Keuper Gas Storage Project

You can filter the results to show only the items that match your interest.

Documents Published By Stage

Pre Application (4)

Developer's Application (210)

Acceptance (9)

Pre Examination (6)

Examination (191)

Decision (5)

Decided (39)

Date

The selection shows documents received from the applicant in relation to the development consent order application.

SourceDescription
Other
2.5.5 KGSP Plan 234 B2 (PDF, 506 KB)
Site layout plan showing the preferred layout of the buildings and structures at Lostock Works. Post-submission change to ?2.5.5 KGSP Plan 234 B1? (supersedes the application document received on 24 November 2015)
Other
5.4 KGSP HRA Revised (PDF, 6 MB)
Habitats Regulation Screening Assessment. Post-submission change to ?5.4 KGSP HRA? (supersedes the application document received on 24 November 2015)
Other
2.6.1 KGSP Plan 270 B2 (PDF, 386 KB)
Plan showing elevations for buildings and structures on Gas Processing Plant (GPP). Post-submission change to ?2.6.1 KGSP Plan 270 B1? (supersedes the application document received on 24 November 2015)
Other
2.3.9 KGSP Plan 510 B2 (PDF, 389 KB)
Works plan showing proposed location. Post-submission change to ?2.3.9 KGSP Plan 510 B1? (supersedes the application document received on 24 November 2015)
Other
2.6.2 KGSP Plan 271 B2 (PDF, 461 KB)
Plan showing elevations for buildings and structures on Solution Mining Compound (SMC3). Post-submission change to ?2.6.2 KGSP Plan 271 B1? (supersedes the application document received on 24 November 2015)
Other
4.3 KGSP Book of Reference Rev 1 - Track Changes (PDF, 33 KB)
Book of Reference (Rev 1) showing Tracked changes against application version received on 24 November 2015
Other
3.1 KGSP Draft DCO Rev 1 (PDF, 505 KB)
Draft Development Consent Order. Post-submission change to ?3.1 KGSP Draft DCO? (supersedes the application document received on 24 November 2015)
Other
2.6.4 KGSP Plan 273 B2 (PDF, 414 KB)
Plan showing elevations for buildings and structures of 132kV to 33kV Substation. Post-submission change to ?2.6.4 KGSP Plan 273 B1? (supersedes the application document received on 24 November 2015)
Other
4.3 KGSP Book of Reference Rev 1 (PDF, 33 KB)
Revised Book of Reference: Compulsory Acquisition Information outlining the land over which compulsory acquisition powers will be exercised
Other
3.1 KGSP Draft DCO Rev 1 - Track Changes (PDF, 565 KB)
Draft Development Consent Order (Rev 1) showing Tracked changes against application version received on 24 November 2015
Other
KGSP PINS S51 Response Annex 1 Equipment Description Tables (PDF, 77 KB)
DAS: Annex 1 - Equipment Description Tables Revised Annex 1 from the Design and Access Statement (this annex also appears in Post-submission change document '8.3 KGSP DAS - Revised')
Other
3.3 KGSP DCO Change Log (PDF, 395 KB)
Consolidated list of all proposed and discussed changes to the submission version of the draft DCO
Other
KGSP PINS S51 Response Annex 4 ES Technical Annex Groundsure (PDF, 158 MB)
Doc Ref 6.2 (Geology Annex A) ? Environmental Statement Technical Annexes Geology Annex A ? Groundsure Report
Other
KGSP PINS S51 Response Annex 5 ES Table 14.1 (Revised) (PDF, 58 KB)
6.1 - Environmental Statement - Chapter 14 ? Landscape and Visual Revised Table 14.1 (Page 14-2) - Post-submission change (supersedes table 14.1 in '6.1 KGSP ES' received on 24 November 2015)
Other
2.8.5 KGSP Plan 277 B2 (PDF, 521 KB)
Plan showing general arrangement of Solution Mining Compound (SMC3). Post-submission change to ?2.8.5 KGSP Plan 277 B1? (supersedes the application document received on 24 November 2015)
Other
8.3 KGSP DAS - Revised (PDF, 35 MB)
Revised Design and Access Statement - to explain the design and access principles and objectives for the development
Other
Keuper Gas Storage Limited (PDF, 188 KB)
Letter enclosing non-material amendments to the DCO application documents, following Section 51 advice from The Planning Inspectorate