Internal Power Generation Enhancement for Port Talbot Steelworks

Mae’r dudalen hon yn gosod allan yr amserlen ar gyfer archwilio’r cais. Mae’n cynnwys y terfynau amser ar gyfer gwneud cyflwyniadau i’r Arolygiaeth Gynllunio a dyddiadau digwyddiadau a gynhelir yn ystod yr Archwiliad. Yn ogystal, mae Amserlen yr Archwiliad wedi’i gosod allan yn yr atodiad i’r llythyr rheol 8 a anfonwyd at Bartïon â Buddiant ar ddechrau’r Archwiliad.

Dyddiad digwyddiadDisgrifiad
 Date Passed
10/12/2014
Archwiliad yn dechrau
 Date Passed
15/01/2015
Deadline 1

Deadline for the receipt by the ExA of:
Submissions
• Statements of Common Ground (SoCG) requested by the ExA – see Annex G
• Habitat Regulations Assessment (HRA) matrices from the applicant
• Local impact reports (LIR) from any local authorities (see s60 of the Planning Act 2008)
• Responses to the ExA’s first written questions
• Comments on relevant representations (RRs)
• Summaries of all RRs exceeding 1500 words
• Written representations (WRs) by all interested parties
• Summaries of all WRs exceeding 1500 words
• Comments on any additional representations and submissions received prior to the examination
• Submissions from interested parties recommending itinerary items for the accompanied site visit
• Any further information requested by the ExA for this deadline

Notifications

• Notification by interested parties of wish to be heard at an open floor hearing
• Notification of wish to be heard at a compulsory acquisition hearing
• Notification by interested parties of wish to make oral representations at any issue specific hearing, including those on the draft Development Consent Order (DCO), environmental matters (including Environmental Impact Assessment (EIA) and Habitats Regulations Assessment (HRA)
• Notification by interested parties of their intention to attend the accompanied site visit
• Notification by statutory parties of wish to be considered as an interested party

View the documents received relating to this deadline
 Date Passed
19/01/2015
Notification by the ExA of date, time and place for;
• Any Accompanied site visit
• Open Floor Hearing
• Compulsory Acquisition Hearing
• Any other issue specific hearing
 Date Passed
05/02/2015
Deadline 2
Deadline for the receipt by the ExA of:
• Responses to comments on RRs
• Comments on LIRs
• Responses to comments on any additional representations and submissions received prior to the examination
• Comments on responses to the ExA’s first written questions
• Comments on WRs
• Any revised draft DCO from applicant
• Any further information requested by the ExA for this deadline

View the documents received relating to this deadline
 Date Passed
12/02/2015
Date for the Issue specific hearing on the draft DCO
View the documents received relating to this deadline
 Date Passed
12/02/2015
Issue Specific Hearing 1
?
 Date Passed
17/02/2015
Deadline 3
Deadline for the receipt by the ExA of:
• Responses to comments on WRs
• Written summary of the oral case put at the draft DCO hearing
• Any documents/ information/amendments requested by the ExA

View the documents received relating to this deadline
 Date Passed
24/02/2015
Date reserved for the
• Accompanied Site Visit
• Open Floor Hearing (evening)

View the documents received relating to this deadline
 Date Passed
24/02/2015
Open Floor Hearing
Open Floor Hearing
 Date Passed
24/02/2015
Site Visit (Accompanied)
Accompanied Site Visit
 Date Passed
25/02/2015
Date reserved for the;
• Compulsory Acquisition hearing
• Issue specific hearing on environmental matters (including EIA and HRA)

View the documents received relating to this deadline
 Date Passed
25/02/2015
Compulsory Acquisition Hearing
?
 Date Passed
25/02/2015
Issue Specific Hearing 2
Hearing on Environmental Matters
 Date Passed
26/02/2015
Date reserved if required, for the ;
• continuation of issue specific hearing on environmental matters (including EIA and HRA)
 Date Passed
05/03/2015
Deadline 4
Deadline for the receipt by the ExA of:
• Written summaries of oral cases put at any issue specific hearings
• Any updated SoCG
• Any documents/information/amendments requested by the ExA for this deadline
• Applicant’s final preferred draft DCO

View the documents received relating to this deadline
 Date Passed
19/03/2015
Deadline 5
Deadline for the receipt by the ExA of:
• Comments on applicant’s final preferred draft DCO
• Any further information requested by the ExA for this deadline

Notification by the ExA of date, time and place for;
• Any additional hearings

View the documents received relating to this deadline
 Date Passed
26/03/2015
Issue by the ExA of;
• the Report on Implications for European Sites (RIES)
• ExA’s second written questions, if required
 Date Passed
14/04/2015
Dates reserved for any additional hearings
 Date Passed
15/04/2015
Dates reserved for any additional hearings
 Date Passed
15/04/2015
Issue Specific Hearing 3
Issue Specific Hearing on Outstanding Issues and Open Floor Hearing
 Date Passed
16/04/2015
Dates reserved for any additional hearings
 Date Passed
23/04/2015
Deadline 6
Deadline for receipt of:
• Comments on REIS
• Responses to the ExA’s second written questions
• Written summaries of oral cases put at the hearings of 14-16 April (if held)
• Responses to comments on Applicant’s final preferred draft DCO
• Any documents/information/amendments requested by the ExA for this deadline

View the documents received relating to this deadline
 Date Passed
11/05/2015
Deadline 7
Deadline for receipt of:
• Comments on responses to the ExA’s second written questions

View the documents received relating to this deadline
 Date Passed
09/06/2015
Close of examination
 Date Passed
09/06/2015
Archwiliad wedi cau