Register of advice

The list below is a record of advice the Planning Inspectorate has provided in respect of the Planning Act 2008 process.

There is a statutory duty under section 51 of the Planning Act 2008 to record the advice that is given in relation to an application or a potential application and to make this publicly available. Advice we have provided is recorded below together with the name of the person or organisation who asked for the advice and the project it relates to. The privacy of any other personal information will be protected in accordance with our Information Charter which you should view before sending information to the Planning Inspectorate.

Note that after a project page has been created for a particular application, any advice provided that relates to it will also be published under the ‘s51 advice’ tab on the relevant project page.

Advice given between between 1 October 2009 and 14 April 2015 has been archived. View the archived advice.

Enquiry received via email

Wrexham Energy Centre View all advice for this project

10 May 2018
Jonathan Dean

Enquiry

I have failed to find any details on how the power station will export the power - was this aspect a separate DCO? If so, which one? If not, please could you signpost me to the details?

Advice given

The Applicant’s Planning Statement states at S.7 that the electrical connection is not part of the application. The Examining Authority's report explains that the ‘Proposed Development requires an electrical connection to the distribution network for export. However as this would be provided underground and pursuant to permitted development powers held by the distribution network operator, the DCO includes no provisions in respect of this connection.’ Further information can be found in the Applicant’s Grid Connection Statement and subsequent revision.