31 Socio-economics
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.30 Environmental Statement - Chapter 30 Tourism and Recreation
Other
Size: 4 MB
Norfolk Boreas Limited
6.2.11.1 Environmental Statement - Figure 11.1 Study area
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.12 Environmental Statement - Figure 10.12 Sabellaria spinulosa reef
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.3 Environmental Statement - Figure 10.3 Infaunal abundance
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.1 Environmental Statement - Figure 10.1 Benthic Survey Locations
Other
Size: 5 MB
Norfolk Boreas Limited
6.2.10.2 Environmental Statement - Figure 10.2 Sediment Distribution
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.7 Environmental Statement - Figure 10.7 Epifaunal abundance
Other
Size: 2 MB
Norfolk Boreas Limited
6.2.10.5 Environmental Statement - Figure 10.5 Infaunal Biomass
Other
Size: 754 KB
Norfolk Boreas Limited
6.1.33 Environmental Statement - Chapter 33 Onshore Cumulative Impacts
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.21 Environmental Statement - Chapter 21 Land Use and Agriculture
Other
Size: 826 KB
Norfolk Boreas Limited
6.1.19 Environmental Statement - Chapter 19 Ground Conditions and Contamination
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.26 Environmental Statement - Chapter 26 Air Quality
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.17 Environmental Statement - Chapter 17 Offshore Archaeology and Cultural Heritage
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.15 Environmental Statement - Chapter 15 Shipping and Navigation
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.23 Environmental Statement - Chapter 23 Onshore Ornithology
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.12 Environmental Statement - Chapter 12 Marine Mammals
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.10 Environmental Statement - Chapter 10 Benthic and Intertidal Ecology
Other
Size: 3 MB
Norfolk Boreas Limited
6.1.13 Environmental Statement - Chapter 13 Offshore Ornithology
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.11 Environmental Statement - Chapter 11 Fish and Shellfish Ecology (Superseded)
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.22 Environmental Statement - Chapter 22 Onshore Ecology
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.25 Environmental Statement - Chapter 25 Noise and Vibration
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.24 Environmental Statement - Chapter 24 Traffic and Transport
Other
Size: 694 KB
Norfolk Boreas Limited
6.1.16 Environmental statement - Chapter 16 Aviation and Radar
Other
Size: 1 MB
Norfolk Boreas Limited
6.1.14 Environmental Statement - Chapter 14 Commercial Fisheries
Other
Size: 629 KB
Norfolk Boreas Limited
6.1.1 Environmental Statement - Chapter 1 - Introduction
Other
Size: 2 MB
Norfolk Boreas Limited
6.1.20 Environmental Statement - Chapter 20 Water Resources and Flood Risk
Other
Size: 618 KB
Norfolk Boreas Limited
6.1.18 Environmental Statement - Chapter 18 Infrastructure and Other Users
Other
Size: 453 KB
Norfolk Boreas Limited
6.1.2 Environmental Statement - Chapter 2 Need for the Project
Other
Size: 12 MB
Norfolk Boreas Limited
5.1.29.1 Consultation Report Appendix 29.01 - Supply chain information pack
Other
Size: 3 MB
Norfolk Boreas Limited
5.1.28.4 Consultation Report Appendix 28.04 - February 2019 newsletter
Other
Size: 8 MB
Norfolk Boreas Limited
5.1.29.3 Consultation Report Appendix 29.03 - 5th December 2018 onshore works supply chain workshop report
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.29.2 Consultation Report Appendix 29.02 - 20th September 2018 skills and supply chain stakeholder workshop report
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.31.1 Consultation Report Appendix 31.01 - 4th October 2018 letter to the Planning Inspectorate
Other
Size: 767 KB
Norfolk Boreas Limited
5.1.28.3 Consultation Report Appendix 28.03 - Hearing Your Views IV covering email
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.28.2 Consultation Report Appendix 28.02 - Landowner Information Pack (Version 2 - April 2018)
Other
Size: 703 KB
Norfolk Boreas Limited
5.1.27.10 Consultation Report Appendix 27.10 - Offshore Order Limits change report consultation responses
Other
Size: 251 KB
Norfolk Boreas Limited
5.1.28.1 Consultation Report Appendix 28.01 - Norfolk Boreas Expert Topic Group meetings - minutes post s-42 and Agreement Logs (confidential holding page)
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.27.9 Consultation Report Appendix 27.09 - Proof of postage to consultees
