A47 Blofield to North Burlingham

This page sets out the timetable for the examination of the application. It includes the deadlines for submissions to be made to the Planning Inspectorate and the dates of events taking place during the Examination. The Examination Timetable is also set out in an annex to the Rule 8 letter that was sent to Interested Parties at the start of the Examination.

Event DateDescription
 Date Passed
25 May 2021
Procedural Deadline A

Deadline for receipt by the ExA of:
- Written submissions on Examination procedure
- Requests to be heard orally at the Preliminary Meeting Part 1
View the documents received relating to this deadline
 Date Passed
08 June 2021
Preliminary Meeting Part 1
Preliminary Meeting Part 1
 Date Passed
15 June 2021
Procedural Deadline B

Deadline for receipt by the ExA of:
• Written submissions on Examination procedure including responses to matters raised orally in the Preliminary Meeting Part 1
• Requests to be heard orally at the Preliminary Meeting Part 2
View the documents received relating to this deadline
 Date Passed
22 June 2021
Examination Begins
 Date Passed
22 June 2021
Preliminary Meeting Part 2
Preliminary Meeting Part 2 (if required)
 Date Passed
06 July 2021
Deadline 1 (D1)

Deadline for receipt by the ExA of:
- Responses to the ExA’s Written Questions(ExQ1)
- Local Impact Reports (LIR) from Local Authorities
- Comments on Relevant Representations
- Further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010 (‘the Examination Rules’)
- Notification by Statutory Parties of their wish to be considered as an Interested Party (IP)
- Notification of wish to speak at an Open Floor Hearing
- Notification of wish to speak at a Compulsory Acquisition Hearing
- Notification of wish to attend an Accompanied Site Inspection (ASI)
- Provision by IPs of suggested locations and justifications for ASI

Applicant to provide:
- Statements of Common Ground (SoCG) requested by the ExA
- Statement of Commonality for SoCG
- The Compulsory Acquisition Schedule
- An Application Documents Tracker
- An updated version of the draft Development Consent Order (dDCO) in clean and tracked versions
- A schedule of changes to the dDCO
View the documents received relating to this deadline
 Date Passed
20 July 2021
Deadline 2 (D2)

Deadline for receipt by the ExA of:
- Comments on documents submitted at D1
- Written Representations (WRs) including summaries of all WRs exceeding 1500 words
- Submission by Applicant of draft ASI arrangements and itinerary
- Any further information requested by the ExA under Rule 17 of the Examination Rules

Applicant to provide:
- Progressed SoCG
- Progressed Statement of Commonality for SoCG
- An updated Compulsory Acquisition Schedule in clean and tracked versions
- An updated Application Documents Tracker in clean and tracked versions
- An updated version of the dDCO in clean and tracked versions
- An updated schedule of changes to the dDCO
View the documents received relating to this deadline
 Date Passed
03 August 2021
Deadline 3 (D3)

Deadline for receipt by the ExA of:
- Comments on responses to ExQ1
- Comments on LIRs
- Comments on WRs
- Comments on documents submitted at D2
- Comments on Applicant’s draft ASI arrangements and itinerary
- Any further information requested by the ExA under Rule 17 of the Examination Rules

Applicant to provide:
- Progressed SoCG
- Progressed Statement of Commonality for SoCG
- An updated Compulsory Acquisition Schedule in clean and tracked versions
- An updated Application Documents Tracker in clean and tracked versions
- An updated version of the dDCO in clean and tracked versions
- An updated schedule of changes to the dDCO.
View the documents received relating to this deadline
 Date Passed
16 August 2021
Open Floor Hearing 1
For any Interested Parties to make representations on the merits of the Proposed Development.
 Date Passed
16 August 2021
Open Floor Hearing 2
For any Interested Parties to make representations on the merits of the Proposed Development.
 Date Passed
17 August 2021
Issue Specific Hearing 1
Issue Specific Hearing dealing with matters relating to the Draft Development Consent Order
 Date Passed
18 August 2021
Compulsory Acquisition Hearing 1 S1
Session 1 dealing with the Applicant’s overall case for Compulsory Acquisition and Temporary Possession
 Date Passed
18 August 2021
Compulsory Acquisition Hearing 1 S2
Session 2 dealing with the site and plot specific issues
 Date Passed
19 August 2021
Issue Specific Hearing 2
Issue Specific Hearing dealing with environmental matters
 Date Passed
20 August 2021
Issue Specific Hearing 3
Issue Specific Hearing dealing with environmental matters
 Date Passed
09 September 2021
Deadline 4 (D4)

Deadline for receipt by the ExA of:
- Written summaries of oral submissions to hearings
- Any post-hearing notes requested at the Hearings
- Comments on documents submitted at D3
- Any further information requested by the ExA under Rule 17 of the Examination Rules

