The Sizewell C Project

The views expressed in this page do not represent those of the Planning Inspectorate. This page consists of content submitted to the Planning Inspectorate by the public and other interested parties, giving their views of this proposal.

The Sizewell C Project

Received 17 September 2020
From The Coal Authority

Representation

The Coal Authority were notified by NNB Nuclear Generation (SZC) Limited (letter dated 03 July 2020) that an application for a Development Consent Order has been made to the Planning Inspectorate. I have checked the application boundary (Figure 1.1.1 - Main Development Site and Off-Site Associated Development Sites Location Plan) against our coal mining information and can confirm that all development areas fall outside the defined coalfield. Accordingly, the Coal Authority has no comments or observations to make on this project.