Other
Size: 2 MB
Norfolk Boreas Limited
5.1.25.1 Consultation Report Appendix 25.01 - Section 47 responses
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.24.1 Consultation Report Appendix 24.01 - Section 42 responses
Other
Size: 90 KB
Norfolk Boreas Limited
5.1.27.3 Consultation Report Appendix 27.03 - MMO project design update meeting - minutes (confidential holding page)
Other
Size: 1,004 KB
Norfolk Boreas Limited
5.1.27.6 Consultation Report Appendix 27.06 - MMO's response to project design change early consultation
Other
Size: 2 MB
Norfolk Boreas Limited
5.1.23.1 Consultation Report Appendix 23.01 - Section 48 notice
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.22.17 Consultation Report Appendix 22.17 - Example LLO email correspondence to hard to reach groups
Other
Size: 2 MB
Norfolk Boreas Limited
5.1.27.1 Consultation Report Appendix 27.01 - Project update design briefing note V1
Other
Size: 813 KB
Norfolk Boreas Limited
5.1.27.4 Consultation Report Appendix 27.04 - Natural England's response to project design change early consultation
Other
Size: 80 KB
Norfolk Boreas Limited
5.1.27.2 Consultation Report Appendix 27.02 - Natural England project design update meeting - minutes
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.22.11 Consultation Report Appendix 22.11 - October 2018 press release coverage
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.22.9 Consultation Report Appendix 22.09 - October 2018 e-newsletter
Other
Size: 2 MB
Norfolk Boreas Limited
5.1.22.8 Consultation Report Appendix 22.08 - October 2018 newsletter
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.22.15 Consultation Report Appendix 22.15 - Statutory Consultation feedback form
Other
Size: 44 MB
Norfolk Boreas Limited
5.1.22.13 Consultation Report Appendix 22.13 - Consultation Summary Document
Other
Size: 788 KB
Norfolk Boreas Limited
5.1.22.12 Consultation Report Appendix 22.12 - Posters advertising consultation
Other
Size: 730 KB
Norfolk Boreas Limited
5.1.22.10 Consultation Report Appendix 22.10 - Example email to hard to reach groups with e-newsletter
Other
Size: 7 MB
Norfolk Boreas Limited
5.1.22.16 Consultation Report Appendix 22.16 - Slide pack examples
Other
Size: 16 MB
Norfolk Boreas Limited
5.1.22.14 Consultation Report Appendix 22.14 - Formal consultation exhibition boards
Other
Size: 814 KB
Norfolk Boreas Limited
5.1.27.8 Consultation Report Appendix 27.08 - Letter to targeted consultees for Offshore Order Limits change report consultation
Other
Size: 5 MB
Norfolk Boreas Limited
5.1.27.7 Consultation Report Appendix 27.07 - Offshore Order Limits change report
Other
Size: 3 MB
Norfolk Boreas Limited
5.1.23.2 Consultation Report Appendix 23.02 - Copies of section 47 and 48 notices in relevant publications
Other
Size: 713 KB
Norfolk Boreas Limited
5.1.22.18 Consultation Report Appendix 22.18 - Hearing Your Views IV covering email
Other
Size: 80 KB
Norfolk Boreas Limited
5.1.27.5 Consultation Report Appendix 27.05 - Project update design update v2 (confidential holding page)
Other
Size: 837 KB
Norfolk Boreas Limited
5.1.21.17 Consultation Report Appendix 21.17 - Letter to Oranje Nassau Energie
Other
Size: 768 KB
Norfolk Boreas Limited
5.1.21.15 Consultation Report Appendix 21.15 - Example email to section 42 consultees
Other
Size: 825 KB
Norfolk Boreas Limited
5.1.21.2 Consultation Report Appendix 21.02 - Land referencing questionnaire
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.22.3 Consultation Report Appendix 22.03 - Eastern Daily Press Statement of Community Consultation (SoCC) advert
Other
Size: 9 MB
Norfolk Boreas Limited
5.1.22.1 Consultation Report Appendix 22.01 - Draft Statement of Community Consultation (SoCC), cover letter and list of hard to reach groups to relevant section 43 authorities
Other
Size: 5 MB
Norfolk Boreas Limited
5.1.18.7 Consultation Report Appendix 18.07 - June 2018 newsletter
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.21.14 Consultation Report Appendix 21.14 - Section 42 letter proof of postage
Other
Size: 799 KB
Norfolk Boreas Limited
5.1.21.13 Consultation Report Appendix 21.13 - 26th October 2018 section 42 letter
Other
Size: 808 KB
Norfolk Boreas Limited
5.1.21.5 Consultation Report Appendix 21.05 - 26th October 2018 section 44 letter to land interests
Other
Size: 768 KB
Norfolk Boreas Limited
5.1.21.4 Consultation Report Appendix 21.04 - Land referencing site notice
Other
Size: 781 KB
Norfolk Boreas Limited
5.1.21.3 Consultation Report Appendix 21.03 - Follow-up letter to landowners
