Mae’r dudalen hon yn gosod allan yr amserlen ar gyfer archwilio’r cais. Mae’n cynnwys y terfynau amser ar gyfer gwneud cyflwyniadau i’r Arolygiaeth Gynllunio a dyddiadau digwyddiadau a gynhelir yn ystod yr Archwiliad. Yn ogystal, mae Amserlen yr Archwiliad wedi’i gosod allan yn yr atodiad i’r llythyr rheol 8 a anfonwyd at Bartïon â Buddiant ar ddechrau’r Archwiliad.

Dyddiad digwyddiadDisgrifiad
 Date Passed
25/05/2016
Unaccompanied Site Inspection
Unaccompanied Site Inspection
 Date Passed
19/07/2016
Archwiliad yn dechrau
 Date Passed
19/07/2016
First Issue Specific Hearing
Issue Specific Hearing on the Draft Development Consent Order
 Date Passed
02/08/2016
Rule 8 letter
Issue by ExA of:

• Examination timetable

• ExA’s first written questions
 Date Passed
23/08/2016
Deadline 1

Deadline for receipt by ExA of:

• Summaries of all relevant representations (RR) exceeding 1500 words

• Comments by the applicant and any other interested parties on RRs

• Written representations (WRs) by all interested parties

All parties must submit their full written case and supporting evidence at this stage, as any representations to be heard at a hearing need to be based on RRs or WRs

• Summaries of all WRs exceeding 1500 words

• Responses to ExA’s first written questions

• Local Impact Reports (LIR) from local authorities

• Statements of Common Ground (SoCG) requested by ExA

• Notification by statutory parties of wish to be considered as an interested party

• Notification by persons within certain categories of interests in land of their wish to become an interested party

• Notification by interested parties of their wish to speak at an issue specific hearing on the DCO

• Notification by affected persons of their wish to speak at a compulsory acquisition hearing

• Notification by interested parties of their wish to speak at an open floor hearing

• Submissions from interested parties or affected persons recommending locations or items for the itinerary for an accompanied site inspection and reasons for their inclusion

• Any further information requested by the ExA for this deadline

View the documents received relating to this deadline
 Date Passed
06/09/2016
Notifcation of Hearings and ASV
Issue by ExA of notification of date, time and place for further hearings and accompanied site inspection(s) at timetable items 7, 8 and 9 (if required)

A banner on the Wrexham Energy Centre Project webpage will be updated on this day to detail the arrangements made. If accompanied sites inspections are not required, the banner will note this. PINS case team will contact the applicant by 2 September 2016 to ensure that press notices meet the local newspaper deadline.
 Date Passed
20/09/2016
Deadline 2

Deadline for receipt by the ExA of:

• Comments on WRs and any responses to comments on RRs

• Comments on LIR

• Comments on responses to ExA’s first written questions

• Any further information requested by the ExA for this deadline

View the documents received relating to this deadline
 Date Passed
27/09/2016
Accompanied Site Inspection (ASI)
Date reserved for:

• Accompanied site inspection
 Date Passed
28/09/2016
Issue Specific Hearing and Open Floor Hearing
Date reserved for:

• Issue Specific Hearing - The draft DCO, environmental and other issues

• Open-floor Hearing if requested
(evening)

Agendas for each hearing will be published on the project page of our website seven calendar days before the hearing is due to take place but will not otherwise be published or circulated. The actual agenda on the day of each hearing is subject to change at the discretion of the ExA.
 Date Passed
29/09/2016
Compulsory Acquisition Hearing and Issue Specific hearing
Date reserved for:

• Compulsory Acquisition Hearing - Compulsory Acquisition and Temporary Possession proposals

• Issue Specific Hearing -environmental and other issues

Agendas for each hearing will be published on the project page of our website seven calendar days before the hearing is due to take place but will not otherwise be published or circulated. The actual agenda on the day of each hearing is subject to change at the discretion of the ExA.
 Date Passed
06/10/2016
Deadline 3

Deadline for receipt of:

• Written summaries of oral submissions put at any hearings held between 27 and 29 September 2016

• Comments on any other documents submitted at Deadline 2 and not previously responded to

• Applicant’s revised draft DCO responding to matters and issues arising at hearings

