The selection shows documents received from the applicant in relation to the development consent order application.

SourceDescription
Other
3.2 - Statement of Reasons - Revision 2 - Changes from Submission - Track Change Version (PDF, 788 KB)
Post-submission changes to '3.2 Statement of Reasons' (supersedes the application document received on 24 November 2014).
Other
Site Notice Order Plan (PDF, 7 MB)
Post-submission changes. Additional submission of Order Plan (the FDO) that was used to accompany the site notices.
Other
Drax Power Station Diversion Order 2014 (Confirmed) (PDF, 1 MB)
Post-submission changes. Additional Submission received of the Long Drax, Diversion Order (the FDO), dated 13 February 2015.
Other
2.2 - Explanatory Memorandum - Revision 2 - Changes from Submission - Track Change Version (PDF, 582 KB)
Post-submission changes to ?2.2 Explanatory Memorandum' (supersedes the application document received on 24 November 2014).
Other
1.3 - Application Index - Revision 2 (PDF, 502 KB)
Post-submission changes to 'Application Index 1.3' (supercedes the application document received on 24 November 2014).
Other
4.1 - Capture Power Limited - Site Location Plan - Revision v4 (PDF, 5 MB)
Post-submission changes to ?4.1 Site Location Plan' (supersedes the application document received on 24 November 2014).
Other
4.4 - Capture Power Limited - Access and Rights of Way Plans (Key Plan and Sheets 1 - 4) - Revision v4 (PDF, 3 MB)
Post-submission changes to '4.4 Access and Rights of Way Plans (Key Plan and Sheets 1 - 4)? (supersedes the application document received on 24 November 2014).
Other
4.2 - Capture Power Limited - Land Plan (Key Plan and sheets 1 - 4) - Revision v4 (PDF, 3 MB)
Post-submission changes to '4.2 Land Plan (Key Plan and Sheets 1 - 4)? (supersedes the application document received on 24 November 2014).
Other
2.1 - Draft Development Consent Order - Revision 2 - Changes from Submission - Track Change Version (PDF, 490 KB)
Post-submission changes to ?2.1 Draft Development Consent Order' (supersedes the application document received on 24 November 2014).
Other
6.3.7i - ES - Traffic Sensitivity Test (PDF, 841 KB)
Post-submission changes. New document (13 April 2015 - Revision 1).
Other
5.2 - Grid Connection Statement - Revision 2 - Changes from Submission - Track Change Version (PDF, 1 MB)
Post-submission changes to ?5.2 Grid Connection Statement? (supersedes the application document received on 24 November 2014).
Other
3.1 - Book of Reference - Revision 4 (PDF, 45 KB)
Post-submission changes to ?3.1 Book of Reference? (supersedes the application document received on 24 November 2014).
Other
4.8 - Capture Power Limited - Indicative Route of Electrical Connection for 400 kV Plan (PDF, 955 KB)
Post-submission changes to '4.8 Indicative Electrical Connection Routes (Work No. 4)? (one sheet replacing Sheets 1 ? 3 originally submitted) (supersedes the application document received on 24 November 2014).
Other
Capture Power Ltd (PDF, 264 KB)
Post-submission changes. Letter to the Planning Inspectorate regarding amendments to the DCO application and updates to the application documents.
Other
ES Volume 2 Chapter H - LVIA Revision 05.2 (PDF, 167 MB)
Post-submission changes to 6.3.12 ES Volume 2 Chapter H - LVIA Technical Report (addition of Figure H 4.5) (supersedes the application document received on 24 November 2014).
Other
4.3 - Capture Power Limited - Works Plan (Key Plan and sheets 1 - 4) - Revision v4 (PDF, 4 MB)
Post-submission changes to '4.3 Works Plan (Key Plan and Sheets 1 - 4)? (supersedes the application document received on 24 November 2014).
Other
5.2 - Grid Connection Statement - Revision 2 - Changes from Submission - Clean Version (PDF, 1 MB)
Post-submission changes to ?5.2 Grid Connection Statement? (supersedes the application document received on 24 November 2014).