Register of advice

The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

Manston Airport View all advice for this project

19 January 2018
Simon Crow

Enquiry

I understand that, according to the DCO process, RSP should have prepared a Consultation Report to PINS outlining how it took into account the feedback responses from its public consultations held in June and July 2017. Am I correct in my understanding that no such report was prepared?
I have been told by RSP that, following the current January and February 2018 statutory consultations, it now intends to prepare a Consultation Report describing how it has responded to feedback from both the 2017 and 2018 consultations.
Would you not agree that that is less than satisfactory? Surely PINS should have received, and the public would rightly expect, the report from the 2017 consultations before a further consultation would take place?

Advice given

The Applicant will be required to submit a Consultation Report with its application for development consent. The Consultation Report is not an iterative document and applicants are not required to produce a separate Report for each round of consultation that they undertake. The Planning Inspectorate cannot test the adequacy of an applicant’s Pre-application consultation until an application (including the Consultation Report) is formally submitted to it.
Notwithstanding the explicit statutory duties places on applicants in respect of their Pre-application consultation (under the Planning Act 2008), the Planning Inspectorate’s Advice Note 14 summarises the purpose and gives advice about the expected format and content of the Consultation Report: attachment 1
For more information and advice about the community consultation process, please see our FAQ: attachment 2


attachment 2
attachment 2
attachment 1
attachment 1