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.21.1 Consultation Report Appendix 21.01 - List of prescribed and non-prescribed bodies consulted under section 42
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.22.7 Consultation Report Appendix 22.07 - Refined Primary Consultation Zone mailing area
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.22.5 Consultation Report Appendix 22.05 - Statement of Community Consultation (SoCC) stakeholder mailing list
Other
Size: 756 KB
Norfolk Boreas Limited
5.1.22.6 Consultation Report Appendix 22.06 - Statement of Community Consultation (SoCC) email
Other
Size: 786 KB
Norfolk Boreas Limited
5.1.21.12 Consultation Report Appendix 21.12 - Acknowledgement of receipt of 25th October 2018 notification letter from the Planning Inspectorate
Other
Size: 796 KB
Norfolk Boreas Limited
5.1.21.11 Consultation Report Appendix 21.11 - 25th October 2018 notification letter to the Planning Inspectorate
Other
Size: 774 KB
Norfolk Boreas Limited
5.1.21.10 Consultation Report Appendix 21.10 - 26th April 2019 letter to a newly identified landowner
Other
Size: 8 MB
Norfolk Boreas Limited
5.1.22.4 Consultation Report Appendix 22.04 - Proof of delivery of Statement of Community Consultation (SoCC) to deposit locations
Other
Size: 14 MB
Norfolk Boreas Limited
5.1.22.2 Consultation Report Appendix 22.02 - Statement of Community Consultation (SoCC)
Other
Size: 747 KB
Norfolk Boreas Limited
5.1.21.9 Consultation Report Appendix 21.09 - 9th April 2019 letter to newly identified landowners
Other
Size: 815 KB
Norfolk Boreas Limited
5.1.21.8 Consultation Report Appendix 21.08 - 26th October 2018 section 44 letter to red line boundary change request consultees
Other
Size: 826 KB
Norfolk Boreas Limited
5.1.21.18 Consultation Report Appendix 21.18 - Letter to West Suffolk Council
Other
Size: 796 KB
Norfolk Boreas Limited
5.1.21.16 Consultation Report Appendix 21.16 - Letter to BBL Technical Limited
Other
Size: 814 KB
Norfolk Boreas Limited
5.1.21.7 Consultation Report Appendix 21.07 - 26th October 2018 section 44 letter bespoke route changes
Other
Size: 807 KB
Norfolk Boreas Limited
5.1.21.6 Consultation Report Appendix 21.06 - 26th October 2018 section 44 letter to substation consultees
Other
Size: 2 MB
Norfolk Boreas Limited
5.1.18.6 Consultation Report Appendix 18.06 - Letter to Pettywell residents
Other
Size: 4 MB
Norfolk Boreas Limited
5.1.18.4 Consultation Report Appendix 18.04 - February 2018 newsletter
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.18.2 Consultation Report Appendix 18.02 - October 2017 newsletter
Other
Size: 837 KB
Norfolk Boreas Limited
5.1.13.28 Consultation Report Appendix 13.28 - 15th May 2017 follow-up meeting letter
Other
Size: 797 KB
Norfolk Boreas Limited
5.1.14.2 Consultation Report Appendix 14.02 - Invitation letter to Cable Relay Station workshop
Other
Size: 778 KB
Norfolk Boreas Limited
5.1.16.1 Consultation Report Appendix 16.01 - Example of LLO information submitted to Parish Councils and local education
Other
Size: 824 KB
Norfolk Boreas Limited
5.1.13.30 Consultation Report Appendix 13.30 - 13th July 2017 letter with plans
Other
Size: 944 KB
Norfolk Boreas Limited
5.1.14.5 Consultation Report Appendix 14.05 - Cable Relay Station workshop feedback report
Other
Size: 757 KB
Norfolk Boreas Limited
5.1.14.3 Consultation Report Appendix 14.03 - Cable Relay Station workshop invitee list
Other
Size: 14 MB
Norfolk Boreas Limited
5.1.14.8 Consultation Report Appendix 14.08 - Necton substation workshop presentations
Other
Size: 826 KB
Norfolk Boreas Limited
5.1.18.5 Consultation Report Appendix 18.05 - 22 February 2018 LLO email to town and parish councils
Other
Size: 15 MB
Norfolk Boreas Limited
5.1.18.3 Consultation Report Appendix 18.03 - Phase III non-statutory public exhibition materials
Other
Size: 839 KB
Norfolk Boreas Limited
5.1.13.27 Consultation Report Appendix 13.27 - 28th March meeting request letter
Other
Size: 819 KB
Norfolk Boreas Limited
5.1.14.6 Consultation Report Appendix 14.06 - Invitation letter to Necton substation workshop
Other
Size: 13 MB
Norfolk Boreas Limited
5.1.14.4 Consultation Report Appendix 14.04 - Cable Relay Station workshop presentations
Other
Size: 1 MB
Norfolk Boreas Limited
5.1.14.1 Consultation Report Appendix 14.01 - 13 June 2017 newsletter
Other
Size: 815 KB
Norfolk Boreas Limited
5.1.13.29 Consultation Report Appendix 13.29 - 15th June 2017 letter to landowners
Other
Size: 813 KB
Norfolk Boreas Limited
5.1.13.26 Consultation Report Appendix 13.26 - 24th March 2017 RFI follow-up letter
Other
Size: 4 MB