Mae’r dudalen hon yn gosod allan yr amserlen ar gyfer archwilio’r cais. Mae’n cynnwys y terfynau amser ar gyfer gwneud cyflwyniadau i’r Arolygiaeth Gynllunio a dyddiadau digwyddiadau a gynhelir yn ystod yr Archwiliad. Yn ogystal, mae Amserlen yr Archwiliad wedi’i gosod allan yn yr atodiad i’r llythyr rheol 8 a anfonwyd at Bartïon â Buddiant ar ddechrau’r Archwiliad.
Dyddiad digwyddiad | Disgrifiad |
---|---|
![]() | Archwiliad yn dechrau |
![]() | Issue by ExA of: · Examination timetable · ExA’s written questions (on website) View the documents received relating to this deadline |
![]() | Deadline 1 Deadline for receipt of: · Comments on relevant representations · Written representations (WRs) by all interested parties · Local Impact Reports from any local authorities · Statements of Common Ground requested by the ExA · Responses to ExA’s written questions · Comments by interested parties in respect of the July 2015 submissions by the applicant in response to the s55 Checklist. · Notification of wish to make oral representations at the issue specific hearings · Notification of wish to speak at an open floor hearing · Notification of wish to speak at a compulsory acquisition hearing · Notification of wish to attend the accompanied site inspection, suggested locations and justifications · Notification by statutory parties of wish to be considered an interested party View the documents received relating to this deadline |
![]() | Deadline 2 Deadline for receipt by the ExA of: · Comments on WRs · Comments on Local Impact Reports · Comments on responses to ExA’s written questions · Revised draft DCO from applicant · Schedule of mitigation from the applicant View the documents received relating to this deadline |
![]() | Site Visit (Accompanied) 1 Accompanied site inspection |
![]() | Site Visit (Accompanied) 2 Accompanied site inspection reserve date |
![]() | Open Floor Hearing 1 Open floor hearing evening |
![]() | Compulsory Acquisition Hearing 1 Compulsory acquisition hearing |
![]() | Compulsory Acquisition Hearing 2 Compulsory acquisition hearing |
![]() | Issue Specific Hearing 1 Issue specific hearing 1 |
![]() | Issue Specific Hearing 2 Issue specific hearing 2 |
![]() | Issue Specific Hearing 3 Issue specific hearing 3 |
![]() | Issue Specific Hearing 4 Issue specific hearing on the draft Development Consent Order |
![]() | Deadline 3 Deadline for receipt of: · Post-hearing documents · Applicant’s revised draft DCO · Any further information requested by the ExA View the documents received relating to this deadline |
![]() | Issue by ExA of: · ExA’s second written questions (on website) |
![]() | Deadline 4 Deadline for receipt of: · Further hearing documents · Comments on post-hearing documents View the documents received relating to this deadline |
![]() | Compulsory Acquisition Hearing 3 Reserved hearing dates if required |
![]() | Issue Specific Hearing 5 Reserved hearing dates if required |
![]() | Open Floor Hearing 2 Reserved hearing dates if required |
![]() | Deadline 5 Deadline for receipt of: · Comments on Option B · Comments on the proposed provision for the compulsory acquisition of additional land · Comments on further post-hearing documents View the documents received relating to this deadline |
![]() | Deadline 6 Deadline for receipt of: · Responses to ExA’s second written questions View the documents received relating to this deadline |
![]() | Deadline 7 Deadline for receipt of: · Comments on responses to ExA’s second written questions · Notification of wish to make oral representations at December hearings View the documents received relating to this deadline |
![]() | Deadline 8 Deadline for receipt of: · Written representations regarding the proposed provision for the compulsory acquisition of rights over additional land View the documents received relating to this deadline |
![]() | Issue Specific Hearing 6 Issue specific hearing on the principles of development and environmental issues including (but not limited to) costs and policy, landscape and visual impacts and land use and land management matters regarding Option B and any outstanding matters on Option A regarding principles of development and environmental issues. |
![]() | Open Floor Hearing 3 Open floor hearing |
![]() | Compulsory Acquisition Hearing 4 Compulsory acquisition hearing on the proposed provision for rights and the imposition of restrictions over additional land |
![]() | Compulsory Acquisition Hearing 5 Compulsory acquisition hearing |
![]() | Open Floor Hearing 4 Open floor hearing on the proposed provision for rights and the imposition of restrictions over additional land |
![]() | Issue Specific Hearing 7 Issue specific hearing on the draft Development Consent Order (DCO) for both the Option B draft DCO and any remaining matters in relation to the Option A draft DCO |
![]() | Site Visit (Accompanied) 3 Reserved site inspection date if required |
![]() | Site Visit (Accompanied) 4 Reserve date for accompanied site inspection if required |
![]() | Deadline 9 Deadline for receipt of: · Post-hearing documents · Revised draft DCO from applicant · Comments on written representations regarding the proposed provision for the compulsory acquisition of additional land · Any further information requested by the ExA View the documents received relating to this deadline |
![]() | Publication of Report on the Implications for European Sites (RIES) Deadline 9 Deadline for receipt of: · Post-hearing documents · Revised draft DCO from applicant · Comments on written representations regarding the proposed provision for the compulsory acquisition of additional land · Any further information requested by the ExA View the documents received relating to this deadline |
![]() | Publication of ExA’s consultation draft DCO (if published) |
![]() | Deadline 10 · Comments on ExA’s consultation draft DCO (if required) and RIES · Comments on post-hearing documents · Any further information requested by the ExA View the documents received relating to this deadline |
![]() | Deadline 11 Deadline for receipt of: · Responses to comments on the ExA’s consultation draft DCO (if published) and RIES · Comments on any further information requested by the ExA View the documents received relating to this deadline |
![]() | Archwiliad wedi cau |