Riverside Energy Park

What happens next

Dates for the Examination can be viewed on the Examination Timetable page.

Notice of the Procedural Decision has been issued by the Examining Authority to Interested Parties in the Rule 8 letter; this includes information about how the Examination will be conducted and the Examination Timetable as currently set out.

10/10/2019 - Deadline for close of examination. See the Examination Timetable for further information.

If you have a legal interest in land affected by a Nationally Significant Infrastructure Project and:

  • have not been identified by the Applicant; and
  • did not register to become an Interested Party;

then you can make a request to the Examining Authority to become an Interested Party under s102A of the Planning Act 2008.

Timeline (11 items)

milestone icon Read the letter

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties

Procedural decision following Preliminary Meeting

17 April 2019
notice icon

The Audio Recordings for the Preliminary Meeting and the note of the meeting held on 10 April 2019 have been published.

16 April 2019
milestone icon
  • Preliminary Meeting takes place
  • Examination begins
10 April 2019
milestone icon

The notification of Preliminary Meeting (Rule 6 letter) has been sent Read the letter

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

13 March 2019
milestone icon
Relevant representations published on the website
18 February 2019
milestone icon
Registration of interested parties closes
12 February 2019
milestone icon Read the letter

The application has been accepted for examination

19 December 2018
milestone icon
Registration of interested parties begins
19 December 2018
milestone icon
Decision on whether or not to accept the application for examination
14 December 2018
notice icon

This application was received by the Planning Inspectorate on 16 November 2018.

The application documents will be made available if the application is accepted for examination.

It is for the applicant to decide whether or not application documents can be published upon submission (see MHCLG guidance on the pre-application process for major infrastructure projects)

21 November 2018
milestone icon
Application received by the Planning Inspectorate
16 November 2018