Wheelabrator Harewood Waste-to-Energy Facility

The list below includes a record of advice we have provided for this project. For a list of all advice issued by the Planning Inspectorate, including non-project related advice, please go to the Register of advice page.

There is a statutory duty, under section 51 of the Planning Act 2008, to record the advice that is given in relation to an application or a potential application, including the name of the person who requested the advice, and to make this publicly available.

Preview
Enquiry received via meeting
response has attachments
Project Update Meeting
Please see attached

29 July 2019
WTI/EFW Holdings Limited - anon.
Enquiry received via email
response has attachments
I wish to object to the following project, could you please help me as how I can do this
Thank you for contacting the Planning Inspectorate regarding the Wheelabrator Harewood Waste to Energy Facility.

The application has not yet been submitted to the Planning Inspectorate for examination and as such we don’t hold any jurisdiction over it.

Please, at this stage, make your views available to the developer whose details are on the letter you enclosed with your email dated 14 March 2019.

If the application is accepted by the Planning Inspectorate for examination, the public will be able to register with the Planning Inspectorate and provide a summary of their views of the application in writing by submitting a ‘Relevant Representation’ in order to inform the Examining Authority.

Advice Note 8 on the Planning Inspectorate’s website provides an overview of the nationally significant infrastructure planning process for members of the public. The Advice Note can be accessed following the below link:
[attachment 1]

20 March 2019
Michael Prydderch
Enquiry received via meeting
response has attachments
Project Update Meeting
Please see attached

09 July 2018
Wheelabrator Technologies Inc - anon.