Applicant to provide:
- Progressed SoCG
- Progressed Statement of Commonality for SoCG
- An updated Compulsory Acquisition Schedule in clean and tracked versions
- An updated Application Documents Tracker in clean and tracked versions
- An updated version of the dDCO in clean and tracked versions
- An updated schedule of changes to the dDCO.
View the documents received relating to this deadline
 Date Passed
28 September 2021
Publication by the ExA 1
Publication by the ExA of:

• Further Written Questions (ExQ2) (if required)
• Report on the Implications for European Sites (RIES) (if required)
 Date Passed
05 October 2021
Deadline 4a (D4a)

Deadline for receipt by the ExA of:
- Responses to ExA’s letter relating to the Applicant's request for a change to the application
View the documents received relating to this deadline
 Date Passed
19 October 2021
Deadline 5 (D5)

Deadline for receipt by the ExA of:
- Responses to ExQ2 (if required)
- Comments on RIES (if required)
- Comments on documents submitted at D4 and D4a
- Any further information requested by the ExA under Rule 17 of the Examination Rules

Applicant to provide:
- Progressed SoCG
- Progressed Statement of Commonality for SoCG
- An updated Compulsory Acquisition Schedule in clean and tracked versions
- An updated Application Documents Tracker in clean and tracked versions
- An updated version of the dDCO in clean and tracked versions
- An updated schedule of changes to the dDCO.
View the documents received relating to this deadline
 Date Passed
02 November 2021
Deadline 6 (D6)

Deadline for receipt by the ExA of:
- Comments on responses to ExQ2 (if required)
- Comments on documents submitted at D5
- Any further information requested by the ExA under Rule 17 of the Examination Rules

Applicant to provide:
- Progressed SoCG
- Progressed Statement of Commonality for SoCG
- An updated Compulsory Acquisition Schedule in clean and tracked versions
- An updated Application Documents Tracker in clean and tracked versions
- An updated version of the dDCO in clean and tracked versions
- An updated schedule of changes to the dDCO.
View the documents received relating to this deadline
 Date Passed
09 November 2021
Compulsary Acquisition Hearing 2
Compulsory Acquisition Hearing - Commences at 11:30am
 Date Passed
09 November 2021
Issue Specific Hearing 4
Issue Specific Hearing on the draft Development Consent Order and Environmental Matters - Commences at 02:00pm
 Date Passed
09 November 2021
Open Floor Hearing 3
For any Interested Parties to make representations on the merits of the Proposed Development. Hearing - Commences at 10:00am
 Date Passed
18 November 2021
Deadline 7 (D7)

Deadline for receipt by the ExA of:
- Written summaries of oral submissions to hearings
- Any post-hearing notes requested at the Hearings
- Comments on documents submitted at D6
- Any further information requested by the ExA under Rule 17 of the Examination Rules

Applicant to provide:
- Progressed SoCG
- Progressed Statement of Commonality for SoCG
- An updated Compulsory Acquisition Schedule in clean and tracked versions
- An updated Application Documents Tracker in clean and tracked versions
- An updated version of the dDCO in clean and tracked versions
- An updated schedule of changes to the dDCO.
View the documents received relating to this deadline
 Date Passed
26 November 2021
Publication by the ExA 2
Publication by the ExA of:

• ExA’s preferred dDCO or proposed schedule of changes to the dDCO (if required)
 Date Passed
07 December 2021
Deadline 8 (D8)

Deadline for receipt by the ExA of:
- Comments on ExA’s preferred dDCO or proposed schedule of changes to the dDCO
- Comments on documents submitted at D7
- Any further information requested by the ExA under Rule 17 of the Examination Rules

Applicant to provide:
- Progressed SoCG
- Progressed Statement of Commonality for SoCG
- An updated Compulsory Acquisition Schedule in clean and tracked versions
- An updated Application Documents Tracker in clean and tracked versions
- An updated version of the dDCO in clean and tracked versions
- An updated schedule of changes to the dDCO.
View the documents received relating to this deadline
 Date Passed
15 December 2021
Deadline 9 (D9)

Deadline for receipt by the ExA of:
- Comments on documents submitted at D8
- Any further information requested by the ExA under Rule 17 of the Examination Rules.
- A finalised Application Documents Tracker in clean and tracked versions
- A finalised and validated version of the dDCO in clean and tracked versions
- A finalised schedule of changes to the dDCO

Applicant to provide:
- Finalised SoCG
- Finalised Statement of Commonality for SoCGDeadline 9 (D9)
View the documents received relating to this deadline
 Date Passed
21 December 2021
Deadline 10 (D10)

Deadline for receipt by the ExA of:
- Comments on documents submitted at D9
- Any further information requested by the ExA under Rule 17 of the Examination Rules.
View the documents received relating to this deadline
 Date Passed
22 December 2021
Examination closed