• Any further information requested by the ExA for this deadline

View the documents received relating to this deadline
 Date Passed
21/10/2016
ExA Second Written Questions
Issue by ExA of:

• Second written questions (if required)

A banner on the Wrexham Energy Centre Project webpage will be updated on this day to detail the documents published. If second questions are not required the banner will be updated to note this.
 Date Passed
31/10/2016
Issue by ExA of notification of date, time and place for any further hearings and accompanied site inspections(s) (
Issue by ExA of notification of date, time and place for any further hearings and accompanied site inspections(s) (if required)

A banner on the Wrexham Energy Centre Project webpage will be updated on this day to detail the arrangements made. PINS case team will contact the applicant by 28 October 2016 to ensure that press notices meet the local newspaper deadline. If further hearings and / or accompanied sites inspections are not required, the banner will note this.
 Date Passed
04/11/2016
Deadline 4

Deadline for receipt of:

• Responses to ExA’s second written questions

• Any further information requested by the ExA for this deadline

View the documents received relating to this deadline
 Date Passed
22/11/2016
Accompanied Site Inspection
Dates reserved for:

• Any further accompanied site inspections
 Date Passed
23/11/2016
Issue Specific Hearing into Environmental and Other Issues
Dates reserved for:

• Issue Specific Hearing into Environmental and Other Issues


Agendas for each hearing will be published on the project page of our website seven calendar days before the hearing is due to take place but will not otherwise be published or circulated. The actual agenda on the day of each hearing is subject to change at the discretion of the ExA
 Date Passed
24/11/2016
Compulsory Acquisition Hearing
Dates reserved for:

• Compulsory Acquisition Hearing

Agendas for each hearing will be published on the project page of our website seven calendar days before the hearing is due to take place but will not otherwise be published or circulated. The actual agenda on the day of each hearing is subject to change at the discretion of the ExA
 Date Passed
24/11/2016
Issue Specific Hearing into the draft Development Consent Order
Dates reserved for:

• Issue Specific Hearing into the draft Development Consent Order


Agendas for each hearing will be published on the project page of our website seven calendar days before the hearing is due to take place but will not otherwise be published or circulated. The actual agenda on the day of each hearing is subject to change at the discretion of the ExA
 Date Passed
25/11/2016
Deadline 5

Deadline for receipt of:

• Comments on responses to ExA’s second written questions
• Any further information requested by the ExA for this deadline

View the documents received relating to this deadline
 Date Passed
02/12/2016
Deadline 6

Deadline for receipt of:

• Written summaries of oral submissions put at any hearings held between 22 and 24 November 2016

• Comments on any other documents submitted at Deadline 5

• A final preferred draft DCO from the applicant

• A final progress summary from the applicant on any commercial agreements or related instruments necessary to support the DCO

• Any further information requested by the ExA for this deadline.

View the documents received relating to this deadline
 Date Passed
12/12/2016
Publication
Publication by the ExA of:

• Report on Implications for European Sites (RIES) (if required)

• ExA consultation draft and/or commentary on the final DCO

• Any further requests for information by the ExA (if required)

A banner on the Wrexham Energy Centre Project webpage will be updated on this day to detail the documents to be published.
 Date Passed
04/01/2017
Deadline 7

Deadline for receipt of:

• Comments on the ExA’s RIES (if required because a RIES is published)

• Comments on the ExA’s consultation draft and/or commentary on the DCO

• Any further information requested by the ExA for this deadline

View the documents received relating to this deadline
 Date Passed
09/01/2017
ExA's request for further information
Issue by the ExA of questions seeking further information and written comments.
 Date Passed
12/01/2017
Deadline 8

Deadline for receipt of:

• Comments on responses to the RIES (if required because a RIES is published)

• Comments on responses to the ExA’s consultation draft and/or commentary on the DCO

• Any further information requested by the ExA for this deadline

• Responses to the ExA's request for further information issued on 9 January 2017.
View the documents received relating to this deadline
 Date Passed
17/01/2017
Deadline 9

Deadline for the receipt of

• Comments on responses to the ExA’s requests for further information as issued on 9 January 2017
View the documents received relating to this deadline
 Date Passed
19/01/2017
Close of Examination
Deadline for the Close of Examination
 Date Passed
19/01/2017
Archwiliad wedi cau