Clocaenog Forest Wind Farm

Enquiry received via email

Clocaenog Forest Wind Farm

25 June 2013
Laura Savage

Enquiry

I unfortunately missed the date to register interest in the Clocaenog wind farm, is this something I can do retrospectively?

Advice given

The deadline to register as an interested party for the Clocaenog Forest Wind Farm application passed on 12 June 2013. Unfortunately we now have no discretion to register you retrospectively.
You may attend the Preliminary Meeting if you wish, as well as any other public hearings that may be held during the Examination.
The arrangements of all the public hearings and meetings will be published on the Clocaenog project webpage in due course, at the following link:
attachment 1
I recommend keeping up to date with the application by checking the project webpage above. We will publish the Examination timetable with the deadlines set by the ExA, as well as all submitted representations and documents during the Examination. If you were to submit a representation during the Examination period, the Examining Authority (ExA) would have the discretion to accept it and take it into consideration.