North Killingholme Power Project

What happens next

A decision on the application for a Development Consent Order for North Killingholme Power Project was taken on 11 September 2014.

Timeline (13 items)

A Decision Letter (PDF, 417KB) and Amendment Order (PDF, 360KB) have been issued by the Department for Business, Energy and Industrial Strategy to make a non-material change to the North Killingholme (Generating Station) Order 2014.

17 September 2021
28 September 2020

An application for a non-material change to the North Killingholme (Generating Station) Order 2014 has been made by C.GEN Killingholme Ltd. If you wish to make a representation this should be emailed to [email protected]. The deadline for receipt of representations is 23.59 on Friday 25 September 2020.

13 August 2020

The examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

28 October 2019
Decision made by the Secretary of State
11 September 2014
Recommendations given by the Planning Inspectorate
11 June 2014
  • Preliminary Meeting takes place
  • Examination begins
11 September 2013
Relevant representations published on the website
27 June 2013
Registration of interested parties closes
21 June 2013
Registration of interested parties begins
09 May 2013
Decision on whether or not to accept the application for examination
19 April 2013
Application received by the Planning Inspectorate
25 March 2013